HomeMy Public PortalAbout07074 O R D I N A N C E NO. 7074
AN ORDINANCE, confirming a contract with Wachter
Construction, Inc. for the construction of storm sewers in
Georgia-Suburban-Harvey Phase I - Section A (S-1873, C-1279), in
the City of Ferguson, Missouri.
BE IT ORDAINED BY THE BOARD OF TRUSTEES OF THE
METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The contract heretofore let by the
Executive Director to Wachter Construction, Inc. as the lowest
responsible bidder for the construction of storm sewers in
Georgia-Suburban-Harvey Phase I Section A (S-1873, C-1279), in the
City of Ferguson, Missouri, with The Metropolitan St. Louis Sewer
District, pursuant to bids received and opened on the 10th day of
March, 1987, and formally executed on the 24th day of March, 1987,
by said contractor and by the Executive Director and the
Secretary-Treasurer on behalf of the District, in the following
form:
is hereby confirmed.
The foregoing Ordinance was adopted March 25, 1987.
-2-