HomeMy Public PortalAbout09559 O R D I N A N C E NO. 9559
AN ORDINANCE, appropriating a total of One Million Five
Hundred Fifty-one Thousand Dollars ($1,551,000.00), to be funded as
follows: One Million Four Hundred Forty-two Thousand Dollars
($1,442,000.00) from the Operation, Maintenance and Construction
Improvement Fund of Black Creek, and One Hundred Nine Thousand
Dollars ($109,000.00) from the Operation, Maintenance and
Construction Improvement Fund of Deer Creek, to be used for project
costs for the construction of storm sewers in Claytonia Creek Storm
Channel (93015), in the City of Richmond Heights, Missouri; and
confirming a contract with Mulligan Construction, Inc. for the
construction of the aforesaid storm sewers, in compliance with
Section 9.040 of the Plan of the District.
WHEREAS, the bid for the construction of said storm
sewers is One Million Four Hundred Seventy-seven Thousand Thirteen
Dollars ($1,477,013.00), and the allowance for construction change
orders is Seventy-three Thousand Nine Hundred Eighty-seven Dollars
($73,987.00), and
WHEREAS, the State of Missouri has agreed to contribute
Forty-two Thousand Dollars ($42,000.00) toward the total costs of
said project; upon the receipt of such funds from said source, said
money will be returned to the Operation, Maintenance and
Construction Improvement Fund of Black Creek, and
WHEREAS, the Director of Finance has certified that there
is an unencumbered balance in the above-named fund sufficient to
pay the obligation authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES
OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The total sum of One Million Five Hundred
Fifty-one Thousand Dollars ($1,551,000.00), to be funded as
follows: One Million Four Hundred Forty-two Thousand Dollars
($1,442,000.00) from the Operation, Maintenance and Construction
Improvement Fund of Black Creek, and One Hundred Nine Thousand
Dollars ($109,000.00) from the Operation, Maintenance and
Construction Improvement Fund of Deer Creek, is hereby appropriated
to be used for project costs for the construction of storm sewers
in Claytonia Creek Storm Channel (93015), in the City of Richmond
Heights, Missouri;
Section Two. The contract heretofore let by the
Executive Director to Mulligan Construction, Inc. as the lowest
responsible bidder for the construction of storm sewers in
Claytonia Creek Storm Channel (93015), in the City of Richmond
Heights, Missouri with The Metropolitan St. Louis Sewer District,
pursuant to bids received and opened on the 29th day of March, 1995
and formally executed on the 19th day of April, 1995 by said
contractor and by the Executive Director and Secretary-Treasurer on
behalf of the District is hereby confirmed, in compliance with
Section 9.040 of the Plan of the District.
Section Three. This ordinance, being an appropriation
3
ordinance, shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted May 11, 1995.