HomeMy Public PortalAbout08379 O R D I N A N C E NO. 8379
AN ORDINANCE, appropriating Two Hundred Thirty Thousand
Five Hundred Dollars ($230,500.00) from the Operation, Maintenance
and Construction Improvement Fund of Black Creek to be used for
project costs for the construction of storm sewers in Hampton
Creek-Laclede Station to Elinore (90103), in the City of Richmond
Heights, Missouri; and confirming a contract with Roy Gittemeier
Contractors, Inc. for the construction of the aforesaid storm
sewers, in compliance with Section 9.040 of the Plan of the
District.
WHEREAS, the bid for the construction of said storm
sewers is One Hundred Ninety-one Thousand Five Hundred Eight
Dollars ($191,508.00), and the cost of engineering, inspection,
construction staking, advertisement costs, easement costs, and
allowance for construction change orders is Thirty-eight Thousand
Nine Hundred Ninety-two Dollars ($38,992.00), and
WHEREAS, the State of Missouri has agreed to contribute
Seventy-six Thousand Eight Hundred Eighty-three Dollars
($76,883.00) toward the total costs of said project; upon the
receipt of such funds from said source, said money will be
returned to the Operation, Maintenance and Construction
Improvement Fund of Black Creek, and
WHEREAS, the Director of Finance has certified that
there is an unencumbered balance in the above-named fund
sufficient to pay the obligation authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES
2
OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Two Hundred Thirty Thousand
Five Hundred Dollars ($230,500.00) is hereby appropriated from the
Operation, Maintenance and Construction Improvement Fund of Black
Creek to be used for project costs for the construction of storm
sewers in Hampton Creek-Laclede Station to Elinore (90103), in the
City of Richmond Heights, Missouri.
Section Two. The contract heretofore let by the
Executive Director to Roy Gittemeier Contractors, Inc. as the
lowest responsible bidder for the construction of storm sewers in
Hampton Creek-Laclede Station to Elinore (90103), in the City of
Richmond Heights, Missouri, with The Metropolitan St. Louis Sewer
District, pursuant to bids received and opened on the 8th day of
April, 1991 and formally executed on the 7th day of May, 1991 by
said contractor and by the Executive Director and Secretary-
Treasurer on behalf of the District is hereby confirmed, in
compliance with Section 9.040 of the Plan of the District.
Section Three. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
3
The foregoing Ordinance was adopted June 19, 1991.