HomeMy Public PortalAboutGEFA 2007-L48WS change order 1-26-10 Georgia Department of Natural Resources
Environmental Protection Division, Watershed Protection Branch
4220 International Parkway, Suite 101, Atlanta, Georgia 30354
Phone: 404/675 -6233
Fax: 404/675 -6246
January 26, 2010
Ms. Diane D. Schleicher
City Manager, City of Tybee Island
Post Office Box 2749
Tybee Island, Georgia 31328
RE: Change Order No. 3 Final
Fort Screven Water Upgrades
Tybee Island, Chatham County
GEFA 2007 -L48WS
Dear Ms. Schleicher:
This office has completed the review of the referenced change order. This change order was
found to be consistent with the scope of work defined by your loan contract. Therefore, on behalf of
the Georgia Environmental Facilities Authority and the Georgia Environmental Protection Division,
Change Order No. 3 to the contract with Southern Champion Construction, Inc. is hereby approved.
Approval of this change order does not alter the total amount or conditions of your GEFA loan
contract.
This is the project summary change order.
Original Contract Amount: $1,071,093.00
Present Contract Amount: 1,210,398.00
Change Order No. 3 (Decrease) - 53,614.00
Revised Contract Amount: $1,156,784.00
Construction Completion Date: May 28, 2009
Increase Contract Time: None
If you should have any questions, please call me at 404/675 -1613.
Sincerely,
Jose C. Remon, Engineer
Engineering & Technical Support Program
cc: Hussey, Gay, Bell & DeYoung, Inc.
ATTN: Mr. Bill Lovett
Georgia Department of Natural Resources
Environmental Protection Division, Watershed Protection Branch
4220 International Parkway, Suite 101, Atlanta, Georgia 30354
Phone: 404/675 -6233
Fax: 404/675 -6246
January 26, 2010
IlEeMEV'MT
Ms. Diane D. Schleicher
City Manager, City of Tybee Island
FEB 0 1 2010
Post Office Box 2749
BY:
Tybee Island, Georgia 31328
RE: Change Order No. 2
Fort Screven Water Upgrades
Tybee Island, Chatham County
GEFA 2007 -L48WS
Dear Ms. Schleicher:
This office has completed the review of the referenced change order. This change order was
found to be consistent with the scope of work defined by your loan contract. Therefore, on behalf of
the Georgia Environmental Facilities Authority and the Georgia Environmental Protection Division,
Change Order No. 2 to the contract with Southern Champion Construction, Inc. is hereby approved.
Approval of this change order does not alter the total amount or conditions of your GEFA loan
contract.
This change order is for exploration necessary to facilitate water line tie -in and abandonment.
Original Contract Amount: $1,071,093.00
Present Contract Amount: 1,197,973.00
Change Order No. 2 (Increase) + 12,425.00
Revised Contract Amount: $1,210,398.00
Construction Completion Date: May 28, 2009
Increase Contract Time: None
If you should have any questions, please call me at 404/675 -1613.
Sincerely,
11 Jose C. Remon, Engineer
Engineering & Technical Support Program
cc: Hussey, Gay, Bell & DeYoung, Inc.
ATTN: Mr. Bill Lovett