HomeMy Public PortalAbout08296 O R D I N A N C E NO. 8296
AN ORDINANCE, appropriating One Million Nine Hundred Eighty-Five
Thousand Six Hundred Dollars ($1,985,600.00) from the Operation, Maintenance
and Construction Improvement Fund of Black Jack - Dellwood to be used for
project costs for the construction of sanitary sewers in Black Jack Creek
Subtrunk Sanitary Relief Sewer - Phase I (87004), in unincorporated St. Louis
County, Missouri; and confirming a contract with Purler-Cannon-Schulte, Inc.
for the construction of the aforesaid sanitary sewers, in compliance with
Section 9.040 of the Plan of the District.
WHEREAS, the bid for the construction of said sanitary sewers is
One Million Seven Hundred Forty Thousand Three Hundred Seventy Dollars
($1,740,370.00), and the cost of inspection, construction staking,
advertisement costs, easement charges, and allowance for construction change
orders is Two Hundred Forty-Five Thousand Two Hundred Thirty Dollars
($245,230.00), and
WHEREAS, the State of Missouri has agreed to contribute One Million
Seventy-Seven Thousand Five Hundred Sixty-Six Dollars ($1,077,566.00) toward
the total costs of said project; upon the receipt of such funds from said
source, said money will be returned to the Operation, Maintenance and
Construction Improvement Fund of Black Jack - Dellwood, and
WHEREAS, the Director of Finance has certified that there is an
unencumbered balance in the above-named fund sufficient to pay the obligation
authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES OF THE
METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of One Million Nine Hundred Eighty-Five
Thousand Six Hundred Dollars ($1,985,600.00) is hereby appropriated from the
Operation, Maintenance and Construction Improvement Fund of Black Jack -
Dellwood to be used for project costs for the construction of sanitary sewers
in Black Jack Creek Subtrunk Sanitary Relief Sewer - Phase I (87004), in
unincorporated St. Louis County, Missouri.
Section Two. The contract heretofore let by the Executive Director
to Purler-Cannon-Schulte, Inc. as the lowest responsible bidder for the
construction of sanitary sewers in Black Jack Creek Subtrunk Sanitary Relief
Sewer - Phase I (87004) in unincorporated St. Louis County, Missouri, with The
Metropolitan St. Louis Sewer District, pursuant to bids received and opened on
the 28th day of December, 1990 and formally executed on the 8th day of January,
1991 by said contractor and by the Executive Director and Secretary-Treasurer
on behalf of the District is hereby confirmed, in compliance with Section 9.040
of the Plan of the District.
Section Three. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted February 13, 1991.