HomeMy Public PortalAbout2010 - FY2010 CAMPO Unified Planning Work Program - 4th Qtr Annual ReportFY 2010 CAPITAL AREA METROPOLITAN PLANNING ORGANIZATION UNIFIED PLANNING WORK PROGRAM PROGRESS REPORT i Fourth Quarter/Annual Report NOVEMBER 1, 2009 -OCTOBER 31, 2010 The preparation of this report was financed in part by the U.S. Department of Transportation, Federal Highway Administration, and Federal Transit Administration in cooperation with the Missouri Department of Transportation. The opinions, findings, and conclusions expressed in this report are not necessarily those of the Federal Highway Administration, Federal Transit Administration, or the Missouri Highway and Transportation Department. The FY 2011 Unified Planning Work Program has been approved and adopted by the Capital Area Metropolitan Planning Organization Board of Directors at the regularly scheduled meeting of August 18, 2010. Minutes of the meeting are on file at the Department of Community Development/Planning Division - Room 120, John CI Christy Municipal Building, 320 East McCarty, Jefferson City, Missouri 65101. MPO Administration is provided by the City of Jefferson, Missouri Department of Community Development/Planning Division Room 120 John G. Christy Municipal Building 320 East McCarty Jefferson City, Missouri Telephone 573-634-6410 http://www.ieffcitMo.org/cd/campo/campo.htmi For questions or comments, contact Janice McMillan or Alan Morrison at the Planning Division Table of Contents Administrationand Staff for the MPO................................................................................................................1 Unified Planning Work Program Elements for FY 2010.....................................................................................1 Unified Planning Work Program Work Element Tasks.......................................................................................2 1.0 CAMPO Program Administration and Support .....................................................................................2 1.1 ......Program Support ..........................................................................................................................2 1.2 ......Public Participation......................................................................................................................4 1.3 ......Staff Development.......................................................................................................................5 2.0 General Development and Comprehensive Planning............................................................................6 2.1 ......Data Acquisition and Maintenance..............................................................................................6 3.0 Long Range Transportation Planning....................................................................................................6 4.0 Short Range Transportation Planning....................................................................................................7 4.1 Coordination of Public Transit Human Service Transportation..........................................................7 4.2 ......Bicycle and Pedestrian Planning..................................................................................................8 4.3 ......Goods Movement/Freight Planning.............................................................................................9 4.4 ......Transportation Safety Planning....................................................................................................9 4.5 ......Transportation Security Planning...............................................................................................10 5.0 Transportation Improvement Plan........................................................................................................10 6.0 Public Transportation (Transit) Planning.............................................................................................11 Entries by Ouarter — svmbol and color Q1 = First Quarter Entries — November through January Q2 = Second Quarter entries — February through April Q3 = Third Quarter Entries — May through July Q4 = Fourth Quarter — August through October / Annual 11 Administration and Staff for CAMPO The CAMPO memorandum of understanding identifies the City of Jefferson as having the responsibility for administration of CAMPO, and as such, provides staffing for CAMPO. For FY 2010, the City of Jefferson provides for a Director, a Staff Assistant, and two full time transportation planners. Unified Planning Work Program Elements for FY 2010 The work program for the MPO identifies what the MPO will do to meet the federal transportation planning requirements, affect coordination and cooperation in comprehensive planning for the region, and identify and satisfy the needs and priorities of the MPO membership to the greatest extent possible and consists of work elements that focus on the different components required to accomplish the work program. These work elements are themselves divided into sections that identify the funding used in accomplishing the work element, the activities intended to accomplish those work elements, the agency or organization will perform those activities, an estimated schedule for completing the activity and the resulting products of the activities. The CAMPO UPWP consists of the following work elements: 1. CAMPO Program Administration and Support 2. General Development and Comprehensive Planning 3. Long Range Transportation Planning 4. Short Range Transportation Planning 5. Transportation Improvement Program 6. Transit Planning FY 2010 CAMPO Unified Planning Work Program Progress Report Unified Planning Work Program Work Element Tasks 1.0 CAMPO Program Administration and Support Activities under this work item include direct program support, administration, interagency coordination, citizen participation, public information, local assistance, and program planning. Plans and programs in support of CAMPO include development of the Unified Planning Work Program, the Transportation Improvement Program, the Public Participation Plan, the Limited English Proficiency Plan, and the Metropolitan Transportation Plan. 1.1. Program Support. The staff of CAMPO provides administrative and support functions essential to the success of the metropolitan transportation planning process such as preparation of agendas, minutes, amendments, exhibits for Technical Committee and Board of Directors meetings, and participation in these same meetings, along with occasional special meetings 1.1.1. Responsible Agency: CAMPO staff 1.1.2. Program Activities (Methodology) a) Completion of Title VI and Environmental Justice reports as required Q4 Title VI report submitted to MoDOT in July and September b) Develop the Unified Planning Work Program and budget for the fiscal year Q3 Prepared draft UPWP and budget, distributed for comments, discussed problems with funding agencies with the Board of Directors, revised the draft UPWP to reflect resolution of budget issues Q4 Approved in the 4U' quarter c) Prepare agendas, minutes and materials for CAMPO Board of Directors, the Technical Committee and subcommittee meetings. Provide individual committee requests for information Ql Staff prepared agendas and related materials for Technical Committee meeting in November, and January, and the Board of Directors meetings in November, December, and January. Q2 Staff prepared agendas and related materials for Technical Committee meetings and the Board of Directors meetings in February, March and April and in May, June and July. Q3 Met with St. Martins Board of Aldermen on MPO updates and participation in committees. Sent letter to Lake Mykee, but no response Q4 Bylaws report prepared for the Board of Directors for Bylaw amendment Q4 Three sections in the Bylaws amended in August Q4 UPWP administrative modifications completed Q4 Staff prepared agendas and related materials for Technical Committee and Board of Directors meetings in August, September, and October d) Prepare and submit documents required by state and federal agencies, including UPWP quarterly progress reports and invoices, an updated TIP and UPWP, amendments as needed, and other documents as required Q1 Prepared and submitted the fourth quarter and annual progress report Q1 Four Amendments processed in November, December, and January (see item 5.1.5 c) for details. FY 2010 CAMPO Unified Planning Work Program Progress Report 2 Q3 Prepared and submitted the second quarter progress report Q4 Prepared & submitted 3`d Quarter Progress Report In August e) Produce a List of Obligated Projects from the previous fiscal year Q1 MPO staff requested information from MoDOT on obligated projects and discussed the project with MoDOT Q2 Completed the List of Obligated Projects for the previous fiscal year f) CAMPO, in cooperation with MoDOT is to establish of a policy on how sub -al located STP funds are distributed in the Jefferson City MPA. (TPPR #7), Q1 Informal meetings with staff were done in December, and January g) Develop a Policy and Procedure Guide for more efficient operation of the MPO Q4 Ongoing, monitoring issues that arise in the amendment of bylaws and policies over previous periods h) Develop criteria and process for prioritizing implementation of transportation plan elements for inclusion in the TIP (TPPR #5), Q1 Subcommittee met on January 7 Q2 The prioritization committee met in February, March and April. Proposals were submitted to the Technical Committee. Q3 Completed in July i) Evaluate the usage of the obligated projects list provided by MoDOT for tracking reasonable progress of locally sponsored Federal -aid projects (TPPR #6) Q4 Completed in October 1.1.3. Products (estimated completion dates) a) A CAMPO Policy and Procedure Guide (August, 2010) Q4 Ongoing b) A List of Obligated Projects from the previous year (November, 2009) Q2 Completed c) FY 2009 UPWP Annual Progress Report (November, 2009) Q1 Completed in November d) FY 2010 UPWP Quarterly Progress Report (February, May, and August of 2010) Q2 I" Quarter report completed in May for November, December, and January Q3 2°d Quarter report completed in for February, March, and April Q4 3`d Quarter Progress Report Completed e) FY 2011 Annual Work Program and Budget (September, 2010) Q2 In progress for 2"d quarter Q3 Completed in 3`d quarter Q4 Approved in 4d' quarter f) Title VI Report to FTA (March, 2010) Q4 Completed in March g) Title VI Report to MoDOT ( December, 2009) Q3 Title VI report sent to MoDOT in July and September FY 2010 CAMPO Unified Planning Work Program Progress Report 3 1.2. Public Participation CAMPO establishes a "proactive public involvement process that provides complete information, timely public notice, full public access to key decisions, and supports early and continuing involvement". 1.2.1. Responsible Agency: CAMPO staff 1.2.2. Program Activities a) Provide the public with notice of CAMPO committee meetings, forums, and focus groups Q2 Meeting notices were sent out for Technical Committee and Board of Directors meetings Q3 Web pages were maintained and updated with new and revised documents and announcements throughout the year, notices were sent out for Technical Committee and Board of Directors meetings Q4 Maintained webpages throughout the year, and expanded contents b) Promote public participation techniques to reach out to those traditionally underserved by transportation and those who have not traditionally participated in the planning process Q1 Identified requirements for participation techniques for outreach c) Conduct public participation, public meetings, hearings and workshops, as needed and in accordance with the Public Participation Plan Q 1 The PPP update was initiated in the first quarter with proposals by staff and discussion by the Technical Committee, Board of Directors, and MoDOT Q3 Plan approved in 3rd quarter d) Maintain CAMPO data and files for Title VI, Environmental Justice, and related non- discrimination activities Q4 Ongoing, Title VI reports submitted in July and September e) Improve notice and documentation for opportunities to comment on proposed transportation projects, plans and programs for citizens, affected public agencies, private transportation providers, and other interested parties Q3 The CAMPO website was updated with recent and updated materials throughout this and previous quarters 1.2.3. Products (estimated completion dates) a) CAMPO meeting notices, publications and advertisements (ongoing) Q4 Completed b) Maintain web pages on transportation plans and programs and the data, policies and forecasts that support them (ongoing) Q4 Completed c) Updates to the CAMPO Public Participation Plan if warranted (July 2010) Q4 Completed FY 2010 CAMPO Unified Planning Work Program Progress Report 4 1.3. Staff Development 1.3.1. Responsible Agency: CAMPO staff 1.3.2. Program Activities (Methodology) a) Participate in professional meetings, conferences and workshops in areas related to transportation planning and Metropolitan Planning Organization activities. Q1 MPO staff participated in four AICP web -based seminars for professional certification maintenance and has scheduled regular monthly web -based AICP seminars throughout the year Q2 Staff participated in two AICP web -based seminars for professional certification maintenance Q2 Attended ribbon cutting and groundbreaking events for bike/ped projects in Callaway County Q3 Staff participated in one AICP web -based seminar for professional certification maintenance Q3 Attended a ONEDOT TIGER II information webinar in May and a Census sponsored urbanized area webinar in June Q3 Attended a river corridor freight presentation through the Mid Missouri Regional Planning Commission Q4 Attended an August Wind and Utility Corridor webinar sponsored by APA Q4 Attended planning law webinar in October b) Training in computer applications and technical processes through vendors, NTI, NHI, FHWA, and FTA (for example) Q4 Attended an FHWA Workshop for Public Sector Employees - Applying Analysis Tools in Planning for Operations Q4 Attended the annual state APA conference in Columbia during October c) Seek professional development for incorporating freight into transportation planning Q1 Researching issues Q4 Researched freight data for use in modeling, transportation plans, and attended freight, and rail presentations as available 1.3.3. Products (estimated completion dates) a) Freight planning program (ongoing) Q4 Ongoing FY 2010 CAMPO Unified Planning Work Program Progress Report 5 2.0 General Development and Comprehensive Planning 2.1. Data Acquisition and Maintenance 2.1.1. Responsible Agency: CAMPO staff 2.1.2. Program Activities (Methodology) a) Expand, organize and maintain socioeconomic and demographic databases. Include items such as land use, transportation infrastructure, housing, environmental, and open space Q3 Monitored nearby municipalities for land use and boundary changes affecting the CAMPO area, such as changes in land use and expansion into the CAMPO MPA. b) Maintain data on low-income, elderly, disabled, and minority populations to support environmental justice outreach and analysis c) Coordinate with GIS staff for the production, collection, storage, analysis and presentation of information for CAMPO and public use Q1 CAMPO staff produced the "official zoning map of Jefferson city" by request of the City of Jefferson Q 1 Production of a map and calculations of the mileage of roads maintained by/for Jefferson City Q4 Coordinated calculation processes with, and distributed updated road mileages to member jurisdictions 2.1.3. Products (estimated completion dates) a) Preparation of maps, other graphics, and databases as necessary for CAMPO and local agency use (ongoing) b) Up to date data bases suitable for identifying trends, and conducting analyses, such as demographic and socio economic analyses (ongoing) 3.0 Lony- Range Transportation Planning 3.1.1. Responsible Agency: CAMPO staff 3.1.2. Program Activities (Methodology) a) Process amendments to the MTP to support the region's long-range planning process Q4 Not required in 2010 b) Organize the MTP components (databases, maps, plans, and modeling) for maintenance and updating, (along with transportation data, see land use and socioeconomic information in General Development and Comprehensive Planning) Q4 Initiated an MTP subcommittee to begin the MTP update. Subcommittee met to discuss timeline, reasons for updating plan, regulations and processes, roles and responsibilities, data requirements, and consultant contracts c) Maintain an inventory of multi -modal transportation facilities and services within the metropolitan planning area for transit, rail, river, aviation, freight, and other transportation modes Q4 Data bases updated in 4`h quarter FY 2010 CAMPO Unified Planning Work Program Progress Report 6 d) Develop and maintain traffic count and congestion data Q4 Coordinating with member jurisdictions as part of the MTP update e) Traffic Analysis Zone review, maintenance and update as necessary QI Delayed by Census until Spring of 2011 f)Assist MODOT in maintaining current maps of roadway functional classifications Q1 Functional Classification change were reviewed by MoDOT prior to development of new maps Q2 Distributed final functional classification maps g) Census TAZ update Q1 See 3.1.5 e 3.1.3. Products (estimated completion dates) a) Consolidated CAMPO area transportation databases (July, 2010) b) Cooperative studies and exchanges of information between agencies (on-going) c) Traffic Analysis Zone( TAZ) review (June 2010) Q1 Rescheduled to 2011 d) Travel demand model data update (continuous) e) Census TAZ update (April- July 2010) Q 1 Rescheduled to 2011 4.0 Short Range Transportation Planning 4.1. Coordination of Public Transit Human Service Transportation 4.1.1. Responsible Agency: CAMPO staff. 4.1.2. Program Activities a) Provide assistance to local governments and applicant agencies in developing transitlparatransit projects for inclusion in the Transportation Improvement Program Ql Staff assisted in new route planning and mapping activities, updated route and schedule guide Q1 Gis and mapping for the proposed Renn Addition and Business 50 West route consolidation Q3 Continued to provided maps and analytic support for proposed changes to the JEFFTRAN Bus Routes, i.e. the New Business 50 Route. Q3 Created route maps for the detour of the Captial Mall Route Route. Q3 Updated maps for all routes to reflect 30 -minute headway and other minor changes. Q3 Updated the JEFFTRAN System Map Q3 Revised and Updated the Route & Schedule Guide Q3 Updated JEFFTRAN website with new maps and Route & Schedule Guide b) Participate in transit -related studies sponsored by other agencies and jurisdictions c) Convene an annual human services transportation group meeting FY 2010 CAMPO Unified Planning Work Program Progress Report 7 d) Monitor, prepare, and distribute information on the region's senior and disabled transportation services e) Review applications for Section 5310 vehicles and recommend funding recipients Q3 Completed in July. Applicants were ranked, selection was done by the Board of Directors, letters sent to applicants, and recommendations sent to MoDOT f) Identify or maintain a clearinghouse of information and resources for coordinating agencies g) Develop and maintain a directory of human service agencies and transportation providers, along with their services Q2 Sent out surveys for updating the list of interested parties Q3 Updated databases in P quarter 4.1.3. Products (estimated completion dates) a) Information and resources for agencies and organizations (ongoing) b) Forum for multi -agency human services transportation planning (annual) c) Additional Section 5310 applications for human service agencies for 2010 funding (May -July 1, 2010) Q3 Completed 4.2. Bicycle and Pedestrian Planning 4.2.1. Responsible Agency: CAMPO staff 4.2.2. Program Activities (Methodology) a) Participate in coordination with City departments and representatives from agencies, such as Parks and Recreation, MODOT committees, focus groups, technical staff, and private interest groups for bicycle and pedestrian planning b) Assist local governments and other project sponsors in the development or design of bicycle and pedestrian plans or projects c) Convene an annual bicycle/pedestrian focus group meeting d) Assistance in development of the Jefferson City local sidewalk plan Q1 Updated the sidewalk database Ql Produced maps for the City of Jefferson Sidewalk Plan e) Review Transportation Enhancement applications bicycle and/or pedestrian components (on- going) Q4 Notified membership of TE application opportunities, assisted jurisdictions in applications and consultation 4.2.3. Products (estimated completion dates) a) Maintain and implement the Bicycle and Pedestrian Elements of CAMPO plans (on-going) b) Amendments to the MTP and TIP for bicycle and pedestrian projects if necessary (on-going) FY 2010 CAMPO Unified Planning Work Program Progress Report 4.3. Goods Movement/Freight Planning 4.3.1. Responsible Agency: CAMPO staff 4.3.2. Program Activities (Methodology) a) Research data sources and information on the freight related programs and plans Q2 Researching Planning and Programming in Small and Medium Sized Metropolitan Areas as recommended in NCHRP Report 570 b) Improve estimates of freight traffic movement and freight generation within CAMPO area (ongoing) c) Convene an annual transportation goods movement/freight focus group meeting d) Review necessity of an update of the freight element of the MTP Q4 Rescheduled to 2011 4.3.3. Products (estimated completion dates) a) Development of freight and goods movement databases (ongoing) 4.4. Transportation Safety Planning 4.4.1. Responsible Agency: CAMPO staff 4.4.2. Program Activities (Methodology) a) CAMPO intends to increase the amount of accident and safety data collected, and to identify accidents and natural hazards as areas for CAMPO to focus on b) Seek additional technical and financial resources to assist in developing transportation safety analysis tools for the region and to improve crash data quality c) Work with local agencies, state DOT, FHWA, and FTA to refine the CAMPO role in SAFETEA- LU transportation safety planning Q4 Ongoing discussions Q4 Attended sessions on this topic at AMPO national conference in 4'h quarter d) Develop and maintain transportation system safety data, acquire and maintain accident and crash data for CAMPO region Q4 Databases updated 4'h quarter e) Support member agencies in integrating safety considerations into project evaluation 0 Convene an annual transportation safety focus group meeting FY 2010 CAMPO Unified Planning Work Program Progress Report 9 4.4.3. Products (estimated completion dates) a) Updated database of traffic accidents and safety-related data (ongoing) Q4 Partially updated b) Mapping of crash data (July, 2010) Q4 Data partially acquired c) Annual report containing analyses of accident data at CAMPO level (October, 2010) Q4 Rescheduled 4.5. Transportation Security Planning 4.5.1. Responsible Agency: CAMPO staff 4.5.2. Program Activities (Methodology) a) Identify special needs populations in the CAMPO area b) Support emergency management agency development of evacuation and emergency response plans c) Add security as a component in evaluating project priorities Q4 Included in the prioritization process d) Convene an annual transportation security focus group meeting 4.5.3. Products (estimated completion dates) a) Report on special needs population (August, 2010) 5.0 Transportation Improvement Plan 5.1.1. Responsible Agency: CAMPO staff 5.1.2. Program Activities (Methodology) a) Prepare an updated 2011-2014 CAMPO Transportation Improvement Program b) Certify the transportation planning process for compliance with federal, state, and local laws c) Facilitate amendments of the Transportation Improvement Program, as required Q1 Amendments to the CAMPO 2010-2013 Transportation Improvement Program Addition of a second Osage River Rail Bridge at Osage City - Total Cost forFY2010 & FY2011: $28,300,000 Upgrade of an existing highway/rail crossing warning device at Osage City - Total Cost for FY2010 & FY211: $268,200 Resurfacing US 54 from Rt. AA/00 in Holts Summit to the Missouri River Bridge - Total Cost for FY2010: $1,084,000 Resurfacing US 50 from Truman Blvd. to Business 50 West - Total Cost for FY2010: $320,000 Resurfacing US 54 from the Missouri River Bridge to Stadium Blvd. - Total Cost for FY2010: $762,000 FY 2010 CAMPO Unified Planning Work Program Progress Report 10 Construction of a bicycle/pedestrian crossing using the Missouri River Bridge - Total cost for FY2010: $7,767,000 Hardship acquisition of property at Lafayette and US 50 as part of the Rex Whitton Expressway improvements - Total cost for FY2010: $806,000 Q3 Amendments to the FY2010-2013 Transportation Improvement Program included TIP #2010- 20, a request by the City of Holts Summit to add a Safe Routes to School Highway Safety Non -Infrastructure Grant project - Approved July, 2010. Also, TIP #2010-10 — Request by the Missouri Department of Transportation to add the Environmental Impact Statement and Hardship Right -Of -Way Purchases and Scoping Project for the US/50 Interchange and Rex Whitton Expressway Improvement Project — In process until September, 2010 Q4 Amendments to the FY2010-2013 Transportation Improvement Program included TIP #2010- 10 in August Q4 Administrative modifications to the TIP completed d) Incorporate annual transit Program of Projects public participation activities into the annual TIP public participation activities Q2 Done in 2nd Quarter Q3 Included in the draft TIP for 2011-2014 e) Develop a project prioritization process Q1 The subcommittee met on January 7 Q3 The development of the process was completed after multiple meetings and discussions of the subcommittee appointed to develop the process, approval from the Technical Committee, distribution to CAMPO member jurisdictions, posting on the CAMPO website, with announcement in the announcements section, and discussion with the Board of Directors. Approval was passed at the July 21, 2010 Board of Directors meeting Products (estimated completion dates) a) An approved 2011 TIP (August 2010) — September, 2010 b) TIP amendments as required (on-going) 6.0 Public Transportation (transit) Planning 6.1.1. Responsible Agenc) : CAMPO staff, JEFFTRAN 6.1.2. Program Activities (Methodology) a) Include Transit Program of Projects into TIP preparation and public notice and advertisements Q3 Included in 2011-2014 TIP development b) Assist and support transit security planning activities c) Assist in route evaluation and environmental justice evaluations as needed Q1 Staff assisted in new route planning and mapping activities, updated route and schedule guide Q1 Gis and mapping for the proposed Renn Addition and Business 50 West route consolidation d) Assist transit in development of a Limited English Proficiency Plan Q2 Assisted JEFFTRAN in their LEP update - completed e) Support transit providers in the integration of safety and security considerations into projects FY 2010 CAMPO Unified Planning Work Program Progress Report 11 Q3 Included safety and security considerations in the project prioritization and project selection process approved in July 6.1.3. Products (estimated completion dates) a) Improvements in transit safety and security (continuous) b) Transit non-discrimination plans and programs (ongoing) FY 2010 CAMPO Unified Planning Work Program Progress Report 12