HomeMy Public PortalAbout2019-10-03 packet
Individuals should contact the ADA Coordinator at (573) 634-6570 to request accommodations or alternative formats
as required under the Americans with Disabilities Act. Please allow three business days to process the request.
Please call (573) 634-6410 with questions regarding agenda items.
Technical Committee
Thursday, October 3, 2019 at 10:00 a.m.
Meeting Location: Boone/Bancroft Room # 200, John G. Christy Municipal Building
320 E. McCarty, Jefferson City, MO 65101 - Enter through Main Lobby
PRESENTATION:
ADA Transition Plans for Right-Of-Way
Julie Stotlemeyer, P.E., Assistant State Design Engineer, MoDOT Central Office Design
1. Call to order, roll call, and determination of a quorum
2. Public comment
3. Adoption of the agenda as printed or amended
4. Approval of the minutes from the meeting of August 1, 2019
5. Communication Received
A. ONE DOT & Governor Approval of TIP Amendment #1
6. New Business
A. MoDOT request for functional class change to Routes M & W at the intersection with Route B in
Wardsville.
Action Requested: Review and discussion, recommendation of approval to the Board of Directors.
Staff Report: During MoDOT’s July 2019 travel way maintenance, line work was adjusted on RT B at the
intersection of B, M, and W in Cole County. The major collector functional classification has been moved
to the ne w location. Staff is seeking a Technical Committee recommendation for approval to the Board of
Directors. More detail is provided in the staff report.
7. Other Business
A. Status of current work tasks
B. Member Updates
8. Next Meeting Date – Thursday, November 7, 2019 at 10:00 a.m. in the Boone/Bancroft Room #200
9. Adjournment
Capital Area Metropolitan
Planning Organization
Room 120 320 E. McCarty, Jefferson City, MO 65101 Phone 573.634.6410 Fax 573.634.64 57
MINUTES
TECHNICAL COMMITTEE
CAPITAL AREA METROPOLITAN PLANNING ORGANIZATION
August 1, 2019
VOTING MEMBERS PRESENT
Cole County: Larry Benz
Jefferson City: David Bange, Vice Chairman
Matt Morasch
Eric Barron
Mark Mehmert
Britt Smith
Holts Summit: Hannah Lechner for Mark Tate
MoDOT: Mike Henderson
Steve Engelbrecht
Private Transportation Interest: Joe Scheppers
Pedestrian or Biking Interest: Cary Maloney
*Arrived Late
VOTING MEMBERS ABSENT
Paul Winkelmann, Callaway County
Eric Landwehr, Cole County
JJ Gates, Jefferson City
Sonny Sanders, Chairman, Jefferson City
Mark Tate, Holts Summit
Paul Stonner, Wardsville
Bob Lynch, MoDOT
EX-OFFICIO MEMBERS PRESENT
Brad McMahon, Federal Highway Administration
EX-OFFICIO MEMBERS ABSENT
Jeremiah Shuler, Federal Transit Administration
STAFF PRESENT (Non-Voting)
Katrina Williams, Transportation Planner
Lee Bowden, Transportation Planner
Beth Sweeten, Administrative Assistant
GUESTS PRESENT
Jennifer Bowden, MORPC
Kim Tipton, MoDOT
1. Call to order, roll call, and determination of a quorum
Mr. Bange called the meeting to order at 10:01 a.m. and asked Ms. Sweeten to call roll. A quorum of 10
voting members was present.
2. Public comment
None received.
3. Adoption of the agenda as printed or amended
Mr. Benz moved and Mr. Smith seconded to adopt the agenda as printed. The motion passed unanimously.
4. Approval of the minutes from the meeting of May 2, 2019
Mr. Benz moved and Mr. Smith seconded to approve the minutes from the meeting of April 4, 2019 as
written. The motion passed unanimously.
Minutes/Capital Area Metropolitan Planning Organization Technical Committee
August 1, 2019 Page 2
5. Communications from the presiding officer
No correspondence was received.
6. New Business
A. Proposed Amendment #1 to the 2020-2024 Transportation Improvement Program (TIP):
JEFFTRAN Improvement Projects
Mr. Bowden gave a short presentation and explained that staff is seeking a recommendation from the
Technical Committee to the Board of Directors to approve an amendment to the 2020 -2024 Transportation
Improvement Program (TIP). The amendment includes the addition of seven JEFFTRAN projects and
adjustments JEFFTAN’s portion of the Financial Plan section, which outlines forecasted revenue,
expenditures, and programmed funding.
He added that the projects total $520,128 and are funded at 80% through the FTA 5339 Bus and Bus
Facilities Formula Grant. The projects, listed on the following pages, will be completed in program years
2020 through 2022. The TIP Project Application forms a re also attached for your review.
Mr. Mehmert briefly spoke on what items within Transit would benefit from the amendment.
Mr. Morasch made a motion to open a seven day public comment period and forward the proposed
amendment the Board of Directors for approval. Mr. Smith seconded the motion. The motion passed
unanimously.
B. Reallocation of remaining Surface Transportation Block Grant (STBG) funds
Ms. Williams explained that CAMPO has a remaining STBG balance of approximately $29,588.55. This
balance stems from two STBG funded projects that were completed under budget. The Clark Avenue
Traffic Study was completed $11,691.80 under budget and the Travel Demand Modeling and Visioning
Services Contract was completed $17,866.75 under budget.
She added that reallocation of the funds must be completed by the end of August, or returned to MoDOT.
Staff only identified one project, the City of St. Martins 2018 TAP project that would be practical for the
reallocation. The City of St. Martins was awarded a Transportation Alternatives Program (TAP) Grant in
2018 totaling $873,529.75 to improve ADA compliance and Pedestrian/Bicycle access along Business 50
West. The STBG funds could be used to reduce the local match for S t. Martins. The TAP project currently
has a local match 55% ($476,073.71) which could be reduced to 51% through the use of STBG funds. She
stated that if it is decided to give the funds to St. Martins, this will result in a staff led administrative
modification of the project in the Transportation Improvement Program.
Mr. Morasch made a motion to reallocate the remaining STBG fund balance to the City of St. Martins for
use in completing the awarded 2018 TAP Project. Mr. Smith seconded the motion, the motion passed
unanimously.
7. Other Business
A. Status of current work tasks
Transportation Improvement Program (TIP). Staff has worked with JEFFTRAN to develop an
amendment to the TIP. Please see the attached staff report for more information.
Federal Performance Measures. Staff continues collaborating with MODOT staff concerning
various federal performance measures required by MAP -21 and the FAST Act.
Jefferson City Data Assistance. Staff is working with other Jefferson City planners in providing
data and mapping assistance in the update of the of the City’s Comprehensive Plan.
Major Thoroughfare Plan Development. Staff is developing a timeline and process for creation of
a Major Thoroughfare Plan. The Major Thoroughfare Plan will be developed through stakeholder
input and will pull directly from the recently completed Travel Demand Model.
Minutes/Capital Area Metropolitan Planning Organization Technical Committee
August 1, 2019 Page 3
B. Member Updates
Jefferson City
--Mr. Bange gave an update on the following: (1) Dunklin Street Bridge replacement and corridor
project; (2); MO Blvd sidewalk
--Mr. Smith said the overlay project was out to bid, but the asphalt company is behind and can’t start
until September. The airport is back open, and they have applied for a grant to make emergency repairs
from the flood.
--Mr. Mehmert stated that new rider guides are available and they are working on bus stop
improvements.
Cole County
--Mr. Benz stated that Cole County had a pre-construction meeting for the railroad expansion at Algoa
and are getting ready to start a few storm water projects
MoDOT
--Mr. Henderson stated the STIP was approved on July 16, 2019
Holts Summit
--Ms. Lechner stated they are getting ready to begin a storm water project, and two sewer projects.
Federal Highway Administration
--Mr. McMahon said they hired a new staff member, Steve Minor.
8. Next Meeting Date - Thursday, September 5, 2019 at 10:00 a.m. in the Boone/Bancroft Room.
9. Adjournment
The meeting adjourned at 10:32 a.m.
Respectfully submitted,
Beth Sweeten, Administrative Assistant
1
Williams, Katrina
Subject:FW: ONEDOT Transit ONLY Approval FY2020-2024 STIP (CAMPO TIP FY2020-2023 Amend
#1)
Attachments:9.9.2019 ONEDOT Transit ONLY Approval FY2020-2024 STIP (CAMPO TIP FY2020-2023
Amend 1).pdf
From: Barnett, Austi (FTA) [mailto:austi.barnett@dot.gov]
Sent: Tuesday, September 10, 2019 12:01 PM
To: kwilliams@jeffcitymo.org; LBowden@jeffcitymo.org; Mike Henderson; Eva Voss; Steve Engelbrecht;
bradley.mcmahon@dot.gov
Cc: Monroe, Cathy (FTA)
Subject: ONEDOT Transit ONLY Approval FY2020-2024 STIP (CAMPO TIP FY2020-2023 Amend #1)
Good afternoon,
Please find attached a signed and scanned copy of the ONE DOT letter for the FTA approval of “Transit Projects
Only” amendment to the Missouri FY2020-2024 STIP to incorporate the CAMPO amendment #1 of the FY2020-
2023 TIP, dated September 9, 2019. A hardcopy of the letter is being transmitted to Patrick McKenna in today’s
mail.
Best Regards,
Austi Barnett
Administrative Program Specialist
Federal Transit Administration | Region VII 🚇
901 Locust St., Ste. 404, Kansas City, MO 64106
816-329-3922
Individuals should contact the ADA Coordinator at (573) 634-6570
to request accommodations or alternative formats as required under the Americans with Disabilities Act. Please allow three
business days to process the request.
CAMPO Technical Committee Staff Report
Routes M & W at the intersection of Route B in Wardsville
October 3, 2019
Summary
Staff is seeking a recommendation from the Technical Committee to the Board of Directors to approve
MoDOT’s request for a functional class change to Routes M and W at the intersection of Route B in Wardsville.
During the July 2019 travel way maintenance, line work was adjusted on RT B in Cole County. The major
collector functional classification has been moved to the new location. One section of the old location was
renamed RT M and another section was renamed RT W. At least one section should retain the major collector
functional classification for connectivity of the major collector currently on RT M and the section we selected
had the higher AADT (Annual Average Daily Traffic) count.
The change request forms are attached to this staff report.
Staff Recommendation
Staff recommends approval of this request and to forward the request to the Board of Directors for their
approval.
Recommended Form of Motion:
Motion to forward the functional class change request to the Board of Directors for approval.
Agenda Item 6A
Our mission is to provide a world-class transportation experience that delights our customers and promotes a prosperous Missouri.
MEMORANDUM
Missouri Department of Transportation
Planning
Central District
TO: Ron Fitzwater, CAMPO Chairman
FROM: Steve Engelbrecht
District Planning Manager
DATE: September 6, 2019
SUBJECT: Functional Classification Request
Cole County
Attached please find information for a functional classification request. The request is being
made to change two proposed routes in the Capital Area Metropolitan Planning Organization.
During the July 2019 travel way maintenance, line work was adjusted on RT B in Cole County.
The major collector functional classification has been moved to the new location. One section of
the old location was renamed RT M and another section was renamed RT W. At least one
section should retain the major collector functional classification for connectivity of the major
collector currently on RT M and the section we selected had the higher AADT (Annual Average
Daily Traffic) count.
Missouri Department of Transportation
Functional Classification Request Form
This form has been developed for all future requests for functional classification (FC) changes to
existing roadways or to classify a planned roadway. A separate form must be completed for each
revision being requested.
Completed forms should be submitted to MoDOT, Transportation Planning. A letter from the MoDOT
district office, a copy of the transmittal letter from the requesting agency and a map showing each
requested revision should also be included.
1. Local name of roadway_____________________________________________________________
2. Termini of roadway
From ________________________________________________________________
To ________________________________________________________________
Length (miles) ________________________________________________________________
3. Type of area _____Rural _____Urban
4. Existing or planned roadway _____Existing _____Planned
If planned, provide the anticipated date that construction will begin and attach documentation of a
commitment to funding for the planned project within an improvement program. (Construction should
begin within 4 years for the roadway to be included on the FC map.)
Date______________________
5. Current functional classification______________________________________________________
6. Requested functional classification____________________________________________________
7. Local consultation occurred _____Yes _____No
Planning partners should be involved to ensure informed consent of the functional classification
designation. Please describe how local planning partners were consulted, or explain if no local
consultation occurred.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
8. Traffic volume (AADT)___________________________
Route M
Route W
Route B
(Old location of Route B)
.03 Miles
X
X
Old Route B Major Collector
New Route M Major Collector
X
CAMPO advised as the TAC meeting.
800-900
9. Existing roadway characteristics
Roadway surface type _________________________
Number of lanes _________________________
Lane width _________________________
10. Justification
a.Explain why you feel the roadway classification should be revised.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
b. Are there any new developments (residential or commercial) or changes in land usage that
will alter the demand on this roadway?
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
c.Will the roadway provide direct access to any points of activity: industries, shopping
centers, schools, etc.?
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
d. Is the demand on this roadway changing, or is the existing demand inconsistent with its
current classification?
____________________________________________________________________________
____________________________________________________________________________
e.Provide additional information you would like to include.
____________________________________________________________________________
____________________________________________________________________________
j:\granns\FC request form_revised 2015.doc
Asphalt
2
10 ft
Linework was adjusted on Route B in Cole County. The major collector FC has been moved
to the new location.
No
No
No
As an extension of Route M and retain the major collector on this section
since it still functions as a major collector and maintains FC connectivity.
Cole County
RT B relocation
old location of RT B
renamed RT W
new location of RT B
old location of RT B
renamed RT M
Functional Classification
INTERSTATE MAJOR COLLECTOR /
OTHER FREEWAY/EXPRESSWAY OTHER PRINCIPAL
Missouri Department of Transportation
Functional Classification Request Form
This form has been developed for all future requests for functional classification (FC) changes to
existing roadways or to classify a planned roadway. A separate form must be completed for each
revision being requested.
Completed forms should be submitted to MoDOT, Transportation Planning. A letter from the MoDOT
district office, a copy of the transmittal letter from the requesting agency and a map showing each
requested revision should also be included.
1. Local name of roadway_____________________________________________________________
2. Termini of roadway
From ________________________________________________________________
To ________________________________________________________________
Length (miles) ________________________________________________________________
3. Type of area _____Rural _____Urban
4. Existing or planned roadway _____Existing _____Planned
If planned, provide the anticipated date that construction will begin and attach documentation of a
commitment to funding for the planned project within an improvement program. (Construction should
begin within 4 years for the roadway to be included on the FC map.)
Date______________________
5. Current functional classification______________________________________________________
6. Requested functional classification____________________________________________________
7. Local consultation occurred _____Yes _____No
Planning partners should be involved to ensure informed consent of the functional classification
designation. Please describe how local planning partners were consulted, or explain if no local
consultation occurred.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
8. Traffic volume (AADT)___________________________
Route W (Old location of Route B)
Route M
Route B
.03
X
X
Major Collector (Old Route B)
Minor Collector, Continuance of Route W
X
CAMPO advised as the TAC meeting.
650-750
9. Existing roadway characteristics
Roadway surface type _________________________
Number of lanes _________________________
Lane width _________________________
10. Justification
a.Explain why you feel the roadway classification should be revised.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
b. Are there any new developments (residential or commercial) or changes in land usage that
will alter the demand on this roadway?
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
c.Will the roadway provide direct access to any points of activity: industries, shopping
centers, schools, etc.?
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
d. Is the demand on this roadway changing, or is the existing demand inconsistent with its
current classification?
____________________________________________________________________________
____________________________________________________________________________
e.Provide additional information you would like to include.
____________________________________________________________________________
____________________________________________________________________________
j:\granns\FC request form_revised 2015.doc
Asphalt
2
10 feet
Line work was adjusted on Route B in Cole County. The major collector FC has been moved
to the new location, need to reclassify the current roadway as an extension of Route W.
No.
No
No.
Which is classified as a minor collector.
Cole County
RT B relocation
old location of RT B
renamed RT W
new location of RT B
old location of RT B
renamed RT M
Functional Classification
INTERSTATE
MAJOR COLLECTOR /
OTHER FREEWAY/EXPRESSWAY OTHER PRINCIPAL
Individuals should contact the ADA Coordinator at (573) 634 -6570
to request accommodations or alternative formats as required under the Americans with Disabilities Act. Please
allow three business days to process the request.
CAMPO Technical Committee Staff Report
Status of Current Work Tasks
October 3, 2019
Summary
The following list includes work tasks that are currently in progress or have been completed since the previous
Technical Committee meeting:
Annual Listing of Obligated Projects. Staff has assembled the document and it is
posted to the CAMPO website at www.jeffersoncitymo.gov/campo.
911 Assistance. Jefferson City/Cole County 911 is in the process of updating dispatch
software. CAMPO staff is providing technical assistance with adjustments to the GIS
road network.
Federal Performance Measures. Staff continues collaborating with MODOT staff
concerning various federal performance measures required by MAP-21 and the FAST Act.
Jefferson City Data Assistance. Staff is working with other Jefferson City planners in
providing data and mapping assistance in the update of the of the City’s Comprehensive
Plan.
Title VI Program update (including Public Participation Plan, Limited English
Proficiency). Staff is working on the combined update of all of these plans. These
required products will be updated with stakeholder and public input. The documents are
excepted to be completed by February 2020.
Major Thoroughfare Plan Development. Staff is developing a process for creation of a
Major Thoroughfare Plan. The Major Thoroughfare Plan will be developed through
stakeholder input and will pull directly from the recently completed Travel Demand
Model.
Agenda Item 7A