HomeMy Public PortalAbout08584 O R D I N A N C E NO. 8584
AN ORDINANCE, appropriating Two Million Five Hundred
Thousand Dollars ($2,500,000.00) from the Clean Water Capital
Improvement Trust Fund to be used for project costs for the
construction of the Bissell Point Watershed Overflow Regulation
System Supervisory Control and Data Acquisition System (BP-05,
92006), in the City of St. Louis, Missouri; and confirming a
contract with Johnson Yokogawa Corporation for the construction of
the aforesaid project, in compliance with Section 9.040 of the
Plan of the District.
WHEREAS, the bid for the construction of the Bissell
Point Watershed Overflow Regulation System Supervisory Control and
Data Acquisition System is Two Million Three Hundred Sixteen
Thousand Six Hundred Fifty-nine Dollars ($2,316,659.00) and the
allowance for change orders is One Hundred Eighty-three Thousand
Three Hundred Forty-one Dollars ($183,341.00), and
WHEREAS, pursuant to Section 7.120 of the Plan of the
District, the appropriation effected herein will not result in a
deficit at the end of the current budget year,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES
OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Two Million Five Hundred
Thousand Dollars ($2,500,000.00) is hereby appropriated from the
Clean Water Capital Improvement Trust Fund to be used for project
costs for the construction of the Bissell Point Watershed Overflow
Regulation System Supervisory Control and Data Acquisition System
2
(BP-05, 92006), in the City of St. Louis, Missouri.
Section Two. The contract heretofore let by the
Executive Director to Johnson Yokogawa Corporation as the lowest
responsible bidder for the construction of the Bissell Point
Watershed Overflow Regulation System Supervisory Control and Data
Acquisition System (BP-05, 92006), in the City of St. Louis,
Missouri, with The Metropolitan St. Louis Sewer District, pursuant
to bids received and opened on the 12th day of December, 1991 and
formally executed on the 7th day of January, 1992 by said
contractor and by the Executive Director and Secretary-Treasurer
on behalf of the District is hereby confirmed, in compliance with
Section 9.040 of the Plan of the District.
Section Three. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted February 12, 1992.