HomeMy Public PortalAbout04713 O R D I N A N C E NO. 4713
AN ORDINANCE, authorizing the Executive Director and
Secretary-Treasurer on behalf of The Metropolitan St. Louis Sewer
District to enter into a contract with St. Louis County, Missouri,
for construction of Bank Stabilization at Barton Lane, in the City
of Ballwin, Missouri.
WHEREAS, St. Louis County, Missouri has agreed to con-
tribute one-third (1/3) of the total costs of said construction,
the remaining two-thirds (2/3) of said total costs having been
paid by the City of Ballwin, Missouri,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES
OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The Executive Director and Secretary-
Treasurer are hereby authorized to enter into a contract with St.
Louis County, Missouri, for construction of Bank Stabilization at
Barton Lane, in the City of Ballwin, Missouri.
Section Two. The contract authorized in Section One of
this ordinance shall be comprised of such terms and conditions as
are approved by the Director of Legal Services of the District.
The foregoing Ordinance was adopted May 5, 1982.