HomeMy Public PortalAboutFY2022 CIRP Presentation - APRIL 2021FY 2022 Capital
Improvement
Program -
Proposed
Construction
Services
Rich Unverferth, P.E.
Director of Engineering
April 19, 2021
Technology Overview
•Participants are in listen-and-view mode
•There are several ways to engage
•Type your question using Q/A icon at the bottom of your screen
at any time (even before the Q/A portion has begun)
•Everyone can read all questions posed and you can “Upvote”
questions you want answered
•Ground Rules: General questions only during live Q&A
•Specific project questions should be directed to Allen Muehlher,
AFMUEH@stlmsd.com
Today’s Agenda
•Introductions and About MSD
•Proposed Program –Summary
•Proposed Program –Ongoing Construction
•Proposed Program –Procurements Needed
•Proposed Program –Work Order Repairs
•Proposed Program –Contingency Projects
•Proposed Program –Looking Ahead
•Construction Management Division Staffing
•Prequalification Process
•Small Contractor Program
•Bid Schedule and Plan Room
•Prevailing Wage Program
•Diversity
•Executive Director’s Report
•Questions and Answers
MSD Overview & Details
•Government Utility
•State Constitution
•Voter Approved Charter
•6 Member Board of Trustees
(3 City & 3 County)
•Two utilities: Wastewater & Stormwater
•520 square mile service area
•All of St. Louis City
•87% of St. Louis County
•~1,300,000 customers
•88 municipalities served
•7 Treatment Plants
•350+ million gallons per day of wastewater treated
•4,500+ miles of sanitary sewers
•1,400+ miles of combined sewers
•3,000+ miles of stormwatersewers
•4th largest sewer system in the United States (as measured by miles of sewers handling wastewater)
Proposed Program –FY2022
•Summary
Proposed Program –FY2022
•Summary
Proposed Program –FY2022
•Ongoing Construction
Project Name Additional
Appropriation
LOWER MERAMEC RIVER SYSTEM IMPROVEMENTS -BAUMGARTNER TO FENTON WWTF TUNNEL 48,000,000
JEFFERSON BARRACKS TUNNEL (LEMAY WWTP TO MARTIGNEY PS)35,000,000
DC-02 & DC-03 SANITARY RELIEF (BRENTWOOD BLVD TO CONWAY RD) PHASE III AND PHASE IV 17,500,000
DEER CREEK SANITARY TUNNEL (CLAYTON RD TO RDP) -PUMP STATION 15,000,000
BISSELL POINT WWTF TRICKLING FILTER MEDIA REPLACEMENT 11,000,000
WATKINS CREEK PUMP STATION (P-101) REPLACEMENT 2,900,000
WATKINS CREEK PUMP STATION (P-101) FORCEMAIN REPLACEMENT (COAL BANK RD TO SPRING GARDEN DR)1,600,000
FF-07 FEE FEE CREEK SANITARY RELIEF (MEADOWSIDE DR TO WILLOW BROOK DR)600,000
131,600,000
Proposed Program –FY2022
•Ongoing Construction
Proposed Program –FY2022
•Ongoing Construction
Proposed Program –FY2022
•Procurements Needed
Construction
Category
# Projects Construction
Cost Estimates
CIPP 7 18,654,000
Facilities 2 118,489,000
Pump Stations 4 12,646,000
Sewers 25 57,970,000
PIR 3 1,780,000
Tunnels 0 0
Bank Stabilization 2 1,131,000
Total 43 210,670,000
Proposed Program –FY2022
•Procurements Needed (CIPP)
Project Name Description Budget
BISSELL - COLDWATER - MISSOURI - MERAMEC PUBLIC I/I
REDUCTION (2022) CONTRACT A
REHABILITATE 100,000 FEET OF THE PUBLIC SEWER SYSTEM USING
THE CURED IN PLACE PIPE METHOD, TO REDUCE PUBLIC I/I.4,216,000
LEMAY PUBLIC I/I REDUCTION AND REHABILITATION (2022)
CONTRACT A
REHABILITATE 42,000 FEET OF THE PUBLIC SEWER SYSTEM USING
THE CURED IN PLACE PIPE METHOD, TO REDUCE PUBLIC I/I AND TO
RENEW THE SYSTEM.
2,932,000
BISSELL - COLDWATER - MISSOURI - MERAMEC PUBLIC I/I
REDUCTION (2022) CONTRACT B
REHABILITATE 34,000 FEET OF THE PUBLIC SEWER SYSTEM USING
THE CURED IN PLACE PIPE METHOD, TO REDUCE PUBLIC I/I.2,906,000
INFRASTRUCTURE REPAIRS (REHABILITATION) (2022)
CONTRACT A
CONSTRUCT CURED-IN-PLACE PIPE INSTALLATION FOR SYSTEM
REHABILITATION AND REPAIR, AS NEEDS ARE IDENTIFIED BY SEWER
CLEANING AND INSPECTION EFFORTS.
2,500,000
INFRASTRUCTURE REPAIRS (REHABILITATION) (2022)
CONTRACT B
CONSTRUCT CURED-IN-PLACE PIPE INSTALLATION FOR SYSTEM
REHABILITATION AND REPAIR, AS NEEDS ARE IDENTIFIED BY SEWER
CLEANING AND INSPECTION EFFORTS.
2,500,000
STORMWATER INFRASTRUCTURE REPAIRS (REHABILITATION)
(2022)
CONSTRUCT CURED-IN-PLACE PIPE INSTALLATION FOR
STORMWATER SYSTEM REHABILITATION AND REPAIR, AS NEEDS
ARE IDENTIFIED BY SEWER CLEANING AND INSPECTION EFFORTS.
2,000,000
COLDWATER SANITARY RELIEF SECTION B, C & D - SECTION B
REHABILITATION
REHABILITATE 2,650 FEET OF 54-INCH TO 66-INCH SANITARY SEWER
USING THE CURED IN PLACE PIPE METHOD.1,600,000
Proposed Program –FY2022
•Procurements Needed (Facilities)
Project Name Description Budget
LOWER MERAMEC WWTF EXPANSION PHASE II
EXPAND THE EXISTING WWTF TO INCREASE CAPACITY FOR
ADDITIONAL FLOW, AND UPGRADE THE FACILITY TO ENABLE
ACCOMMODATION OF POTENTIAL NUTRIENT REMOVAL
REQUIREMENTS.
117,200,000
MISSOURI RIVER WWTF DIGESTER GAS STORAGE COVER
REPLACEMENT
REPLACE TWO MEMBRANE GAS STORAGE COVERS FOR THE
ANAEROBIC DIGESTERS.1,289,000
Proposed Program –FY2022
•Procurements Needed (Pump Stations)
Project Name Description Budget
CAULKS CREEK A PUMP STATION (P-750) IMPROVEMENTS CONSTRUCT IMPROVEMENTS TO PUMP STATION P-750.8,516,000
EARTH CITY EXPRESSWAY PUMP STATION (P-708)
REPLACEMENT REPLACE PUMP STATION P-708.1,700,000
EARTH CITY UPS PUMP STATION (P-702) REPLACEMENT PHASE
II
CONSTRUCT REPLACEMENT OF PUMP STATION P-702, 266 FEET OF 8-
INCH FORCE MAIN, AND 128 FEET OF 8-INCH TO 72-INCH SANITARY
SEWER.
1,500,000
FENTON CREEK PUMP STATION (P-425) IMPROVEMENTS
REPLACE PUMP STATION P-425, CONSTRUCT 700 FEET OF 4-INCH
FORCE MAIN, AND CONSTRUCT 840 FEET OF 8-INCH SANITARY
SEWER.
930,000
Proposed Program –FY2022
•Procurements Needed (Sewers)
Project Name Description Budget
HARLEM BADEN RELIEF PHASE IV (HEBERT) - HAMILTON TO
DARVER TRUNK SEWER
CONSTRUCT 3,660 FEET OF 12-INCH TO 108-INCH STORM AND
COMBINED SEWERS, AND 900 FEET OF PIPE IN TUNNEL.9,300,000
BADEN CITYSHED MITIGATION BASINS (CALVARY, FREDERIK,
PARTRIDGE AND TILLIE) - SEPARATION SEWERS
CONSTRUCT 11,000 FEET OF STORM SEWER FOR SOFT
SEPARATION.6,300,000
MC-02 WATSON TO EDGAR RD SANITARY RELIEF (SKME-580A)CONSTRUCT 9,050 FEET OF 8-INCH TO 36-INCH SANITARY SEWER,
AND ELIMINATE CONSTRUCTED SSO OUTFALL BP-557.6,130,000
PRICE TO PIONEER SANITARY RELIEF CONSTRUCT 5,665 FEET OF 8-INCH TO 24-INCH SANITARY SEWER.5,744,000
GEYER SANITARY RELIEF AND WINDSOR SPRINGS P-521
STORAGE (BIG BEND BLVD TO WINDSOR SPRINGS DR)
CONSTRUCT 6,460 FEET OF 10-INCH FORCEMAIN, UPGRADE
WINDSOR SPRINGS PUMP STATION, AND PERFORM PRIVATE I/I
REDUCTION AT 7 PROPERTIES.
5,030,000
ST. GEORGE CREEK SANITARY RELIEF (DAISY LN TO GRAVOIS
RD TO NEW HAMPSHIRE AVE)
CONSTRUCT 2,510 FEET OF 8-INCH TO 21-INCH SANITARY SEWER.
ELIMINATE CONSTRUCTED SSO OUTFALL BP-404.3,305,000
DOLAN PLACE AND GRANDVIEW PLACE COMBINED SEWER
RELIEF
CONSTRUCT 610 FEET OF 12-INCH TO 36-INCH COMBINED SEWER,
AND 650 FEET OF REINFORCED CONCRETE BOX CULVERT 9 FOOT
WIDE BY SIX FOOT HIGH.
3,000,000
HAMPTON CREEK SANITARY RELIEF (DEER CREEK TRUNK TO
OXFORD DR) PHASE IB
CONSTRUCT 324 FEET OF 72-INCH SANITARY SEWER, INCLUDING
128 FEET OF PIPE IN TUNNEL AND NEW JUNCTION CHAMBER.3,000,000
SUB-TRUNK #2 SANITARY RELIEF (BIRMINGHAM CT TO COVE
LN)
CONSTRUCT 4,400 FEET OF 18-INCH TO 21-INCH SANITARY SEWER.
CONTINGENCY PROJECT TO ELIMINATE CONSTRUCTED SSO
OUTFALLS BP-210, BP-211 AND BP-213.
2,515,000
LOUISVILLE AVENUE AND OAKLAND AVENUE COMBINED
SEWER RELIEF
CONSTRUCT 950 FEET OF 12-INCH TO 36-INCH RELIEF SEWER, AND
800 FEET OF 96-INCH COMBINED SEWER FOR WET WEATHER
STORAGE.
2,275,000
Proposed Program –FY2022
•Procurements Needed (Sewers)
SUB-TRUNK #3 SANITARY RELIEF (MURIEL DR TO JENNER LN)
CONSTRUCT 4,300 FEET OF 8-INCH TO 27-INCH SANITARY SEWER.
CONTINGENCY PROJECT TO ELIMINATE CONSTRUCTED SSO
OUTFALL BP-214.
1,905,000
SOUTH BROADWAY AT MERAMEC COMBINED SEWER
REPLACEMENT CONSTRUCT 1,700 FEET OF 12-INCH TO 30-INCH COMBINED SEWER.1,500,000
CANTERBURY AND ROLAND SANITARY RELIEF (NELSON DR TO
ROLAND BLVD)
CONSTRUCT 1,680 FEET OF 8-INCH TO 15-INCH SANITARY SEWER,
AND CONSTRUCT 680 FEET OF NATURAL CHANNEL STABILIZATION.1,404,000
CAREY CT 1664 SANITARY AND STORM SEWER REPLACEMENT
CONSTRUCT 668 FEET OF 8-INCH SANITARY SEWER, 585 FEET OF 30-
INCH TO 42-INCH STORM SEWER TO REPLACE ERODING CHANNEL,
AND 30 FEET OF 15-INCH STORM SEWER.
1,300,000
WEBSTER GROVES TRUNK E SANITARY REHABILITATION AND
I/I REDUCTION PHASE IV
CONSTRUCT 3,200 FEET OF 12-INCH TO 21-INCH STORM SEWER,
AND PERFORM PRIVATE I/I REDUCTION AT 40 PROPERTIES.1,300,000
SCHUETZ ROAD SANITARY RELIEF (FOREST BROOK LN TO
SUNNY WOOD CT)CONSTRUCT 1,033 FEET OF 8-INCH TO 15-INCH SANITARY SEWER.753,000
GRAND GLAIZE TRUNK SANITARY RELIEF (BALLWIN GOLF
CLUB TO CLAYMONT COVE CT)CONSTRUCT 1,935 FEET OF 6-INCH TO 15-INCH SANITARY SEWER.740,000
OAKWOOD FARMS PUMP STATION (P-470) ELIMINATION
CONSTRUCT 920 FEET OF 8-INCH SANITARY SEWER. DECOMMISSION
AND ABANDON EXISTING PUMP STATION P-470 AND ASSOCIATED
FORCEMAIN.
445,000
TREVILLIAN 20 AND 50 SANITARY SEWER REPLACEMENT REPLACE 360 FEET OF 6-INCH VCP WITH 8-INCH SEWER.435,000
Proposed Program –FY2022
•Procurements Needed (Sewers)
DEKAMAY DRIVE STORM SEWER (MGJB-130)CONSTRUCT 1,050 FEET OF 12-INCH TO 24-INCH STORM SEWER.355,000
CLAYTON RD 9925 SANITARY SEWER REPLACEMENT CONSTRUCT 395 FEET OF 12-INCH REPLACEMENT SANITARY
SEWER.285,000
WASHINGTON TERRACE 14 SEWER REPLACEMENT REPLACE 100 FEET OF 15-INCH COMBINED SEWER.279,000
BROADHEAD #921 STORM SEWER CONSTRUCT 176 FEET OF 30-INCH STORM SEWER.265,000
ORCHARD AND WINDSOR LANE STORM SEWER CONSTRUCT 579 FEET OF 24-INCH STORM SEWER.250,000
ST. JACQUES SANITARY RELIEF (ST. JACQUES ST TO N
LAFAYETTE ST)
CONSTRUCT 195 FEET OF 8-INCH SANITARY SEWER, REPLACE 154
FEET OF 12-INCH SEWER WITH 15-INCH SEWER, AND ELIMINATE
CONSTRUCTED SSO OUTFALL BP-110.
155,000
Proposed Program –FY2022
•Procurements Needed (PIR)
Project Name Description Budget
SHREWSBURY SANITARY RELIEF SEWER AND I/I REDUCTION
(WEIL AVE AND I-44)PERFORM PRIVATE I/I REDUCTION AT 202 PROPERTIES.980,000
CLAYTON MERAMEC ELEMENTARY PRIVATE I/I REMOVAL (S.
MERAMEC AVE AT WALINCA TER)
REMOVE STORM DRAINS AND DOWNSPOUTS CONNECTED TO THE
SANITARY SEWER.500,000
FISHPOT TRUNK WEST AND ED LOU LANE I/I REDUCTION (SMITH
DR AND VLASIS DR)
REPLACE 343 FEET OF 8-INCH SANITARY SEWER, AND PERFORM
PRIVATE I/I REDUCTION AT 14 PROPERTIES.300,000
Proposed Program –FY2022
•Procurements Needed (Bank Stabilization)
Project Name Description Budget
WC-33 LA PADERA - EL CAMARA STORM IMPROVEMENT CONSTRUCT 1,160 LINEAR FEET OF ROCK LINING AND
BIOSTABILIZATION.881,000
RECO AVENUE BANK STABILIZATION
CONSTRUCT 595 FEET OF ROCK BLOCK TOE WALL, COMPOSITE
REVETMENT, AND HEAVY STONE REVETMENT BANK
STABILIZATION.
250,000
Proposed Program –FY2022
•Work Order Repairs
Project Name Description Budget
INFRASTRUCTURE REPAIRS
(WASTEWATER) (2021)CONSTRUCT REPAIR OR REPLACEMENT OF WASTEWATER INFRASTRUCTURE DISTRICTWIDE.7,000,000
INFRASTRUCTURE REPAIRS
(FACILITIES) (2021)
CONSTRUCT REPAIR, REPLACEMENT, OR IMPROVEMENT PROJECTS TO ADDRESS NEEDS AT
FACILITIES SUCH AS TREATMENT PLANTS AND PUMP STATIONS.3,000,000
STORMWATER INFRASTRUCTURE
REPAIRS (2021)
CONSTRUCT REPAIR OR REPLACEMENT OF STORMWATER INFRASTRUCTURE THROUGHOUT THE
DISTRICT.6,000,000
Proposed Program –FY2022
•Contingency Projects
Project Name Budget
BISSELL & LEMAY WWTF FLUIDIZED BED INCINERATORS 101,000,000
HALL STREET STORM SEWERS 7,000,000
CSO VOLUME REDUCTION GREEN INFRASTRUCTURE 5,000,000
HARLEM CITYSHED MITIGATION BASINS (ASHLAND AND ESSEX)4,000,000
NEW ENGLAND TOWN CLIFF CAVE PUMP STATION (P-323) IMPROVEMENTS 4,000,000
CSO VOLUME REDUCTION GREEN INFRASTRUCTURE - RIVER DES PERES 3,000,000
HARLEM BADEN RELIEF PHASE IV (HEBERT) - SEWER REHABILITATION 2,768,000
PUMP STATION MANLIFT REPLACEMENT 2,400,000
LINDWORTH STORM SEWER SEPARATION 1,600,000
CLAYTON CITY HALL STORM SEWER 1,590,000
LEMAY 1 PUMP STATION (P-301) COOLING TOWER REPLACEMENT 650,000
REASOR DRIVE STORM SEWER 465,000
LINDWORTH STORM SEWER SEPARATION 400,000
VALLEY VIEW PUMP STATION (P-734) REPLACEMENT 380,000
STONINGTON PLACE SANITARY RELIEF (CLAYTON RD TO GEORGIAN ACRES ST)300,000
EVERMAN AVE 9518 STORM SEWER 280,000
Proposed Program –FY2022-26
•Looking Ahead
Fiscal Year
Anticipated Total
Construction
Budget
Estimated
# of bid
opportunities
FY22 298,000,000 43
FY23 423,000,000 78
FY24 454,000,000 43
FY25 368,000,000 35
FY26 245,000,000 26
Total 1,788,000,000 225
Proposed Program –FY2022-26
•Looking Ahead –Design Build Projects
Fiscal Year Project
23 BISSELL & LEMAY WWTF FLUIDIZED BED
INCINERATORS
23 ELTORA WET WEATHER STORAGE FACILITY
25 MISSISSIPPI FLOODWALL ORS PUMP STATIONS
REHABILITATION PHASE IV
Construction Management Division Staffing
https://msdprojectclear.org/about/our-
organization/departments/engineering/
Construction Management Division Staffing
Prequalification Process
•Contractors must be prequalified to bid
•Prequalification applications are accepted at any time
•https://msdprojectclear.org/doing-business/capital-improvement-replacement-program/capital-construction/prequalification-process/
•Contractors are prequalified for Specific Work Categories
•Annual Renewal of Prequalification is required
Small Contractor Program (SCP)
•Program Purpose
•SCP Project Size
•SCP Typical Work Types
•https://msdprojectclear.org/doing-
business/capital-improvement-replacement-
program/small-contractor-program/
Michael Buechter, P.E.
Program Manager, Design
Engineering Division
Phone: (314) 768-2772
Fax: (314) 768-6341
E-mail: mtbuec@stlmsd.com
Bid Schedule
•https://msdprojectclear.org/doing-
business/capital-improvement-replacement-
program/
Plan Room
•https://www.stlmsdplanroom.com/
Prevailing Wage Program
•https://msdprojectclear.org/doing-
business/prevailing-wage/
Diversity
•https://msdprojectclear.org/doing-
business/supplier-diversity/
Shonnah Paredes
Manager of Diversity Programs
Executive Director Division
Phone: (314) 768-6395
Fax: (314) 768-2760
E-mail: sparedes@stlmsd.com
Disparity Study Update
Remaining Disparity Study Timeline
•Analysis completed by 4/30/2021
•Draft of final Disparity Study Update by 5/31/2021
•MSD provide comments on draft by 6/12/2021
•Issue final Disparity Study Reports 7/1/2021
Disparity Study Results
•Present results to MSD Board of Trustees
•Begin campaign to communicate results to Staff, Stakeholders
and Public
•Generate Disparity Study Implementation Plan
Executive Director’s Update
•Bond Issue and Charter Election Results
•Plans for Stormwater Program
•Status of Board of Trustees
Further Details will be provided during Quarterly
AGC/SITE Update Meetings
www.MSDProjectClear.org
Questions
and Answers
Thanks to: