HomeMy Public PortalAbout08646 O R D I N A N C E NO. 8646
AN ORDINANCE, appropriating One Hundred Seventeen
Thousand Five Hundred Dollars ($117,500.00) from the Operation,
Maintenance and Construction Improvement Fund of Creve Coeur-
Frontenac to be used for project costs for the construction of
storm sewers in Capitol #10420 (90133), in the City of Frontenac,
Missouri; and confirming a contract with Fred M. Luth & Sons, Inc.
for the construction of the aforesaid storm sewers, in compliance
with Section 9.040 of the Plan of the District.
WHEREAS, the bid for the construction of said storm
sewers is Seventy-five Thousand Nine Hundred Eleven Dollars and
95/100 Dollars ($75,911.95), and the cost of engineering,
inspection, construction staking, advertisement costs, easement
costs, allowance for construction change orders and other costs,
is Forty-one Thousand Five Hundred Eighty-eight and 05/100 Dollars
($41,588.05), and
WHEREAS, St. Louis County, Missouri, pursuant to its $5
Million Stormwater Bond Issue Program, has agreed to contribute
Thirty Thousand Five Hundred Dollars ($30,500.00) toward the total
costs of said project; upon the receipt of such funds from said
source, said money will be returned to the Operation, Maintenance
and Construction Improvement Fund of Creve Coeur-Frontenac, and
WHEREAS, the Director of Finance has certified that
there is an unencumbered balance in the above-named fund
sufficient to pay the obligation authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES
2
OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of One Hundred Seventeen Thousand
Five Hundred Dollars ($117,500.00) is hereby appropriated from the
Operation, Maintenance and Construction Improvement Fund of Creve
Coeur-Frontenac to be used for project costs for the construction
of storm sewers in Capitol #10420 (90133), in the City of
Frontenac, Missouri.
Section Two. The contract heretofore let by the
Executive Director to Fred M. Luth & Sons, Inc. as the lowest
responsible bidder for the construction of storm sewers in Capitol
#10420 (90133), in the City of Frontenac, Missouri, with The
Metropolitan St. Louis Sewer District, pursuant to bids received
and opened on the 9th day of April, 1992 and formally executed on
the 28th day of April, 1992 by said contractor and by the
Executive Director and Secretary-Treasurer on behalf of the
District is hereby confirmed, in compliance with Section 9.040 of
the Plan of the District.
Section Three. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted April 29, 1992