HomeMy Public PortalAbout08900 O R D I N A N C E NO. 8900
AN ORDINANCE, appropriating One Million One Hundred
Thirty Thousand Dollars ($1,130,000.00) from the Clean Water
Capital Improvement Trust Fund to be used for project costs for
the procurement of Medium Voltage Adjustable Drive Systems (BP-
04B, 93025B) for the Bissell Point Watershed Overflow Regulation
System Bissell Point Pumping Station Modifications, in the City of
St. Louis, Missouri; and confirming a contract with Ross Hill
Controls Corporation for the furnishing of the aforesaid
equipment, in compliance with Section 9.040 of the Plan of the
District.
WHEREAS, the evaluated bid for the furnishing of Medium
Voltage Adjustable Drive systems is One Million Eight-two Thousand
Sixty Dollars ($1,082,060.00), and the allowance for change orders
is Forty-seven Thousand Nine Hundred Forty Dollars ($47,940.00),
and
WHEREAS, pursuant to Section 7.120 of the Plan of the
District, the appropriation effected herein will not result in a
deficit at the end of the current budget year,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES
OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of One Million One Hundred Thirty
Thousand Dollars ($1,130,000.00) is hereby appropriated from the
Clean Water Capital Improvement Trust Fund to be used for project
costs for the procurement of Medium Voltage Adjustable Drive
Systems (BP-04B, 93025B) for the Bissell Point Watershed Overflow
2
Regulation System Bissell Point Pumping Station Modifications, in
the City of St. Louis, Missouri.
Section Two. The contract heretofore let by the
Executive Director to Ross Hill Controls Corporation as the lowest
responsible bidder for the furnishing of Medium Voltage Adjustable
Drive Systems (BP-04B, 93025B) for the Bissell Point Watershed
Overflow Regulation System Bissell Point Pumping Station
Modifications, in the City of St. Louis, Missouri, with The
Metropolitan St. Louis Sewer District, pursuant to bids received
and opened on the 22nd day of December, 1992 and formally executed
on the 9th day of February, 1993 by said contractor and by the
Executive Director and Secretary-Treasurer on behalf of the
District is hereby confirmed, in compliance with Section 9.040 of
the Plan of the District.
Section Three. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
3
The foregoing Ordinance was adopted March 10, 1993.