HomeMy Public PortalAbout08286 O R D I N A N C E NO. 8286
AN ORDINANCE, making a supplemental appropriation of One Million
Nine Hundred Thousand Dollars ($1,900,000.00) from the Clean Water Capital
Improvement Trust Fund to be used for project costs for the construction of the
Bissell Point Major Process Equipment (BP-7, 90265) at the Bissell Point
Wastewater Treatment Plant, in the City of St. Louis, Missouri; and confirming
a contract with Tarlton Corporation for the construction of the aforesaid
contract, in compliance with Section 9.040 of the Plan of the District.
WHEREAS, Ordinance Nos. 8235 and 8237 adopted December 12, 1990
appropriated the initial funding for the Aeration Air Compressors and the Final
Clarifier Sludge Collection Equipment, which have been assigned to this
contract for installation, and
WHEREAS, the bid for the construction of the Major Process
Equipment is Twelve Million Six Hundred Ninety-nine Thousand Dollars
($12,699,000.00), and the allowance for change orders is Six Hundred One
Thousand Dollars ($601,000.00), and
WHEREAS, pursuant to Section 7.120 of the Plan of the District, the
appropriation effected herein will not result in a deficit at the end of the
current budget year,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES OF THE
METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of One Million Nine Hundred Thousand Dollars
($1,900,000.00) is hereby appropriated from the Clean Water Capital Improvement
Trust Fund to be used for project costs for the construction of the Major
Process Equipment (BP-7, 90265) at the Bissell Point Wastewater Treatment
Plant, in the City of St. Louis, Missouri.
2
Section Two. The contract heretofore let by the Executive Director
to Tarlton Corporation as the lowest responsible bidder for the construction of
the Major Process Equipment (BP-7, 90265) at the Bissell Point Wastewater
Treatment Plant, in the City of St. Louis, Missouri, with The Metropolitan St.
Louis Sewer District, pursuant to bids received and opened on the 20th day of
December, 1990 and formally executed on the 8th day of January, 1991 by said
contractor and by the Executive Director and Secretary-Treasurer on behalf of
the District is hereby confirmed, in compliance with Section 9.040 of the Plan
of the District.
Section Three. This ordinance, being an appropriation ordinance,
shall take effect immediately upon its enactment.