Loading...
HomeMy Public PortalAbout2018-10-11 packetRevised Notice of Meeting & Tentative Agenda City of Jefferson Public Works & Planning Committee Thursday, October 11, 2018 7:30 a.m. John G. Christy Municipal Building, 320 East McCarty Street Boone/Bancroft Room (Upper Level) TENTATIVE AGENDA 1) Introductions 2) Approval of the September 13, 2018 Committee meeting minutes 3) New Business 1. Schellridge Traffic Study (David Bange) 2. Ride the Bus Free Day on Election Days as Recommended by the Public Transit Advisory Committee (Mark Mehmert) 3. Bike Pavement Striping and Signage on West Main and Miller Streets (David Bange) 4. TAP Grant Applications (David Bange) 5. High Street Viaduct BEAP Study (Matt Morasch) 6. Pedestrian Crossing at Schools (Requested by Councilman Hussey) 7. 2045 Metropolitan Transportation Plan Update (Alex Rotenberry) 8. CDBG 2019-2023 Consolidation Plan (Jayme Abbott) 4) Other Topics 5) Citizen opportunity to address Council/Staff on Stormwater and Other Public VVorks Issues 6) Adjourn NOTES indivrduats should contact the ADA Coordinator at (573) 634-6570 to request accommodations or alternative formats as required under the Americans with Disabilities Act Please allow three business days to process the request Please calf (573) 634-6410 with questions regarding agenda items Memorandum 320 East McCarty Street • Jefferson City, Missouri 65101 • P. 573.634.6410 • F: 573.634.6562 • wwwjettersoncitvmo.gov Date: October 8, 2018 To: Public Works and Planning Committee From: David Bange P.E., City Engineer -D-p-6 Subject: Intersection of Industrial and Jaycee Drives The Committee will recall that during the July 2018 meeting Staff presented a traffic study for the intersection of Industrial Drive and Jaycee Drive that indicated that the intersection did not meet any of the warrants for a traffic signal and observations revealed that the intersection was operating efficiently as a two way stop. After discussion Staff was instructed to collect additional traffic counts and look into such things at lighting and truck traffic and to report back to the Committee. Manual turning movement counts were collected during the morning and afternoon peak on Tuesday, September 11, 2018. Counts were taken from 7:00 A.M. to 8:30 A.M. with the peak falling between 7:15 and 8:15 A.M. The evening counts were taken between the hours of 4:00 P.M. and 5:30 P.M. with the peak falling in the hour between 4:30 and 5:30 P.M. Machine counts were taken from Friday, September 21 through Thursday, September 27, 2018. Evaluation and comparison of these two sets of data has led us to believe that some type of error is present within it, as some counts are more than 2.5 times removed from the expected values. Because of this it to will be necessary to reset the counters and collect the data again. In addressing the level of lighting at the intersection the City has worked with AmerenUE who will be installing a brighter LED light in the place of the light that is currently located at the southeast corner of the intersection. In addition a new light will be placed on the northwest corner of the intersection. Staff has also made contact with Unilever regarding truck traffic at this intersection. They indicated that about 50 percent of the time they use Jaycee Drive as their route to and from the warehouse located off of Jaycee Drive. It was also stated that the removal of the signal has not affected the timing or operation of their trucks. He did acknowledge that making a left turn from Jaycee Drive to Industrial during peak times was more of a risk, but that their drivers were professionals. They did not mention any needs or accommodations. As was mentioned in the Staff memo from the July meeting the intersection could be served by a roundabout. Among the benefits of roundabouts is the ability to handle varying volumes of traffic, removal of the maintenance associated a traffic signals, greatly reduce stopped time and hard accelerations, and reduce crashes. For these reasons if improvements were sought at this intersection Staff would favor the construction of a roundabout. U.1Public WorkslEngineeringldbangelPUBLIC WORKS & PLANNING12018110-20181Jaycee and Industrial Memo docx Memorandum 2 If you have any questions I can be reached at 634-6433. DB:db U:1Public Works'Engineeringldbange\PUBLIC WORKS & PLANNING12018110-2018Waycee and Industrial Memo.docx JEFI49ffRAN connecting our community Department of Public Works Memorandum 320 E. McCarty Street • Jefferson City, Missouri 65101 • P 573-634-6410 • F 573-634-6562 • www.ieffcitymo.orq Date: October 8, 2018 To: Public Works Committee Through: Matt Morasch, P.E., Public Works Director From: Mark Mehmert, Transit Director Vi/Az` Subject: Public Transit Advisory Committee proposal for free rides on election days Public Works Staff request the committee provide input regarding providing a trial "ride the bus free day" on election days. In its September 25 meeting, the Public Transit Advisory Committee voted to recommend the Public Works Committee consider directing JEFFTRAN to offer free rides on election days. If endorsed by the Public Works Committee, staff recommends a trial for the November 6, 2018 election day. Through the Missouri Public Transit Association (MPTA), staff contacted other Urban and Small Urban properties to inquire about their policies regarding this concept. Election Day Free Rides Urban Transit System Free? Paratransit included? Columbia Yes Yes Joplin No N/A KCATA Yes unknown Springfield No N/A If the committee includes paratransit, staff estimates lost revenue of $2,000 to $2,500 each day based on an analysis of fares collected on prior election days. If paratransit is not included, lost revenue is estimated at $500 to $600. Please feel free to contact me if you have questions. MM:mm City► 1111 11111 lef 11111 erson X11 Public Works Miller and West Main Striping City Project Number 32158 1041. 11 111 Begin West T Main Striping End West Main Striping Begin Miller Street Striping Plans Accepted by. Daze: Matthew Norasch. P.C. Public Works tfhrector O End Miller Street Striping INDEX OF SHEETS 1 Cover Sheet 2 General Notes and Sued -Lana Marking Doted 3-7 Mifor Street Striping 8-13 West Main Street Striping 14 Sign Details 15 Miser Street Wayfinding Signs 18 Wast Main Wayfirtding Signs 17 Sign Schedule a5 W yllµtq'S 0.'1! nrnntittErson T� _-r,-yrs fiy�3�� F.� City of Jefferson, Missouri �'-rryS'sis. ' tAl.rtnl nti`"`� Carrie Tergin, Mayor '11rrut,,mobls° " tt a Nanta ammo 1 um East rrnw.51n4t 1C; ''�- latScrso Utr..ano.i 651111 mase an 6633.10.10 I. 6TA 674-1517 Ivo.".•mo�ny .tion AowPst«4Hkncitt...7 t7svW P. Bator PE -2O07020241 stir . :1 of'. 7 I®®O®01 4®oj ®x4®■`lo`I 11 1 11 lirII -‹ I 1 N4 V t+ ► f•t+;ff 0111111 FR: k fity I! B a 1 I P L c f a O co O 2 S r 7c � O A m D �i i i b 3b 3�' 1,1 111! �b Si S 8 gig{{ $ of 1i11e1 �€ g s li!$sa T$ 41.11" $ g € Re his ! $ Y� $ !hiBtiD I I thief pp,<R die ` 1,$ jaj t ill I Yea 1aqg g !PI iit sri Y4161 I I I I I II I I I I I I In 1 n e1e�n C aa�ljpoo i I IIII I I I I I o I j ai1!III t yef1111!oI i IiIIII1 I!Iil�I*I i l $$illi 0!!!eliri 1 1E 111 n City of efferson a ►uaua W0K DMMM Cr OPS General Nater Sharron, Detail 11 I a +OG ea II iatid 040 0000 u I I ae NO: DATE: REVISION AND DESCRIPTION DAi en. ro.t Miller and West Main Striping Project No.121 S8 Welt Main Step and Millar Street z +agIv 11DM 9 /19310 ,1301,7 00t -00I NVQ ihnUISNI 'M 000L•OOC :uopdp)soo pup uoisInaa :a1va :0N 8s WO U+roid eulduts uptiti Isom put aIIM Iaa15 Ja1191 ucy au5 11 t.pp -,Ta IC o,, rlStru,t 4wri IttnturtiMiQIg006-00tBOput uRW'MOOLL-OOL :uop • N)sap • ut uoIslioa NMI IIMM :arta aS ILS• iwoid (*oils upy, 1SOM Put JNIM Pain +01191 taw BIS N. 0 ld0td in /I4 MAY USE FULL LANE detrr11w ebpa Ydo . 4' We% 10 Ing, 30' gap {t») W. MRler Street (100 Mock) v 0 Z ISORE) E E YIELD T08?i(ES ye m Mixed mane �eblpe. 8hllr. 4' •E... 7 tang, e' ere (t7p) furor motel (to) 1 t - 1 t Reawre101i4610,101i4610,paIse t. Ir a past net+ c.,t . .$il amt o Ng p sign moss raiding Am. Ln.ert F-.'--,� re peeking ogee to M 7 fort aoors aura s+a.ot 1 f'':1 1.1.1.1 1.1 1 1 1 1 1 11.1 1'LJ....4:1J Centerline ebbe. YMaor. 4' Bade, 10' long. 37 gar (tw) aHAREOcl+tEL'�_ uric l.""}T"'T c,sl i-�1 1S°S '`' ` YIELOT0SKS E Hear Street (100 Mk.* Peewee Iwo WI, SHUT MAWR 5of17 Ll J° 9 YIP1,fIM lTinS -- 1: , .d.,. iry.n .pd , OR 14.41 a 1.41.49. Wei r ; '� � � � 11 ill) !.6 A 411u 'mwl ,Z 'arm. .Y ..mitt..mitt'.44. +,! !wl 01+m6� jp IR* j irD 1-11 = 11 irn +�. w 2.....•....... • InatoLoOtr,t: -'?t< —'' r".. fYtlt:vtl ��,+gy.:tturased at,,da.. ii491Wingia911 j Y '1.1 . rtILL i '`•/¢ + a_ .r 1 wx. w ae,..wo r - sa>IK10101_ • - , o. { A;< .6Ea3a — . '•;� 1 _ _ _• I ' — {-' Isl. I 1 ?tiV13)48t13#14hS 1 rd» w. 1 .11-au Wn• •ws 64w,' of t tuq .7. a a,.as. r.•. ,z1 { r . I 11. • ''- I I h` d l ' r , , K MI .dsn. N.s.... on. 64u, : swn :..n. ae.. 1�n049 I --�.os-�31.4 awn _ -- '•.. / _ ti if • _ - . 04l Lop,. li I € 2. - $ i ... -- -_r-_. -- - - -- - - - e.. +' - .. M. ..., . e. .,. 1#! MM .. a4 I.r.on-- 5ire Plan Miller Street Miller and met win StntHny Protect •33156 wool liar 144.1 *Amp cep wen 1..d .1.. OHM ided Fwe Am lowed mimatii 4 ,- .. @co A x '64 i Mh ! .1411 .44..4.1 ,rag C3 .7 1 m " rte. ' ' � r Q. r ppf LL { I . Z O o 1 Revision and Description. Pr sr (at) 4.6 AC 4.r.1 ,01 'Mr .► +lea s4+1. •4wiW .. ..M. Mid...moi 040. - I r — i� �� ..,d y..q! M .IF i,•,.lf OW 4.m _. •.,1W •WM 0.101 I fluJot ....... . Jten .to:r1..• .,... ...µ, ' MD fir g mom t -C.1 I- *.14- t..•••• ; -; .. • ,Puri $ M TIM IP P3c1Q OOt-COI ;NI Pur uRYi'M WV -001 :uOi1d asap pue uOt iA :iI!a ffS I lisp Inroad 5u,du1S U!» 11aM put Aim yo»iS ugtI1 °M uLlj PPS Rat Wog 11 1a 001 "t r 1 Rr00 0 .slltbi No Pada" yipa ed pod 'nstal naw port ..d R4-11 .br1 R e11,d-.'I Ile Parking undo, R4--11. Ur,Rom of lie Perk 7n0 1pn MAI M r 01000. rPd..a91. Rma. Wrlmq Ho Parking lin Rind poit kola no. pat and .eylhdvnq .q. Rln.toll Ho Prektng ribs ander wop4&iq Nps. Bo11rn el Ho Porldnq lqa lull M r aka,. dd.wak. • Went Main Sired 3107" a.71 -k 0 a rr VI a Oa- ritigAtM SAINT kt.,aF0 9 of 1 7 11 Noe 'M 6191 JAIL N14149.. .._. _ i 0971 =t. Ir •O9 N 4191' `._.- -"_ • eak ' ' 1 . ' 41,1,, . ', - • air\ -," - .. • i •• . • - 4, - o 01 -.e $; .a, II.I, ,• ••.- • -•, - IPIP rte,CgrjlfAit:.i;f Revision and Description: L -'4 447111,ID5E FULLLNIE - . ..•.I-._; 30 -- ' ,- - -i- -: _ ..._. :- ,..,.. _ _ - ,..• .11 titrklkt, at‘IgCCn.,!,<\ sva. , 1' 1. • v. i" Y 1 1l'' , , 1, . .. . IIIIP . . - .... . -. .... - . - .1 , j °I.I.N.... ak. IOU • , \ ear -7 30' • , West Main SOW Sherrow *,mbol (t)9 , • "N- -.. 1 III 73 ,,_..._,.. rillfi. ., i v sv 47 Sri 1....1 t cov i 1.11_11./fE e/14.J5 , ' • ,I, ,- r 1 " .4 /III • .1',,,,„. 44'1' ' 11111111r- . 411/11111frt! ... , '';'. , t. 3 9 bl. e V ... ..'t 3 • • , .--:; . _ , . _ '• • - e • _ . --,- -"— - — 1 ir , .. --,.--... .,... . , . • • • . ,... . . ... . . . sac 74 . " ; *lifiliii: . - _... _ _ . _ . -__ r .-,-,) -6.93 ..• 'A , 0 '.. „ 4 ' • ',,, \ I 't:' -:.""I 17' . •••• - , '.• o;-_ :, 1 7 V . _. E,....,,,,. WeS1 Main SI t " o ao•--j-1. • . '"---t" • .: ,' O; a, opto(lo) • t 1I1 • . I v filliss/*4 41 wt,-• 2ODUa-tB0onia'2-E,inV0%R. 2I.4O.1 : .. 19iit . 1 l M - I - _ . 4 . _,,,,,......41Kirris:..,-•-•..., •. , . , .. . __ - - • - --.... • ' 7 ck' ;11 4.1' • ; ' - • . '... r of (4.4"' Jeffersd , . ' •--' . ' Rorrnin• orlslIng No liorldrio o1on, snow rosle• -' sign ond pool. Inololl new poll oncl R4-11 Collor ol Ito Perking otor. shod be 7' above .- sign. RAnololl No PorkSig *Iv unclor R4-11. finished wide. Rolnotal 5rins Robb. oIgn on _.. :"`""""................, peel blow No Poldnp Hon to lb* oast. .7"14% .• , . iv , , 1. .. 2 . Rofecole Snow Stosita • .. 41 I.4. . ..... ..., 41 1• ' , %, t,,..,-, , ' " g i SIgn lo . • 411. , eit 71.14iNiE 11.10 pool. ' . ... : // w f .1. ,,e• . ..../ - . I . 1 , li . r i a • •44. , •=.-._.-..,_._ i Ift4 -II, 3.0'430. ; .....- le ) I -. • e- - . . ..,,,••••'f' ` . ...: -1 ......."440mos„...,-.."100.4..41111.C1:1131:11.::6 r -:"p 11--„,.6.---. :8 ' k''' ' • .e.,,.., "'-4 ..'..' ., , ''. _.... ---1111kiiiii4, ' • II. , .1" laa. ._, Sharron ornbol (40 h-ssier , ' SlIttlf RINSER 1 2 of 1 e 11 fi7J" W 01.111.11111 SACC; kvnm+ Ile Trucks eland placard cad post. MOO new poet and rruy ndra ran. rran.6al Nn Mucks ran and placard anew Wo,dlall a .lad. 1 ."1 d,Dalin. of plo_erd la def NO aLore tap a curb 1 HSI 1 ra Mount to street light pee u.rnd eldnlose stew strops , �sharrae .t.nhw Menet la stip' Iloht pale under° -'^I' 1 Shan Cita 1611.1 alga wry- 1I 140001111 IWO.trop. i I{ ,rad 4 RI °1rr lllllll • #6).4 1,AV 111 PRESTON 6,4, PIANO l • HIMONIl e P4-200701024 "`4H 1NAt,s',�`S\d~� 67,00070:—. r. 0 0 z 0 'EL 4r VI $tIrfT NUMBER 13 of 17 END WAYFINDING SIGNAGE r 9` 4-0.2 Downtown Jefferson City 0.4 East Branch. Greenway +0.9 ..' Community Park Wayfinding Destination BEGIN Begin Placard 27 1' Wayfinding Direction Wayfinding Direction Wayfinding Sign Colors Pantone 1815 Pantone 314 SHARED BIKE LANE YIELD TO BIKES Shared Bike Lane Sign iv End Wayfinding Signage* CAD MAY USE FULL LANE R4-11 30"x30" W11-1 30"x30" SHARE THE ROAD W16P 18"x24' 70 Wayfinding Direction Wayfinding Direction Mol., 1. Paint 1.1. laryMva g land 0400 be 0.00' Itdcb 44(n48In m) aluminum MIN tetrar.lI.0M Min faces dIWlady printed bah UV -cured Ink. 91140 Sop. Enablers Gad* Regally. Shoreline. °rena7.e MI 10.n.p.r na Alm. 1.2. Shared Me Lanz son.. Beath p1.mrd. and *tendon/ Man. .haw mn..t the r.9 Pan'0Me Of the .UTOO and /NWT. 2. Parte mal be da.eMa d U &emit (S b. pre foot) m. 2' advent/ea wore perforated (12 gouge) 00.1 per elph eched4. 7. Modena andel b0ndlnq art hardware M accordance 81th 0001701 standard 803 Mall b. Lend to mount .lane la the 0adsdng II9ha pates. 4. The 19pe100a 1Thr the oeynndfn9 slpns mm be 0.0844... 0. sign 100900048 *huh 10081(1 fond map .000»9. for Theta.. 0. 011181 ortsah nal be prmlded. 7. Sloes mall be located .0 than the lon..t point o, the .lad or group of sign. M 7' minimum above the e.9so4./4arb. * End 4ayllndhh0 San04e Mon may h. Mooed 0t 0' .above tha elkKent curt,. 0 Same Mone ea he mounted In point or sal be maunt.d .181 .sfstIng/rMocated M9ne. The 00110041.' mop Insure the proper post length to accommodate 00 Mone dated on the syn «nodule one noted an the dans. 9. dhoti/1,411M of .0.4110, to be approved by the .mamma. Revision and Descriptio d 0 0 z Fe a, 011. en.a., •a r940(01101e1 *MU 040040 14 of 17 _ 0.7 DownMyer, J4elln rdy. +0.4 £13148rontrt Green...my 27 +0.6 bownlown lefersonCily +1.1 nua &cosh Greermoy 2 02 4 Downtown InlInnon COY CM Wears Geld, Greenwoy 41.3 Palk 6 44 30 8 45 (1.1 4 wouti Crock Gtonnyeay +0.3 OXd munichb440 33 niy 3 4: 3 +0 7 1 nil e106011 G.0 7 r.ommultly +1.7 1nn14,.: 35 10 46 Downtown jellenon 6217 +0.6 &mit Moen Gmenway +1.2 COrrIRROVY Pak 11 4 Grc6nwoy 1.7 MO Zyry06& PeclestfmnIkidge 38 16 04 Wont; Crook GloOnwpy 0,0 4 Wo4k310111" Park IV) AlOr10 13 17 40.1 711.00/4 Cloak Gtecomoy +1.6 iMmtinglon Ptak +3.7 Ko.y Um, 49 18 0.4 4 Goymlavon Jalknion Cry OM- 4 Eotl IN cinch Gartmwae 9 .1 Commaray Poet 14 I • • Fog Rdonch • Grato.nuy . 1:1-5 4 C.009110(41Y Pk 50 22 +119 Wcnnirmlnn ram _ 1.7 Knly hal 23 15 26 31 34 Revision and Descripvon: .4 al bo, C and the 1 C5-300 dkrek of fast 5 We‘t tamer 3 8 pea P. !WV.... 7111y7 01.111040 1 5 of 1 7 __,: OCE -0_ _ _- OL :uandunsaaa =small o mm -m __+. sub!s mm «Wa_ .Ica vas (( U OSJQJJr J 93 Miller Street Signs Sinn He Son Nene Van nen Pint 117.. Nai.. 1 wo9A7d119 desUnotlan 21'.40' r equate .o7MA 9 dwthotIon 2r.40' r opera 3 •o7$h4hg dat1Alo7 21'.40 2' epior• 4 R4-11 30.30• 2• .pia. 5 .aynndt9 direction (s) 12'.28• U manna 6 .oy@odg drwUon (8) 12'.28' U cowed 7 194-11 30•.w U marmot 8 .oynndr0 drwlian (R) Ir.28' 9 44-11 30'.30' U monn11 IO woyM4h9 49.Abn (1) 12,29 U chorine I1 .0)thdn9 01111nc1fan 21'3140 r sorsa 12 R4-11 30'40' U dialog 13 .asnna79 destballan 21'.40' r .quare 14 .oyM4hg destination 21'x40 r swot. 15 .414109 4esthoU81 21•.40' r ower. t8 .27900109 49.0tran (R) 12128' U Mould Ink R4 -Il 37%30' 17 .o)+hlhg dr«Uon (L) 12.29 U channel 18 .0)rr,dh9 oration (L) 12.26' 19 R4-11 30%30' U Monne 20 9ogIn proceed 10.6' 2• .9002. 21 Snored like Lan. 30.020• .es oboe. 22 .a)4,ong 4rw00n (R) 12.29 U dsonnol 23 wo"dh9 enation (S) 12.2r U Monne/ 24 Snored BA. tan. 30.119 25 ad.d BA. tan. 38•%18' 28 .oy4dhg dredger (S) 12•.28' U drone 27 .o71rndkp 4eslha00. 21•1.40' 28 gored B2s4 Lan. 39.10 29 Shored Moe Lana 36'%19 30 .oyMdhg desthotlan 21'%10' r .9001. 31 .o)4nd,g 4roe0on (S) 12'.29 U channel 32 Shad 09. Lane 39,19 33 Shoed BA. Len. 39'.18• 34 *0)7Ndh9 ?Wootton (5) 1241• U channel 35 .ay6ndh9 4..100081 21•■49 r swore 30 B.g1n piword Iger r 19002. 37 Shored Me Lane 36'.19 .so mow 30 ••N10dhg deslh.tb. 21'x40 2. laud. 39 Sigh pl.odd Woe r •90• 40 shored Mos Lw. 30• l0 sou more 41 .971ndh9 direction (R) wear U axone/ 42 50180 placard 19x6 43 snared 87s. Inn. 3V.15 44 .0y6ndp 4W.c0on (L) Ire25 U 2Inonnn2 45 .ay1ndo9 dooUon (L) 12.28' U dwa211 46 weslsndhg dr«tion (R) Ir.28' 47 R4-11 30'1130' U 090.44 48 84-11 39.30• 49 .ayMdig do21.00.0 21•x40 r .goon 80 .eytnding u/tr 01100 21'40' 2 swd. Stan 10 he located across Oun711n Street ham ra1h.00 Co-I000to on nae pool wish .dsing Parking sign Mount an .24.029 U monn.l post co -Iowa ono nes pool .Bas wasting parkin sip Mount on .roll Opt pol..Rn stalWn steel strops Mount an .trw1 Opt pots .On stables. nod .raps Mount lav gored 1991. lm' Non Mount bolas Begin placard Co-haate an now post .1112 ..10(5,9 SP3O dpi Mount on .rte COW pol..n0, Cold.» stool *traps Mount an .rest I19M pole Atte .1,9411, .rod strops Co-boate an n.st post with existing Pok1n9 .lgo Mount an .wet Apt pd. with denies. nod .raps Mount an .trot fight pole .sin, .10110» .ts2 *raps Mount an etre.t light pole with dakdos. ohne strops Co -local. on nn post with .d.t5,9 Pmkh9 Non Mean! an *root light pd. clow ..Ming p0180429 .ion .tth .1,84.ss .1411 Amp. Mount an sired tight pee wilt skidoos 0(44* strops Mount oboes Shoed Bits Lan* 019n Mount bolo. 1.910 plowrd Moans more Shared Bke tar,. sign Mount holo. Birgit placard 9oun1 81 street right pee with stohl.ss stool strops oboe. Shared BAs lane alp Mom( on strut 129f,1 pale with 'tondos. sed .trop. bobs Begin 91aoard Mount an *rout tight pd. with .tutees..l.N strops Mount an strut Ugh! polo 1902 elondoss .lad drops West Main Street Signs Moa No Stan Name S1gn Run Pmt Tone Notes 61 W11-1 30x30' r soya. 02 080-29 19924' 00• 0000. w .o74hdr9g 499128, 12x20• u chard 93A End Wo71hdh9 S1gdrg• Ir.12' 8» ohm 54 .aylrWhq erection (9) 12'.29 U chanty 66 W11-1 30•,30 r sgaara e0 W20-19 18'.44' .0 doers 57 R4-11 30•.30' U cho n, as .oytrd109 Arwllen (5) Mate* u chane 69 .o7trW129 direction (s) 12'49 r epwr. 60 84-11 30o30' r pacts 61 .e7awh9 d.Uon (s) Mae' u mane e2 wayr1dhg d*otran (5) It.29 r seen• O3 R4-11 30.130' so. ribose 04 .gOn4109 dr.0tw, (s) 12130• U dialed 63 R4-11 30',37 r sgta. 09 R4 -I1 37.30• U channel 07 .2)140109 dredtw11 (5) 125530' U mans 06 .0)1,1419 db.olbn (5) 12.30 u droan11 09 .o7nwrg drwtwn (5) 12a3o' U chanted 70 coy ceng *action 12230' u mond 71 R4-11 30',30• U channel 72 .01.019 Week., (s) 12.30' U channel 73 04-11 37.37 U eland 74 .ayOrdhg drreatbn (5) 12,.70' U Mdn11 76 .0ythdh9 dr.0lbn (5) 12'037 U shown 76 84-11 37.37 U channel 77 W11-1 37137 r rem* 75 WI11-I9 19,24' .w mow 79 wgtheh9 direction (S) 12.29 r egad. CO .aythdh9 direction (S) Ir,28' 51 84-11 37440 el wa7nnd,9 dr.ora, (U) 12.29 Mount chore 4026-19 Mount holo. 0111-1 s.. plan for olio. 4u79n Mount Wo..0)n,dh9 drwtton 11^ sign mer h. goc.d 01 a• o1or. curb Co -locate an now peat .21 wl.lhp No Parking .I90 Mount obese 915-19 Wont lido. 1111-1 Co-l000to on nes post .U, .,ddling No 902kh9 don Co-boote on noe post with .11.1119 No Truk .295 and plop. Co -boots an nes post with .dsUn9 No Pattie 1195 Co-fooAe on nn post AN .dsUf9 No Pasdt9 sign Mount chow 94-11 Mont hen ..7mdhg dwlland Co -haute on now post .WU, edo00g No Truck at9n and plague S.e plan to anew d.slp2 Mout chose 009-19 Mount Odes 821-1 Co-IOOo*• on now post with M.tn9 No Mount to 9010.! light pots nth Corer». Mont to *Use light polo nth .beds. Mount to .test tight pd. nth 020900es Truck sign and plop,. . 1.N .reps h oe strops d.d etrops tlom*ntinB1llII 4'�pFM/Sss y.pAVID PRESTON le, NUMBmi 1.13-2007020241 Revision and Description: 4) 6 Z 3 s 20 1 1 o.•41 P. 14444 2'1. M-2»2070141 1N0tT NUMMI 17 of 17 Memorandum 320 East McCarty Street • Jefferson City, Missouri 65101 • P: 573.634.6410 • F: 573.634.6562 • www.jeffersoncitymo.gov Date: October 8, 2018 To: Public Works and Planning Committee From: David Bange P.E., City Engineer[ J Subject: Ranking of Transportation Alternative Program (TAP) Projects City Staff would like the Committee to rank the two projects which are being prepared for submission for possible TAP funding. Staff is recommending that the W. Main/Industrial project be ranked first and the Missouri Boulevard project ranked second. TAP grants support a number of types of projects with a focus is non -motorized transportation. This grant opportunity is part of the federal highway bill and applications are accepted every two years. If chosen the grant will pay for up to 80% of a project's cost with the remaining 20% coming from the applicant. The West Main/Industrial project entails the construction of sidewalk along parts of West Main, Jaycee Drive, Industrial, and part of Truman Boulevard with a short stub projecting down Highway 179. The sidewalk would begin on West Main Street at Belair Drive which is the current termination point of sidewalks that connect into the residential areas along Belair, Boonville, and Hayselton Drive , among others. From there it will pass through Jaycee Drive and westward along industrial Drive through Highway 179 and down Truman Boulevard to the Range Nature center. This project will serve several goals including the connection of a residential area to commercial establishments on Industrial Drive including grocery and retail stores as well as connection to the extensive recreational opportunities offered at the nature center. Secondly it would facilitate a transit connection point by providing a signalized pedestrian crossing of Highway 179 at Truman Boulevard. This would allow transit riders from what will be known as the Yellow Route (High Street West) to transfer to the Black Route (Capital Mall) along an ADA accessible route while adding bus shelter facilities at these locations. The subject of the other application is a continuation of the construction of sidewalks along Missouri Boulevard beginning at Beck Street and extending to St. Mary's Boulevard. This project will connect five existing bus stops and would create a continuous sidewalk along the northern side of Missouri Boulevard from W. Main Street to Stadium. The project would include the addition of two signalized pedestrian crossings, one crossing Dix Road at Missouri Boulevard and the other crossing Missouri Boulevard at Stadium Boulevard. This project would be the culmination of a number to projects to provide sidewalks along this important commercial corridor. If you have any questions I can be reached at 634-6433. DB:db L1:\Public Works\EngineeringldbangelPUBLIC WORKS & PLANNING12018110-20181TAP Applications docx lepoN-ueld a}iS .pA18 urlossIW W. Main and Industrial Site Plan -Model ART LETT WEST SERVICE. THE LDARTLETT & WEST WAY. February 24, 2010 Mr. Matt viorasch, P.E. Deputy Director for Public Works City of Jefferson 320 E. McCarty Street Jefferson City, M(7 65101 Re: BEAP Project 09LTAP-34 Bridge No. 2180003 High Street Viaduct in the City of Jefferson, MO Dear Mr. Morasch: We had opportunities to visit and view the bridge noted above and shown in the figures herein. The High Street viaduct is located in the City of Jefferson approximately 0.5 mile south of the Missouri River bridges. This structure has been open to traffic since 1950 when it (Bridge No. 1.148) was constructed as part of a project administered by the Missouri State Highway Department on the behalf of the City and funded by city, state and federal governments. Figure 1: The High Street viaduct constructed in 1949 and 1950 (at a cost of $783k) replaced the Thomas viaduct built in 1913 (at a cost of $26k) to become what some reports called the City's new landmark. The observations summarized in this Bridge Engineering Assistance Program (BEAP) report support the conclusion that the bridge should be rehabilitated rather than widened or replaced. However, it is also recommended that the City begin the long-range planning and budgeting process to replace the bridge by including the project in the 2030 Metropolitan Plan for the Capital Area Metropolitan Planning Organization (CAMPO). Specific repair strategies are described in greater detail on pages 10 and 11 of this report and are similar in many ways to the repairs made in 1985 by contract (i.e., not by the City's forces) as a City project. In summary, we recommend that the following bridge components be repaired: Superstructure: Repair as needed the concrete overlay near the expansion joints, the curbs on each side of the bridge and the bearing areas of the cast -in-place concrete tee beams. Treat and protect concrete surfaces by applying a penetrating sealer to the concrete deck and an epoxy sealer to the curbs. It is not recommended that span 11-12 on the west end of the bridge be realigned to its original position as was recommended, but not done, during the 1985 rehabilitation work. Expansion joints: Replace all 17 expansion joints at the intermediate and end bents. This work must be done if repair work to the substructure units is to have any lasting value. Substructure: Repair the deteriorating portions of 12 substructure units with many of the intermediate bents on the bridge's east end needing the greatest amount of repair. Treat and protect the concrete surfaces closest to the joints by applying an epoxy coating to the plan -defined areas generally described here as the entire beam cap and a portion of the columns. The full engineering and drafting services needed to provide contract -ready documents for these repairs are beyond the scope of this BEAP study. Any major rehabilitation work done to the bridge makes the structure ineligible for federal funding for 10 years even if it is funded locally; the repairs listed above do not constitute a major rehabilitation. Until the time that the bridge is repaired or replaced by contract, it is recommended that the City: a.) monitor the concrete deck, curb and substructure units for increased cracking, spalls and delaminations, b.) repair the existing deck overlay with concrete or approved accelerated mortars when necessary, c.) consider protecting the deck with a penetrating sealer such as Pavon® Indeck or Star Macro Deck to be applied every 3 to 5 years, d.) periodically clean and maintain the expansion joints, and e.) continue to remove drift that may accumulate at the intermediate bents. Existing Bridge Information The High Street viaduct has a posted speed limit of 30 m.p.h. (20 m.p.h. in front of St. Peter's School), does not have a posted weight limit and crosses Missouri Boulevard, Wears Creek and a spur line of the Union Pacific Railroad (UPRR). High Street, classified as an "Urban Minor Arterial", currently carries approximately 5685 vehicles per day and is projected to have an Average Daily Traffic (ADT) count of 9380 in 2027 according to the National Bridge Inventory (NBI) Structure Inventory and Appraisal (SI&A) Sheet. The two-lane roadway approaches lead to an 867'± long bridge having a 26'-0" wide roadway and carrying two lanes for two-way vehicular traffic. Both the west and east approaches have wider roadways (curb to curb) than the bridge, but the additional widths are utilized for parallel parking. The bridge's substructure units consist of parallel retaining walls and a hollow abutment at the east end, a vertical wall abutment at the west end, and 11 intermediate bents that are founded on pile footings. The superstructure consists of 6 lines of cast -in-place concrete tee beams with 5'-0" wide sidewalks, 18'/" tall concrete curbs and 3'-0"± tall galvanized steel handrails on each side. Each of the 12 tee beam spans are simple spans with the first 10 being square (no skew) and the two western -most spans varying in skew to accommodate the two sets of railroad tracks undemeath. The bridge is inspected every two years; a general inspection was last done in January 2010 and an underwater inspection was completed in July 2008. The NBI SI&A condition ratings for the deck, superstructure and substructure are 6, 6 and 6, respectively, on a scale of 0 (failed condition) to 9 (excellent condition) with a rating of 4 or less for any one of the condition ratings making the bridge "structurally deficient". The condition ratings of 6 (satisfactory condition) are consistent with if not better than other typical bridges of this vintage and can be attributed to some degree to the lower traffic speeds and relatively little truck traffic. The horizontal alignment of the roadway approaches is good (rating of 7 for Approach Roadway Alignment) and the "Satisfactory Condition" rating of 6 for the Channel Protection evaluation indicates that among other things, that there are minor issues with slumping banks, creek migration and drift. The Scour Assessment's rating of 5 indicates that the bridge foundations, although they have been exposed by scour, are stable. The Waterway Adequacy's rating of 8 signifies that the bridge is above high water and that the approach roadway has a slight chance of being overtopped. The flooding evaluation is consistent with reports that the viaduct remained open during the 1993 flood and served as a critical connection to the downtown area. The current Structural Evaluation rating of 5 ("somewhat better than minimum adequacy") indicates that although there aren't any weight restrictions currently, the bridge does not have the same structural capacity as newer structures. The bridge's current rating of 3 for deck geometry is "basically intolerable requiring a high priority of corrective action" and makes the bridge `functionally obsolete". The 2030 Metropolitan Transportation Plan for CAMPO indicates ADTs of 4775 (count in 2005) and 6980 (projection for 2030). For both the 2001 to 5000 and >5000 ADT ranges, a 28'-0" roadway would increase the deck geometry rating to a 4 and the bridge no longer would be considered "functionally obsolete". MoDOT's intent regarding federally funded bridge projects is that they remove all deficiencies and that the bridge be reasonably expected to last a minimum of 25 years before developing any significant deficiencies. Consequently, federal funds can't be used to rehabilitate the viaduct unless it were to be widened by at least two feet to the 28'-0" width that would remove its "functionally obsolete" deficiency. The totality of the structural, functional and condition evaluations currently results in an NBI SI&A sufficiency rating of 66.5% and indicates that the bridge does qualify for partial federal bridge replacement funds (80% - 20% split) because the bridge is "functionally obsolete". Consequently, the SI&A does provide a recommendation to repair the general deterioration by rehabilitating the bridge with work done by contract (not by owner's forces). In the absence of City - specific information, the SI&A's cost estimate was developed by using nation-wide averages for new, widened and rehabilitated bridges. The SI&A's estimated total project cost of $1,884,000 (150% of bridge cost) is comprised of bridge work ($1,256,000), roadway improvement work ($125,000, or 10% of bridge cost) and incidentals. Additionally, the Non -State Structure Inspection Report prepared by MoDOT mentions the structural components (deck joints and concrete overlay) having notable deterioration and recommends possible methods of repair. 2 Field Observations Observations were made from on and around the bridge during the visual inspection opportunities. The descriptions and documentation of specific conditions found are summarized as follows: Figure 2: View from cast of the viaduct that carries rvo lanes of vehicular traffic, pedestrians on two 5' wide sidewalks, and was part of the hike route for the 2008 Tour of Missouri. Figure 3: 'West approach narrows from 36'-0" (curb to curb) in front of the fire station to 2G'-0" on the bridge. 3 Figure 4: Neoprene joint seals installed during previous repairs vary from good condition (left picture) to essentially missing (right picture) with many in bad shape that allow salt, dirt and moisture to help accelerate deterioration below. f iLrirc l ntprock concrete overlay applied in 1985 needs repair in man locations, most often at the joints, 4 Figure 6: Locations of spalled concrete and exposed rebar often found along the curbs are more of an aesthetic issue than a structural or functional problem. Cracking of the 1985 overlay is worse in the eastern spans than to the west. Figure 7: Sealing of overlay will slow the deterioration but saturation of the concrete tee beams can't be reversed easily. 5 Figure 8: Sealing of overlay will slow the deterioration but cracking and leaching of tee beams can't he reversed easily. L ,}: 1 )1Thr,}i=ms and bc,inng areas of some deterini; 6 u�ct shutvs a hearing :u cast abuttnrnt. Figure 10: Spoiling and cracking of beam caps and columns along with the efflorescence found at many bents. Figure 11: Previous and future repairs to intermediate bents can only be expected to last 10 to 20 years±. Figure 12: Intermediate bents along and over Wears Creek get much taller and will make repair work more difficult and expensive. Drift and other debris restricting flow in the channel should be removed periodically. Figure 13: Span 11-12 has shifted duce to temperature fluct rations and the change in bridge skew needed to better align with the UPRR. The 1985 rehabilitation did not reset the span but did take measures to prevent future movement. 8 Figure 14: The inspection report indicates that the concrete tee beams have cracked and spalled near the steel brackets added to intermediate bent no. 12 in 1985 to prevent continuing and accumulating movement of spans 11-12 and 12-13. Figure 15: Remnants of an unreinforced concrete retaining wall intended to provide bank protection along Wears Creek. 9 Superstructure Repair At an estimated construction cost of $187,000 shown below, the following construction activities will be required: • Remove any existing asphalt patching material and all deteriorated concrete. • Repair the existing 11/2" overlay with a qualified concrete or special mortar in accordance with the specifications. • Apply Protective Surface Treatment for Concrete — Penetrating Sealers to the concrete overlay in accordance with the specifications. Penetrating sealers such as Pavony' Indeck or Star Macro Deck are often applied by cities, counties and illoD( )T to their own structures rather than through contracted work. • The curbs can be addressee) with either of two options — repair the curb to its as -built dimensions or build up the curb to a slightly bigger area. The additional area of a "blockout" would be mechanically attached to the curb with resin anchors — the repaired curb's concrete would rely on bond to the exposed rebar and may not last as long. • Clean and Epoxy Seal the concrete curbs and other surfaces around the drainage systems in accordance with the specifications. Quantities for concrete repairs commonly run over their estimates because of rhe inherent difficulty in determining accurately the structural integrity of large areas of the structure. Areas of deterioration are often estimated by sight only or with non-destructive methods when significant portions of the structure are accessible. For comparison purposes, 9875.3 ft2 of deck repair was done in 1985 (3300 ft2 had been estimated). The sealing of the deck to address the cracking of the existing 11/2" overlay should be given a high priority because it is relatively inexpensive and would serve to protect the $417k investment made with the 1985 rehabilitation project - $310k of that investment was for deck repairs and the concrete overlay. Significant changes to the overlay, either through an additional overlay or as a removal with a replacement of an equal depth, are not recommended at this time. Consequently, there are no changes to the bridge's load ratings. Repair Item Estimated Quantity Estimated Cost Expected Life Repairing Concrete Deck (Half -Soling) 200 Square Feet $10,000 10-15 years# Repair the Curb or Construct a Curb Blackout 850 Linear Feet $102,000 Clean and Epoxy Seal the Curbs 7000 Square beet $42,000 Superstructure Repair — Bearing Areas of Tee Beams 100 Square beet $13,500 Penetrating Sealer Applied to the Roadway Surlacc 2420 Square Yards $19,360 3 to 5 years ZN & A 1:0‘../ /p.. tool \L e.1 xc%. R,...1..,,,,.06 /n /,.. ., , . . . .• Y•c orVat/--i i ' ' 6`,.1...14..•• uenlr- alletfs ,yrs ..e • /Wal+ --,s: c,.,..., . ,, ,,rte .w,Jy or'.nJob ICrINiR 1,,,11,11/C '....,44,10^�' �� At''.:,.n ,;'-,,S1 •;<. ,rnu. C� HALF SECTION NEAR END SPAN ht -1r 7r_E uEal"1 :; I r-- t is..e. 0 Figure 16: Details of repairs to concrete overlay and curbs Replace all 17 Expansion Joints At an estimated construction cost of $150,000 shown below, the following construction activities will be required: • Remove the entire length of each of the 17 existing neoprene joint seals that hacl been bonded to concrete with epoxy. • Install the new expansion joints using the manufacturer's recommended procedures (surface preparation, etc.) and materials (two -component rapid curing liquid polymer and two -component silicone rubber sealant used for l0 the X.J.S. option illustrated below). Expansion joints like the X.J.S. system have been installed by those agencies owning and maintaining bridges, but it can be done under contract as well. Repair Item Estimated Quantity Estimated Cost Expected Life Removal of Concrete Overlay and Existing Joint 410 Ft2 and 17 Each $10,000 10-20 years± X.J.S. Expansion Joint System 700 Linear Feet $140,000 • :6vf Typ .tcw i Irapra;: N/ear,ng 3u, ,1.-2,-<7 .• 1 1...(a.,ea Neopcerne_ •)01.-/A SeL\t (_arei,ng ?ono,e!c deco and end drophrogr'n - 5o.vcu l Z` ope n, nye and eoo,y neoprend •1o,nt xoi Ira p'ace Po., 09991 90: R(. S ketol Scalam Say.. 900 PNS ) (39atm•99mm1 C'wrcra,c X.AS. Ek'nsld., si'e.w Figure 17: Details for the existing neoprene joint seal (left) and for a new expansion joint like the X.J.S. system (right). Repair of End Bent No. 1 and all 11 Intermediate Bents At an estimated construction cost of $273,000 shown below, the following construction activities will be required: • Remove the delaminated concrete in accordance with Section 704 of the Missouri Standard Specifications for Highway Construction. Per Section 704, the type of repair for the specifically defined areas will be outlined by the engineer during construction. • Use formed and unformed concrete repair of the delaminated and spalled areas. • Use Protective Coating — Concrete Bents and Piers (Epoxy) on the plan -defined areas of the beam caps, columns and diaphragms in accordance with Section 711 as protection against future deterioration. Quantities for concrete repairs commonly run over their estimates because of the inherent difficulty in determining accurately the structural integrity of large areas of the structure. Areas of deterioration are often estimated by sight only or with non-destructive methods when significant portions of the structure are accessible. For comparison purposes, 267.7 ft2 of similar type repairs were done to bents 2, 3, 4, 5 and 12 in 1985 (200 ft'- had been estimated). Concrete repairs in vertical or overhead applications have a much better chance to retain their integrity if a sufficient amount of clean reinforcement or other means of mechanical anchorage is available. If it is not, the newly applied concrete will have a shorter duration of effectiveness before it delaminates like the concrete that has fallen or been knocked down to the ground. Repair Item Estimated Quantity Estimated Cost Expected Life Substructure Repair — Formed and Unformed 1100 Square Feet $250,000 10-20 years± Protective Coating — Conc. Bents and Piers (Epoxy) 7500 Square Feet $22,500 • 4 Ei_(vA,117N 0( (XI',(ING INI(R40()l All F1 •t, CN0'„ ::1t. 11(:h 0( IV((Ru( IOAT( NEN1 Figure 18: Example details for substructure repair. 11 Bridge Replacment (Future Work) .1 (oral replacement of the bridge is not warranted at this time but will become a more and rune cost-effective option as the frequency of rehabilitation projects continue, to increase. For comparison purposes, the estimated cost of a new bridge (W-8" wide out -to -out by 867'! long) that could be expected to last 50 w 75± years would be about S3,500,000. The 41'-8" width would provide a 28'-0" roadway with 16" concrete barrier curbs, 5'-0" sidewalks and a pedestrian fence on each side. The following arc among the items that should be considered during the planning for and design of a new bridge:: • Wears Creek hydraulics: 1 Flood insurance Study has been done for this area- • 'i'Itc roadway width (curb to curb) needed for the desired level of service fur the traffic on West Fligh Street and the impact of a potentially wider bridge on High Street's connections to Missouri Boulevard. • The roadway width needed for the desired level of service fur Missouri Boulevard traffic and its impact on the span over Missouri Boulevard and on the adjacent bridge (no. 2180(104) over Wears Creek built at the same time as the viaduct. • The necessity of replacing the bridge given many alternative routes. Both McCarty Street and Main Street have at -grade intersections with the railroad and likely are more susceptible to flooding. • The proximity of the fire station to the t-iaducr. • Need for, number of, width tf,and east .end connectivity o(sidcwalk(s). • list. ylechanically Stabilized 1 .artlt {AI 1•.) walls at each end of the bridge. Ilse a II -shaped wall at the cast end with one portion moved closer to Missouri Boulevard and with two parallel walls along each side of High Street that end close ro where the existing cast -in-place retaining wails end. • Length :and grade of bridge: The lilt'.± existing length could be reduced by ntuvtng ilte east abutment closer to Missouri Boulevard. The 4.5'!"0 grade would have to be maintained although a long, relatively steep bridge is not ideal for pedestrian purposes. The Thomas viaduct had terminated at Walnut Street (now Illissouri Boulevard) and its steep grade (90/4.) reportedly caused problems. • Clearances (vertical and horizontal) to the railroad and Missouri Boulevard: the current vertical clearance to the F11'ltli is about 22' ro the tee beam superstructure (4'± depth) the railroads typically want ;t minimum of 23'. The vertical clearance to Missouri Boulevard is not shown on the plans or the Sl&.1 -- it is estimated to be 15' to 17' to the 4.5'± deep tee beam superstructure. • Coordination efforts with the railroad. • Location and ts'pcs of expansion joints. • Type(s) of superstructure: a series of shorter, shallower concrete spans at each end (over the UPRR and Missouri Boulevard) with a series of longer, deeper spans (concrete or steel) over Wears Creek is a possible scenario, • The need for and cost of lighting. • The need for and cost of architectural enhancements like form liners and ornamental fencing. • Tall intermediate bents requiring larger diameter columns and bigger footings will be more expensive than a typical crossing's substructure. The repair and replacement costs described and shown in the tables above are bridge construction costs only. Costs associated with engineering services, desired roadway and/or sidewalk improvements, traffic handling, utility relocation efforts, temporary construction easements, railroad protective liability, insurance and contractor mobilization are not included. 1\'e appreciate this opportunity- ro he of service to the City of Jefferson under the Bridge Engineering Assistance Program. Please call should you have any questions. irtcppperely IdA IC` Chris J. Criswell, P.F:. Cc: Mr. Dion Knipp, Moll( - District 5 Mr Icff .\holt:, ltilol)f)T - Bridge Division I2 ' CHRISTOPHER J. CRISWELL NUMBER E-28605 . Memorandum 320 East McCarty Street • Jefferson City, Missouri 65101 • P: 573.634.6410 • F: 573.634.6562 • www.jeffersoncitymo.gov Date: October 8, 2018 To: Public Works and Planning Committee From: David Bange P.E., City Engineer goJJ Subject: Pedestrian Crosswalks at Thorpe Gordon and South Elementary Schools Staff has been asked by the Committee to provide information regarding the pedestrian crosswalks at Thorpe Gordon and South Elementary Schools. The crosswalk at Thorpe Gordon is located across Jackson Street at a point where the street transitions from two way traffic to one way traffic. The crossing is currently 48 feet wide and parking is restricted within 125 feet of the crossing. The crossing is located just below the crest of the hill in the direction from which the traffic is coming and sight distance to the crossing is in excess of 400 feet. The posted speed limit is 30 mph and is reduced to 20 mph with a flashing speed limit sign during school arrival and dismissal times. Staff have not had the opportunity to observe this crossing and thus do not have full knowledge of the issues particular to this pedestrian crossing. However, given that at the location of the crosswalk the street carries traffic only in the northbound direction the width of the street far exceeds what is necessary for the traffic. The crosswalk at South School is located across Linden Drive. The street is approximately 31 feet wide and parking is prohibited on the south side and within 70 feet of the crosswalk on the northern side of the street. Like Jackson Street the speed limit is posted at 30 mph but is reduced to 20 mph during school arrival and dismissal times. Sight distance from both directions is approximately 300 feet. During the planning of the construction of a sidewalk in the 900 block of Broadway Street Staff spent time observing this crossing. At that time it was observed that during dismissal time cars from both directions would begin to line up along the curb line of both approaches to the school driveway. This creates a very congested area around the school and while it creates visual impairments it correspondingly reduces speed through the area. At the time of the observations students gathered in a group at the crosswalk and with the direction of a school staff member would cross the street in a group. The procedure appeared to be very safe and efficient. Given e-mail exchanges with representatives from the school district it appears that they are seeking improvements to these crosswalks. In the past, such as with the crosswalk that was installed on Dunklin Street at the Employment Security building, the City has provided the design and project U:\Public Works\Engineering\dbange\PUBLIC WORKS & PLANNING\2018\10-2018\School Crosswalks.docx Memorandum 2 oversite for the improvements while the costs were covered by the requestor. In that case the cost of the improvements which included bump outs, signage, and flashing lights was a bit over $40,000. If you have any questions I can be reached at 634-6433. DB:db U:IPublic WorkslEngineeringldbangelPUBLIC WORKS & PLANNINGI2018110-20181School Crosswalks.docx WE NEED YOUR INPUT CAMPO 2045& CAPITAL AREA METROPOLITAN TRANSPORTATION PLAN OPEN HOUSF Jefferson City October 10th 3pm to 6pm City Hall 320 E. McCarty St. Jefferson City, MO Holts Summit October le 4pm to 7pm City Hall 245 S. Summit Dr. Holts Summit, MO WWW.CAMPO2O45.COM The Metropolitan Transportation Plan is a regional long-range plan that sets goals and defines strategies to meet the transportation needs of the Capital Area. The Capital Area Metropolitan Planning Organization (CAMPO) includes Holts Summit, Jefferson City, St. Martins, Taos, Wardsville, & portions of Cole and Callaway Counties. CAMPO campo@jeffcitymo.org (573)634-6410 CAMPO does not discriminate based on rate, color, sex, age, disability or national origin, in accordance with Title VI of the Civil Rights Act of 1964, and the Civil Rights Restoration Act of 1987. Please contact CAMPO for the Title VI Complaint Procedure and a Title VI Complaint Form, also available at www ieffersoncitymo.govicampo. Individuals should contact the ADA Coordinator at (573)634-6570 to request accommodations or alternative formats as required under the Americans with Disabilities Act. Please allow 72 business hours to process the request. DEPARTMENT OF PLANNING AND PROTECTIVE SERVICES MEMORANDUM TO: Public Works and Planning Committee THROUGH: Sonny Sanders, Director of Planning and Protective Services FROM: Jayne Abbott, Neighborhood Services Manager DATE October 5, 2018 RE: CDBG 2019-2023 Consolidated Plan The City of Jefferson annually receives federal funding from U.S. Department of Housing and Urban Development (HUD), Community Development Block Grant (CDBG) Program. As a result, the City is required to prepare a five year strategic and an annual action plan identified as a Consolidated Plan. The 2019-2023 Consolidated Plan is designed to help the City of Jefferson to assess their affordable housing and community development needs and market conditions, and to make data -driven, place -based investment decisions. The Consolidated Plan serves as the framework to identify housing and community development priorities that align and focus funding from the CDBG program. The Citizen Participation and consultation process for the 2019 -- 2023 Consolidated Action Plan was achieved through a variety of strategies, including an interactive budget -based public meeting, survey, direct correspondence, and outreach to community organizations. All efforts were made to contact appropriate parties and obtain thorough input. These consultations with participation from citizens provided the plan direction and scope. A survey was made available and sent to members of the local Unmet Needs Committee, churches and other organizations with encouragement to pass the survey on to their clients and others who may be interested. A residential survey was also made available. The survey was open from July 20, 2018 until August 21, 2018. The survey requested input to assess the needs of the community by utilizing CDBG funds. The first public meeting was held on August 16, 2018, at City Hall Boone/Bancroft Conference Room. Participants were asked to rate categories including housing, infrastructure, public facilities, public services, by placing stars by the needs of the community. On August 17, 2018, a Stakeholders meeting was held at City Hall Boone/Bancroft. Conference Room. Local organizations discussed effective and meaningful ways to utilize CDBG funds without duplicating services in the community. An emphasis was placed on making the most impact with the estimated annual allotment of $250,000. Through survey and meetings, the following items were identified as priority needs which are activities that may be undertaken in program years 2019-2023: • Down Payment Assistance; • Minor Home Repair; • Public Infrastructure Improvement; • Demolition of Dilapidated Structures; and • Public Services. For the 2019 program year, the following activities will be funded through CDBG: Program Priority Needs Addressed Outcome (# Assisted) Budget Down Payment Assistance Affordable Housing 11 Households $56,078 Minor Home Repair Sustainable Housing 6 Households $15,198 (PI $15,000) Infrastructure Improvements Preserve & Improve Area Neighborhoods; Economic Opportunities 3,000 Individuals $112,541 Demolition Removal of Slum & Blight; Economic Opportunities 2-3 Buildings $45,000 Administration (20% Cap) $57,204 Total: 8286,021 A public hearing was held on September 4, 2018 to present the draft copy of the 2019 — 2023 Consolidated Action Plan. Notice was published in the News Tribune on August 27, 2018. The draft copy of the 2019 — 2023 Consolidated Action Plan was made available on www.jeffersoncitymo.gov/government/redevelopment and grants/plans.php. Comments regarding the draft plan were accepted through October 5, 2018. One comment was received asking to add lighting as an eligible activity. The Plan was adjusted accordingly to the comment. Staff is recommending to Public Works and Planning Committee to move the 2019-2023 Consolidated Plan onto Council to be considered for approval via Resolution during the November 5, 2018, Council meeting. It is anticipated to submit the 2019-2023 Consolidated Plan to HUD on or before November 16, 2018. DEPARTMENT OF PLANNING AND PROTECTIVE SERVICES MEMORANDUM TO: Public Works & Planning Committee THROUGH. Sonny Sanders, Director of Planning and Protective Services FROM: David Grellner, Environmental Health Manager "'7% DATic? October 2, 2018 RE: Cemetery Maintenance Agreement A Cemetery Maintenance Review Committee conducted an interview of the sole bidder for the City of Jefferson Cemetery Maintenance Agreement for maintenance services of Long -view Cemetery, Woodland Cemetery, and Old City Cemetery. The bidder was evaluated on cost, past experience, reliability, and expertise of personnel. Based on the evaluations, AJ. Lawn Care LLC from Centertown, Missouri is recommended to be awarded the Cemetery Maintenance Agreement at a bid of $99,300.00 for the three-year agreement. AJ. Lawn Care Company was chosen because the company has over ten years of experience in lawn care services, has the required number of personnel and equipment to complete the job, and has previous experience in maintaining cemetery grounds at other locations. The first year of the maintenance agreement will cost $31,500.00, the second year $33,072.00, and the third year $34,728.00. Funds have been allocated in cemetery maintenance account (10- 532-540060) in budget year 2019 to cover the cost of the maintenance agreement for year one. City of Jefferson, Missouri Tabulation of Bids Bid No. 3005 Subjuct Cemetery Maintenance Dept: Planning & Protective Services AJ Lawncare LLC Centertown, MO Date: September 18, 2018 ITEM QTY unit Unit Price Total Price Unit Price Total Price Unit Price Total Price Year One Care and Maintenance of Fairview, Woodland and Longview Cemeteries as specified 12 mo $2,625.00 $31,500.00 t Year Two Care and Maintenance of Fairview, Woodland _ and Longview Cemeteries as specified 12 mo $2,756.00 $33,072.00 Year Three Care and Maintenance of Fairview, Woodland and Longview Cemeteries as specified 12 mo $2,894.00 $34,728.00 Total Cost Three Years $99,300.00 Discount for prompt payment none Prices in this bid firm for 90 days Represent Disadvantaged Bus. no Represent Woman-Owned•Bus. no Coop. Procure. Cole Co. yes Housing Authority yes• Vendors sent RFB with no response: Pro Lawn Care, Jefferson City, MO Westco Grounds Maintenance, Jefferson City, MO Enhanced Lawn Care, Jefferson City, MO Schultes Lawn Care & Landscape, Lohman, MO All Seasons Landscaping, Jefferson City, MO Suess Grounds Maintenance, Jefferson City, MO Schrimpf Landscaping, Jefferson City, MO Pro Landscape Maintenance, Jefferson City, MO ) Smoke N Green Lawn & Landscape, Jefferson City, MO Lamberson Lawn Care, Centertown, MO r--- Capital City Lawn Care, Jefferson City, MO Gaines Landscaping, Jefferson City, MO Atkins Building Services, Jefferson City, MO Superior Choice Lawncare, Russellevllle, MO Martin's Lawn & Landscaping, Jefferson City, MO Dans A+ Lawn Care, Jefferson City, MO Forever Green Lawn Care, Jefferson City, MO Advantage Lawn Care, Jefferson City, MO Troesser Lawn Care, Jefferson City, MO 1