HomeMy Public PortalAbout09-0366 City of Tybee CITY OF TYBEE ISLAND
BUILDING PERMIT
DATE ISSUED: 08 -6 -2009 PERMIT #: 090366
WORK DESCRIPTION REPLACE & EXTEND ENTRANCE RAMP
WORK LOCATION 9 CEDARWOOD -REC CENTER
OWNER NAME CITY OF TYBEE
ADDRESS PO BOX 2749
CITY, ST, ZIP TYBEE ISLAND GA 31328 -2749
PHONE NUMBER
CONTRACTOR NAME CITY OF TYBEE
ADDRESS PO BOX 2749
CITY STATE ZIP TYBEE ISLAND GA 31328 -2749
FLOOD ZONE
BUILDING VALUATION
SQUARE FOOTAGE
OCCUPANCY TYPE U
TOTAL FEES CHARGED $ 0.00
PROPERTY IDENTIFICATION #
PROJECT VALUATION $ 500.00
TOTAL BALANCE DUE: $ 0.00
It is understood that if this permit is granted the builder will at all times comply with the zoning, subdivision, flood control, building, fire,
soil and sedimentation, wetlands, marshlands protection and shore protection ordinances and codes whether Local, state or federal, including
all environmental laws and regulations when applicable, subsequent owners should be informed that any alterations to the property must be
approved by the issuance of another building permit. Permit holder agrees to hold the City of Tybee Island harmless on any construction
covered by this permit.
This permit must be posted in a conspicuous location in the front of building and protected from the weather. If this permit is not posted
work will be stopped. The building contractor will replace curb paving and gutter broken during construction. This permit will be voided
unless work has begun within six months of the date of issuance.
Signature of Building Inspector or Authorized Agent: )0#5
P. 0. Box 2749 - 403 Butler Avenue, Tybee Island, Georgia 31328
(912) 786 -4573 - FAX (912) 786 -9539
www.cityoftybee.org
,l City of bee Island • Community Develc ient Dept. irk
4 /, ' Inspection Report somik 403 Butler Ave. • P.®. Box 2749 • Tybee Island, GA 31328 '='® NATIO INTERNAL
s Phone 912.786.4573 ext. 114 • Fax 912.786.9539 CODE COUNCIL
/ MEMBER
i J !
Permit No. r� - 0 3 Co (,-7 Date Requested 17 1 2 10
Owner's Name 11 r / ' I eP� Date Needed 7 ° 13 -/
a
Gen. Contractor Subcontractor
Contact Information �� e. 1.0S 3302—
Project Address 0Pd rf .s il 0,4 Scope of Work . v ' 44 .,) r
Inspector 1/ ( i i Date of Inspection . --° f / / o
Inspection 1 C "l , 0 r- —C rra 1 Pass f El` Fee
T J
-7 (j...,_ r # 1
f t) /)/ ;1 ="'l`�. ,�4 /,4 -4, /?:„ 6 _, ,-_-,,4,4,47
d , 5(-1.15,-C:-: - ' "
l
I
Inspection Pass ❑ Fail ❑ Fee
Inspection Pass ® Fail 0 Fee
Inspection Pass ® Fail ® Fee
\_ \ ; -tb 5
; riet_e � \
City of Jee Island • Community Develo ent Dept. i�ti%
) . , Inspection Report R��;
, v -i / 403 Butler Ave. • P.O. Box 2749 • Tybee Island, GA 31328
Phone 912.786.4573 ext. 114 Fax 912.786.9539
CODE COUNCIL'
/� MEMBER
Permit No .7,'9 2L D ate Requested /k/ f L.'
Q
/ ,r / /
Owner's Name !_� L ..z .7,./.4 Date Needed ,dal /, /! 7
Gen. Contractor �� a Subcontractor
Contact Information \,..,.°C2/
Project Address ‘'Di
Scope of Work ,4',f
Inspector '' / Date of Inspection .44/67
/ /
Inspection 7 — Pass El Fail 0 Fee
- 2)5t(V. 5 ' ./,-- 11-2_,<,-A) w r \i,,0 --. e :,,, , -:: - /2, 7 -
Inspection Pass ❑ Fail ❑ Fee
Inspection Pass ❑ Fail ❑ Fee
Inspection Pass ❑ Fail ❑ Fee
r\ '
City of TOee Island • Community DeveloL ,ent Dept.
it"
Inspection Report 11:21ti
1 4./
a )1
403 Butler Ave. • P.O. Box 2749 • Tybee Island, GA 31328 INTERNATIONAL
_.„.. Phone 912.786.4573 ext. 114 • Fax 912.786.9539 CODE COUNCIL
MEMBER
Permit No. n 6 7 - 0 3 &7 b Date Requested ( - ' 7/ Q
Owner's Name 0 : 4 4 Or 74,16,co Date Needed ‘'' - F 0
Gen. Contractor L.4-4 D ri 6 ge... Subcontractor
/ f
Contact Information .4"/ f hos- et 2 iq - _Lcr / )
Project Address q 1 P ti C1r7._,LI Q '3 CI
Scope of Work ADA- r 4 vv il
1 -
Inspector - 1/ C i Date of Inspection /
( 6) ( 0
Inspection DrO , 4 r -it- -r: II a ) Pass El Fail g Fee
EX.c,f_f_bS MAY-461011 56-pt. t 1 14
1:::)<CE MAXI i/Pik..Md
VA t.) 1-\ta tha' I V \fie., i la rob( oci:-_, ic." - 1304)0A
1---1-4NSI>ie.4-1 1 071 ,t_- i--34).-07 606-ti ,:k.K.us ,:_;,
Inspection i Pass ri Fail El Fee
, iirtD 1 N).._1. 06+ 4-4
A - F)
oL
et_
c.-.14 ( A /-- T 4-
1 Nbi
'6 Z-di--c 1 2 0 _ 5 ..,20 ... , 1
--
1 tTY-- 27,c;o6, 1010 -yiDIS
Inspection Pass El Fail 0 Fee
pi S r rAf ( 4 .)I , _:=1"\., D) I;
-
--
I
Inspection Pass 0 Fail 0 Fee
CITY OF TYBEE ISLAND, GEORGIA
APPLICATION FOR BUILDING PERMIT
}
oQ- o 3 G
Location: 7 CL i`/ PIN #
—
NAME ADDRESS TELEPHONE
Owner 2 d7 / 1 1 ec L4(ji)/`�--
Architect ' v
or Engineer /` yC/ 2? (`e /'i fe,L.
Building /'
Contractor � yG �.� ��
'v
(Check all that apply)
►;4 Repair ❑ Residential R r Footprint Changes
II Renovation ❑ Single Family Discovery
❑ Minor Addition ❑ Duplex ❑ Demolition
❑ Substantial Addition ❑ Multi- Family
❑ Other ❑ Commercial
Details of Project: g ,p /1 CP £ `�2U'''1 c� / te)
�} a�
Estimated Cost of Construction: $
Construction Type 1 (Enter appropriate number)
(1) Wood Frame (4) Masonry (6) Other (please specify)
(2) Wood & Masonry (5) Steel & Masonry
(3) Brick Veneer
Proposed use:
Remarks:
ATTACH A COPY OF THE CERTIFIED ELEVATION SURVEY OF LOT and complete the
following information based on the construction drawings and site plan:
# Units # Bedrooms # Bathrooms
Lot Area Living space (total sq. ft.)
# Off - street parking spaces
Trees located & listed on site plan
Access:
Driveway (ft.) With culvert? With swale?
Setbacks: Front Rear Sides (L) (R)
# Stories Height Vertical distance measured from the average adjacent
grade of the building to the extreme high point of the building, exclusive of chimneys, heating
units, ventilation ducts, air conditioning units, elevators, and similar appurtances.
During construction: /
On -site restroom facilities will be provided through C 1 C 7
On -site waste and debris containers will be provi ed by
Construction debris will be disposed by f by means of
I understand that I must comply with zoning, flood damage control, building, fire, shore
protections and wetlands ordinances, FEMA regulations and all applicable codes and regulations.
I understand that the lot must be staked out and that the stakes will be inspected to ensure that the
setback requirements are met. I understand also that a certified plot plan showing elevation must
be attached to this application and that an as -built elevation certification is due as soon as the
habitable floor level is established. Drainage: I realize that I must ensure the adequacy of
drainage of this property so that surrounding property is in no way adversely affected. I accept
responsibility for any corrective action that may be necessary to restore drainage impaired by this
permitted construction.
Date: L /0 Signature of Applicant: 4
1
Note: A permit normally takes 7 to 10 days to process.
The following is to be completed by City personnel:
Zoning certification NFIP Flood Zone
Approved rezoning/variance?
Street address and number: New Existing
Is it in compliance with City map?
If not, has street name and /or number been reported to MPC?
FEMA Certification attached
State Energy Code Affidavit attached
Utilities and Public Works:
Describe any unusual finding(s)
Access to building site
Distance to water main tap site
Distance to sewer stub site
Water meter size
Storm drainage
Approvals: Date FEES
O Zoning Administrator / Q / Permit
Code Enforcement Officer Inspections
Water /Sewer , ., / Water Tap
Storm/Drainage g /G' /t-- / � y Sewer Stub
Inspections (/ L l Aid to Const
City Manager . j
(!I (I 4.-V
TOTA,
OWE OF l asse m,
NATURAL
RESOURCES •St
:tC — rr � a rr
lli
GEORGIA
Permit Acknowleduement of
Asbestos/Environmental Notification to Georgia EPD for
Proiects Involvinu Demolition. Wrecking, or Renovation
The undersigned hereby acknowledges that the issuance of this permit does not in any way grant
permission to the owner, owner's representative, or permit holder to proceed with demolition,
wrecking, or renovation of a structure prior to the filing of any required ten (10) day "Project
Notification for Asbestos Renovation Encapsulation or Demolition" form in accordance with
the Georgia Asbestos Rules. The Georgia Environmental Protection Division administers the
rules. In most cases, the rules require both the owner and the involved contractors to assure the
portion of the building involved in the project is thoroughly inspected by an Accredited Asbestos
Inspector for materials that contain asbestos; and the removal of the asbestos before renovation,
wrecking, or demolition begins almost without exemption. Georgia EPD requires a completed
demolition notification from be submitted 10 workings days in advance even if no asbestos is
present in the building. Further guidance for regulatory compliance and contact telephone
numbers are provided by the brochures entitled Asbestos & Renovation and Asbestos and
Demolition. Other environmental issues such as asbestos removal techniques, lead abatement,
ground contamination, or unusual site conditions may have EPD regulations that could affect the
project.
FA/7c-)
Uersigned Date
-e I/` 7s
Printed Name
Office Use Only:
Project Address:
Permit Number:
REQUIRED FOR: Building Permits
Relocation Permits
Sign Permits
Demolition Permits
Land Clearing, Disturbance or Excavation Permits
Tree Removal Permits
Relocation Permits
Special Review Permits
Site Plan Approval
Subdivision of Land
Sketch Plan Approval
Preliminary Plan Approval
Final Plat Approval
Minor Subdivision Plat Approval
Major Subdivision Plat Approval
In addition to specific requirements for the above permits and approvals, applicants must
demonstrate that they are in compliance with the City of Tybee Island Storm Water Management
requirements as outlined in Chapter 5 -4, Code of Ordinances.
Section 5 -4 -9 Prohibition provides, in part, as follows:
(4.) It is unlawful for any person to cause or permit any storm water to flow from their
property onto the property of another person, unless such storm water naturally
flowed thereon prior to any development activity.
(5.) It is unlawful for any person to interrupt the flow of any storm water runoff from
adjacent property onto their property by any development activity.
As part of the City's approval process applicants must illustrate how these storm water
management prohibitions will be met, including a showing of how storm water naturally flowed
on the affected property (prior to any development activity), and what changes in storm water
flow have occurred or are expected to occur, as attachments to this form. The City's approval or
permit does not guarantee that the applicant's plans will result in meeting requirements. The final
product must actually meet the City Ordinance requirements.
Applicant name: ^i
Project I.D.:
Attachments approved by: Date: