HomeMy Public PortalAboutDPW Qtr 4 Report 2012DPW Quarter 4, FY 2012 Projects 19th Street Crossover Note: Lumber was purchased in the previous quarter for $4,633.32 Man Hrs Equipment Materials Labor Total 420 $1,800.00 $646.70 $10,500.00 $12,946.70 2) Jones Avenue Drainage Project Man Hrs Equipment Materials Labor Total 340 $5,100.00 $5,418.00 $8,500.00 $19,018.00 3) Marsh Rack Removal Man Hrs Equipment Materials Labor Total 204.5 $5,425.00 $0.00 $5,112.50 $10,537.50 Maintenance Clean, Restock, and Maintaining Facilities, Restrooms, and Parks Man Hrs Equipment Materials Labor Total 1252.9 $1,710.00 $15,045.47 $31,322.50 $48,077.97 Cutting grass, Ditches, Trimming and Landscaping Man Hrs Equipment Materials Labor Total 1,948.6 $33,057.50 $524.00 $48,715.00 $82,296.50 Cleaning up Street Trash and Barrels (including street sweeper) Man Hrs Equipment Materials Labor Total 1,046.5 $38,600.00 $1,330.00 $26,162.50 $66,092.50 Cleaning up Beaches (Trash & Recycling) Man Hrs Equipment Materials Labor Total 488.05 $7,725.00 $92.42 $12,201.25 $19,926.25 Fixing, Replacing, and Installing New Signs Man Hrs Equipment Materials Labor Total 137 $0.00 $1,414.81 $3,425.00 $4,839.81 Island-wide Road Repair & Maintenance Man Hrs Equipment Materials Labor Total 540 $8,100.00 $3,000.00 $13,500.00 $24,600.00 Maintaining Beaches (Swings, Mobi-Mats, and Crossovers) Man Hrs Equipment Materials Labor Total 270 $0.00 $0.00 $6,750.00 $6,750.00 Drainage Maintenance Man Hrs Equipment Materials Labor Total 400 $1,800.00 $674.88 $10,000.00 $12,474.88 Building Maintenance - Pay & Display and Meter Poles Man Hrs Materials Labor Total 24 $0.00 $600.00 $600.00 - Coating DPW Roof & Cleaning Gutters Man Hrs Materials Labor Total 36 $1,754.92 $900.00 $2,654.92 - Lifeguard Deck Man Hrs Materials Labor Total 95 Paid for by J. Brown $2,375.00 $2,375.000 - Misc. Work orders and repairs Man Hrs Materials Labor Total 206.5 $4,044.91 $5,162.50 $9,207.41 - Fire Department Beam & Soffet Man Hrs Materials Labor Total 46.5 $4,787.69 $1,162.50 $5,950.19 Fire & Safety Building Updates Bldg Man Hrs Materials Labor Total Campground 85 Camp paid for $2,125.00 $2,125.00 85 $2,125.00 $2,125.00 Previous total from Qtr 2 & Qtr 3, FY 2012 $18,124.95 Total Investment for Fire & Safety Updates $20,249.95 Holidays, Festivals & Events Beach Bum Man Hrs Equipment Materials Labor Total 66.5 $997.45 $0.00 $1,662.50 $2,659.95 Work Orders DPW, Building Maintenance and Parks & Rec. have completed 106 Work Orders for the following departments this quarter: YMCA - 4 Campground - 2 Police Dept. - 7 M.S.C. - 10 Fire Department - 13 DPW - 16 Facilities, Parks, and Restrooms - 6 City Hall & Resident Requests and Observations - 26 TEMA - 2 Water Dept - 0 Parking - 20 Fleet Department The Fleet Department has completed 171 Service and Repair Orders for the following departments this quarter: City Hall - 1 Parts: $0.00 Labor: $75.00 Campground - 1 Parts: $0.00 Labor: $25.00 DPW - 85 Parts: $53,545.51 Labor: $14,690.00 Fire Department - 24 Parts: $1,418.29 Labor: $4,750.00 Parking - 9 Parts: $947.93 Labor: $1,425.00 Police Dept. - 33 Parts: $2,356.45 Labor: $3,200.00 Water/ Sewer - 18 Parts: $1,896.95 Labor: $1,237.50 Totals: Parts: $60,165.13 Labor: $25,402.50 Total: $85,567.63 Total time spent on research, ordering parts, inventory, paperwork and filing, and cleaning the shop: 323.9 man hours Cost in labor: $8,097.50 Purchasing 251 Purchase Orders have been made this quarter amounting to $154,574.02 Major Purchases -Deere & Company for new Tractor $18,500.00 -MPC for NPDES Permit $15,000.00 -Lawnmower Store for new Toro Mower $7,800.00 Completed Training: Motor Age Training – Michael, Patrick, Paul Master Gardener Class Completed – Megan, Chase GSWCC Level 2 Course – Cory, Aaron B. Tonnage Reports: Waste Pro Organic – 40 Tons, 44 Hauls Construction Debris – 201.8 Tons, 40 Hauls Compactor – 54.19 Tons, 13 Hauls Southern Metals Recycling Recycled metal – 20.355 Tons Republic Services – Compactors Atlantic Ave – 63.74 Tons, 26 Hauls Lovell Ave – 67.78 Tons, 13 Hauls