O R D I N A N C E NO. 9289
AN ORDINANCE, appropriating a total of One Million Four Hundred Ten
Thousand Dollars ($1,410,000.00), to be funded as follows: Nine Hundred
Seventy Thousand Dollars ($970,000.00) from the Clean Water Capital
Improvement Trust Fund and Four Hundred Forty Thousand Dollars ($440,000.00)
from the Sanitary Replacement Fund to be used for project costs for the
construction of the Bissell Point Watershed Overflow Regulation System Northern
Sewer Rehabilitation (BP-013F, 92116F), in the City of St. Louis, Missouri; and
confirming a contract with Affholder, Inc. for the construction of the
aforesaid contract, in compliance with Section 9.040 of the Plan of the
District.
WHEREAS, the bid for the construction of the Northern Sewer
Rehabilitation is One Million Three Hundred Forty-four Thousand Seven Hundred
Forty Dollars ($1,344,740.00) and the allowance for change orders is Sixty-five
Thousand Two Hundred Sixty Dollars ($65,260.00), and
WHEREAS, pursuant to Section 7.120 of the Plan of the District, the
appropriation effected herein will not result in a deficit at the end of the
current budget year,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES OF THE
METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The total sum of One Million Four Hundred Ten
Thousand Dollars ($1,410,000.00), to be funded as follows: Nine Hundred
Seventy Thousand Dollars ($970,000.00) from the Clean Water Capital Improvement
Trust Fund and Four Hundred Forty Thousand Dollars ($440,000.00) from the
Sanitary Replacement Fund is hereby appropriated to be used for project costs
for the construction of the Bissell Point Watershed Overflow Regulation System
Northern Sewer Rehabilitation (BP-013F, 92116F), in the City of St. Louis,
Missouri.
Section Two. The contract heretofore let by the Executive Director
to Affholder, Inc. as the lowest responsible bidder for the construction of the
Bissell Point Watershed Overflow Regulation System Northern Sewer
Rehabilitation (BP-013F, 92116F), in the City of St. Louis, Missouri, with The
Metropolitan St. Louis Sewer District, pursuant to bids received and opened on
the 28th day of June, 1994 and formally executed on the 12th day of July, 1994
by said contractor and by the Executive Director and Secretary-Treasurer on
behalf of the District is hereby confirmed, in compliance with Section 9.040 of
the Plan of the District.
Section Three. This ordinance, being an appropriation ordinance,
shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted August 10, 1994.