HomeMy Public PortalAbout08856 O R D I N A N C E NO. 8856
AN ORDINANCE, appropriating One Million Seven Hundred
Fifty Thousand One Hundred Dollars ($1,750,100.00) from the
Operation, Maintenance and Construction Improvement Fund of
Coldwater Creek to be used for project costs for the construction
of the Waterford to Parker Storm Channel (91087), in the City of
Florissant, Missouri; and confirming a contract with Mulligan
Construction, Inc. for the aforesaid construction, in compliance
with Section 9.040 of the Plan of the District.
WHEREAS, the bid for the construction of said storm
channel is One Million Five Hundred Twenty-eight Thousand Four
Hundred Sixteen and 60/100 Dollars ($1,528,416.60), and the cost
of engineering, inspection, construction staking, advertisement
costs, easement costs, and allowance for construction change
orders is Two Hundred Twenty-one Thousand Six Hundred Eighty-three
and 40/100 Dollars ($221,683.40), and
WHEREAS, the City of Florissant, Missouri has agreed to
contribute One Hundred Thirty-two Thousand Five Hundred Fifty
Dollars ($132,550.00) toward the total costs of said project; upon
the receipt of such funds from said source, said money will be
returned to the Operation, Maintenance and Construction
Improvement Fund of Coldwater Creek, and
WHEREAS, St. Louis County, Missouri has agreed to
contribute Thirty-nine Thousand Nine Hundred Dollars ($39,900.00)
toward the total costs of said project; upon the receipt of such
funds from said source, said money will be returned to the
2
Operation, Maintenance and Construction Improvement Fund of
Coldwater Creek, and
WHEREAS, the Director of Finance has certified that
there is an unencumbered balance in the above-named fund
sufficient to pay the obligation authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES
OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of One Million Seven Hundred
Fifty Thousand One Hundred Dollars ($1,750,100.00) is hereby
appropriated from the Operation, Maintenance and Construction
Improvement Fund of Coldwater Creek to be used for project costs
for the construction of the Waterford to Parker Storm Channel
(91087), in the City of Florissant, Missouri.
Section Two. The contract heretofore let by the
Executive Director to Mulligan Construction, Inc. as the lowest
responsible bidder for the construction of the Waterford to Parker
Storm Channel (91087), in the City of Florissant, Missouri, with
The Metropolitan St. Louis Sewer District, pursuant to bids
received and opened on the 30th day of November, 1992 and formally
executed on the 8th day of December, 1992 by said contractor and
by the Executive Director and Secretary-Treasurer on behalf of the
District is hereby confirmed, in compliance with Section 9.040 of
the Plan of the District.
Section Three. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
3
The foregoing Ordinance was adopted January 19, 1993.