HomeMy Public PortalAbout15615 Bissell – Coldwater – Missouri – Meramec Public II Reduction (2021) Contract A (12508)ORDINANCE NO. 15615
AN ORDINANCE, making an appropriation of Three Million One Hundred
Thousand Dollars ($3,100,000.00) from the Sanitary Replacement Fund to be used for sanitary
sewer rehabilitation in Bissell – Coldwater – Missouri – Meramec Public I/I Reduction (2021)
Contract A (12508) in the Cities of Ballwin, Des Peres, Ellisville, and Kirkwood, Missouri; and
authorizing the Executive Director and Secretary-Treasurer on behalf of The Metropolitan St.
Louis Sewer District to enter into Contract No. 21982 with SAK Construction, LLC for sanitary
sewer rehabilitation.
WHEREAS, the bid for said sanitary sewer rehabilitation is Two Million Nine
Hundred Eighty-Nine Thousand One Hundred Forty-Three Dollars ($2,989,143.00) and the
allowance for construction change orders and other project expenses is One Hundred Ten
Thousand Eight Hundred Fifty-Seven Dollars ($110,857.00); and
WHEREAS, the Director of Finance has certified that there is an unencumbered
balance in the above-named fund sufficient to pay the obligation authorized herein.
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES OF
THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Three Million One Hundred Thousand Dollars
($3,100,000.00) is hereby appropriated from the Sanitary Replacement Fund for sanitary sewer
rehabilitation in Bissell – Coldwater – Missouri – Meramec Public I/I Reduction (2021) Contract
A (12508) in the Cities of Ballwin, Des Peres, Ellisville, and Kirkwood, Missouri; said contract
being comprised of such terms and conditions as have been approved by the Office of the General
Counsel of the District.
Section Two. The Executive Director and Secretary-Treasurer are hereby
authorized on behalf of The Metropolitan St. Louis Sewer District to enter into 21982 with SAK
Construction, LLC, as the lowest responsible bidder for sanitary sewer rehabilitation in
Bissell – Coldwater – Missouri – Meramec Public I/I Reduction (2021) Contract A (12508) in the
Cities of Ballwin, Des Peres, Ellisville, and Kirkwood, Missouri, pursuant to bids received on the
15th day of January, 2021.
Section Three. This ordinance, being an appropriation ordinance, shall take effect
immediately upon its enactment.
The foregoing Ordinance was adopted on March 11, 2021.