HomeMy Public PortalAbout05998 O R D I N A N C E NO. 5998
AN ORDINANCE, making a supplemental appropriation of
One Million Four Hundred Ninety-four Thousand Five Hundred Dollars
($1,494,500.00) from the Fee Fee Sewer Extension and Improvement
Fund of which One Hundred Forty-nine Thousand Four Hundred Fifty
Dollars ($149,450.00) is to be used to pay the District's ten
percent (10%) share; a grant of One Million One Hundred Twenty
Thousand Eight Hundred Seventy-five Dollars ($1,120,875.00) is
anticipated from the Environmental Protection Agency, and a grant
of Two Hundred Twenty-four Thousand One Hundred Seventy-five
Dollars ($224,175.00) is anticipated from the Missouri Department
of Natural Resources for Contracts E-396, Amendment 2 (Engineering
Services during construction of Creve Coeur Creek Pump Station,
Force Main, and Interceptor Trunk Sewer), C-972 (Construction. of
Creve Coeur Creek Force Main), C-973 Construction of Creve Coeur
Creek Pump Station), C-991 (Construction of Creve Coeur Creek
Force Main Discharge Structure), C-974 (Construction of Creve
Coeur Creek Sanitary Interceptor - Reach "A"), C-975 (Construction
of Creve Coeur Creek Sanitary Interceptor - Reach "B"), C-976
(Construction of Creve Coeur Creek Sanitary Interceptor - Reach
"C"), C-977 (Construction of Creve Coeur Creek Sanitary
Interceptor - Reach "D"), and C-978 (Construction of Creve Coeur
Creek Sanitary Interceptor - Reach "E"), Federal Project C-291148-
06.
WHEREAS, the District anticipates a seventy-five
percent (75%) grant from the Environmental Protection Agency of
the United States to pay seventy-five percent (75%) of the cost of
said project, and
WHEREAS, a fifteen percent (15%) grant is anticipated
from the Missouri Department of Natural Resources to pay fifteen
percent (15%) of the cost of said project,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES
OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of One Hundred Forty-nine
Thousand Four Hundred Fifty Dollars ($149,450.00) is hereby
appropriated from the Fee Fee Sewer Extension and Improvement Fund
to pay ten percent (10%) of the cost for Contracts E-396,
Amendment 2 (Engineering Services during construction of Creve
Coeur Creek Pump Station, Force Main, and Interceptor Trunk
Sewer), C-972 (Construction of Creve Coeur Creek Force Main), C-
973 Construction of Creve Coeur Creek Pump Station), C-991
(Construction of Creve Coeur Creek Force Main Discharge
Structure), C-974 (Construction of Creve Coeur Creek Sanitary
Interceptor - Reach "A"), C-975 (Construction of Creve Coeur Creek
Sanitary Interceptor - Reach "B"), C-976 (Construction of Creve
Coeur Creek Sanitary Interceptor - Reach "C"), C-977 (Construction
of Creve Coeur Creek Sanitary Interceptor - Reach "D"), and C-978
(Construction of Creve Coeur Creek Sanitary Interceptor - Reach
"E"), Federal Project C-291148-06.
Section Two. The anticipated grant from the
Environmental Protection Agency of the United States amounts to
One Million One Hundred Twenty Thousand Eight Hundred Seventy-five
Dollars ($1,120,875.00), which will be deposited in the Fee Fee
Sewer Extension and Improvement Fund, and is to pay seventy-five
percent (75%) of the cost for Contracts E-396, Amendment 2
(Engineering Services during construction of Creve Coeur Creek
Pump Station, Force Main, and Interceptor Trunk Sewer), C-972
(Construction of Creve Coeur Creek Force Main), C-973 Construction
of Creve Coeur Creek Pump Station), C-991 (Construction of Creve
Coeur Creek Force Main Discharge Structure), C-974 (Construction
of Creve Coeur Creek Sanitary Interceptor - Reach "A"), C-975
(Construction of Creve Coeur Creek Sanitary Interceptor - Reach
"B"), C-976 (Construction of Creve Coeur Creek Sanitary
Interceptor Reach "C"), C-977 (Construction of Creve Coeur Creek
Sanitary Interceptor - Reach "D"), and C-978 (Construction of
Creve Coeur Creek Sanitary Interceptor - Reach "E"), Federal
Project C-291148-06; and said amount is hereby appropriated to be
used to make said payments when due and payable under the terms of
the contracts for said project.
Section Three. The anticipated grant from the Missouri
Department of Natural Resources amounts to Two Hundred Twenty-four
Thousand One Hundred Seventy-five Dollars ($224,175.00), which
will be deposited in the Fee Fee Sewer Extension and Improvement
Fund, and is to pay fifteen percent (15%) of the cost for
Contracts E-396, Amendment 2 (Engineering Services during
construction of Creve Coeur Creek Pump Station, Force Main, and
Interceptor Trunk Sewer), C-972 (Construction of Creve Coeur Creek
Force Main), C-973 Construction of Creve Coeur Creek Pump
Station), C-991 (Construction of Creve Coeur Creek Force Main
Discharge Structure), C-974 (Construction of Creve Coeur Creek
Sanitary Interceptor - Reach "A"), C-975 (Construction of Creve
Coeur Creek Sanitary Interceptor - Reach "B"), C-976 (Construction
of Creve Coeur Creek Sanitary Interceptor - Reach "C"), C=977
(Construction of Creve Coeur Creek Sanitary Interceptor - Reach
"D"), and C-978 (Construction of Creve Coeur Creek Sanitary
Interceptor - Reach "E"), Federal Project C-291148-06; and said
amount is hereby appropriated to be used to make said payments
when due and payable under the terms of the contracts for said
project.
Section Four. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted April 10, 1985.