I. RECOMMENDATION - PNM CORPORATION
A. Waive competitive bidding as per Ordinance 92-15, Section 7 and award
bid to P.N.M. Corporation and the Village Manager be authorized to
execute a change order in the amount of $238,388 (plus contingency of
10%) for top soil, sod and trees.
B. Recommendation is supported by the Village Engineer and the Village
Landscape Architect, William O'Leary.
II. CONSTRUCTION CONTRACT - PNM CORPORATION
A. Awarded by Village Council on July 26, 1994, executed August 8, 1994
B. Amount: $506,517.50
C. Contract provides for site work, drainage, jogging path and promenade
D. Playground Equipment
1. Council authorized program on October 11, 1994
2. Amount: $98,000 plus contingency
E. Contract does not include top soil and sod
F. State contract executed on September 1, 1994 by PNM Corp. with
$51,700 savings for the Village plus project could be completed ahead of
schedule because of shorter haul
85 West McIntyre Street • Key Biscayne, Florida 33149 • (305) 365-5514 • Fax (305) 365-5556
MISSION S 141 EMENT "TO PROVIDE A SAFE, QUALITY COMMUNITY ENVIRONMENT FOR ALL ISLANDERS 1 HROUGI1 RESPONSIBLE GOVERNMENT."
III. ESTIMATE FOR TOP SOIL AND SOD - (290,150 Square Feet)
A. May 17, 1994 - Cost estimate $201,600
B. June 14, 1994 - Cost estimate $182,403
C. July 12, 1994 - Cost estimate $184,000
IV. ACTUAL TOP SOIL, SOD AND TREE BIDS - JULY 22, 1994
Trees 197 +
A. PNM Corp $287,248.50 $53,210.00
B. PJ Construction $191,499.00 $46,889.00
V. PROPOSALS FOR TOP SOIL, SOD AND TREES
A. PNM Corp.
1. Proposal dated August 1, 1994
a. Top soil
b. Sod (no bid)
2. Proposal dated August 2, 1994
a. Top soil and sod
3. Proposal dated September 21, 1994
a. Top soil and sod
(same as PJ original low bid)
B. PJ Constructors, Inc.
1. Proposal dated August 2, 1994
a. Top soil and sod plus 1.5% for
performance bond
VI. ADVANTAGES TO AWARD TO PNM CORP.
$118,808.00
$205,000.00
$191,499.50
$211,809.50
A. Proposal dated September 21, 1994 is equal to original low bid
B. Project might be completed ahead of schedule
C. Warranty on irrigation system will be effective since only one contractor
will be working
D. Eliminate damage to jogging path, promenade and walkway
E. Eliminate finger pointing between contractors
F. Sod completed prior to project completion which is good for growth of
grass
G. If re -bid, cost could be higher
H. PNM performance up to now has been good
I. Prevent unanticipated logistical problem
J. Sod be given additional time to knit together
VII. DISADVANTAGES
A. Cost may be less, if re -bid, although questionable
VIII. GRANTS
A. Land and Water Conservation Fund
(awarded for acquisition) $100,000
B. Florida Communities Trust
(acquisition - award pending) $700,000
C. Florida Recreation Development
Assistance Program
(development - award pending) $100,000
IX. SUMMARY OF COSTS
P.N.M. P.J. ACTUAL PNM
Base Bid $466,850 $585,500 $466,850
Jog Path 17,600 29,700 17,600
Promanade 73,767 62,120 73,767
$558,217 $677,320 $558,217
- 51,700 - 145,500 - 51,700
$506,517 $531,820 $506,517
Trees + 53.210 + 46,880 + 46,889
$559,727 $578,709 $553,406
Fi11/Sod 287,248 191,499 191,499
5846,9 $779,208 ,$744,905