HomeMy Public PortalAbout20221118smRCfinalRAIL COMMITTEE ACTION MINUTES
Page 1 of 16
Special Meeting
November 18, 2022
The Rail Committee of the City of Palo Alto met on this date in the
Community Meeting Room and by virtual teleconference at 1:00 P.M.
Present In Person: Burt, Cormack
Present Remotely: Kou
Absent: None
Vice Mayor Kou Called the meeting to order at 1:00 P.M.
City Clerk Leslie Milton stated two were present, and there was a quorum.
Oral Communications
Elizabeth Alexis had put forward one of the alternatives regarding
Charleston and Meadow and had sent in some comments. She questioned
if the alternatives of leaving the intersection as it was should be
considered because she believed it would fail to meet the purpose and
intent of the project with regard to improved traffic flow and would have
long-lasting implications for bikes and pedestrians. She asked if turning
the intersections into roundabouts would improve that. She thought the
underpass would be great, but was concerned that the bike community
rejected it because it was a work in progress. She had given the
Committee a handout which would be helpful in understanding how
different alternatives would perform.
Ron Roth lived near the Alma train crossing and University Avenue
Caltrain Station, and the frequent train whistle interfered with his life. He understood the whistle was no longer required for safety purposes and
requested its elimination.
Yvonne lived on Alma Street and found it difficult to sleep with the noise
of the train and the whistle and would be grateful if the project reduced
the noise.
Bruce Arthur was present on behalf of the Palo Alto Bike and Pedestrian
Advisory Committee, a subcommittee set up to deal with rail crossings in
South Palo Alto, and had sent an email. He detailed concerns related to
ACTION MINUTES
Page 2 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
the underpass plan putting all pedestrians and cyclists on one side of the
crossing of Meadow and Charleston and recommended the City build a
separate bike and pedestrian path in some area of South Palo Alto. He
provided recommendations for a safe crossing in South Palo Alto during
the construction process.
Adrian Brandt addressed Caltrain being part of electrification and circuits
not being compatible with electrification. He explained the chosen solution
of dual-speed check (DSC), which should be installed by the end of the
year. He addressed Caltrain’s plan of a second round of signal
improvements with a wireless system, which there would be almost a
year’s time between the implementation of DSC and the wireless system.
He stated the latest staff report to the board indicated problems and
complaints with the DSC circuits that had been installed at six crossings,
which they had deactivated and continued to work on improvements.
Action Items
1. Verbal Update on Interagency Activities
A. Caltrain – No update provided
B. VTA - No update provide
C. City Staff
Transportation Director Philip Kami provided a City update. He commented
on seeking grant funding and applying for the Transit and Intercity Rail
Capital Program (TIRCP), and conversation had been initiated with VTA on
the application. They planned on Meadow and Charleston being the first
priority. A middle-of-the road approach would be taken for the funding
sought as they did not know which alternative would be selected. They had
followed up with Caltrain staff and were waiting on a response regarding the San Francisquito bridge project, which it was reiterated an alternative
analysis was needed for rehabilitation and strengthening of the bridge, and a
cost benefit analysis for the alternatives had been requested. Caltrain hired
Kimley-Horn to perform the Caltrain Corridor Strategy on grade separations,
and the scope and stakeholder engagement plan was in process. There
would be monthly meetings with City/County Staff Group, LPMG, and other
stakeholders, and a stakeholder advisory team would be developed, which
would provide recommendations. Two diagnostic meetings were being
scheduled with CPUC and the Joint Powers Board staff for the Quiet Zone
Study for Palo Alto Avenue.
Mayor Burt expressed regarding the Caltrain Corridor Study that a consulting
team had been engaged, and there had been two presentations at the LPMG
meeting. They were receptive to input in terms of including additional
ACTION MINUTES
Page 3 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
criteria and methodology for decision-making. The concept of a corridor-wide
study seemed promising. Related to the San Francisquito Creek bridge and
Caltrain not moving forward aggressively with replacement of the bridge
preceding the Committee developing a preferred alternative, several years
ago there had been an extensive study of the El Palo Alto Tree, which
publishing of the study had not been completed, but he understood it would
be done. He mentioned some of what the study showed. VTA had an Ad Hoc
Committee on grade separation. It came out in the first meeting that
Caltrain had agreed to Mountain View’s assertion that four tracks at the
Castro Station could not be integrated. He indicated the Committee needed
to take a more aggressive position with Caltrain for four track in certain
areas of the corridor.
Transportation Director Kami remarked that staff had asked Caltrain about
the four tracking and was anticipating more information.
Mayor Burt specified the Committee should ask for the documents submitted
to Caltrain by Mountain View and make assertions to Caltrain in a manner
similar to Mountain View’s. He did not believe permission was needed to do
that. He asked to be notified if there was no response.
Vice Mayor Kou indicated if there was documentation from one city that
affected another city staff should iterate to Caltrain that material should be
shared with the affected city so there could be a conversation.
Transportation Director Kami noted they requested from Kimley-Horn and
Caltrain staff coordination and communication with all the cities.
Nadia Naik of CARRD added that Mountain View’s City Council had taken the
position of voting on the four tracks and sending the message to Caltrain, so
consideration may need to be given to scheduling.
Vice Mayor Kou stated the Committee was still waiting for information, but if
Mountain View was placing this on their calendar to vote on and submit to
Caltrain, then the Committee needed to start a conversation with Mountain
View soon or something needed to be on the Committee’s calendar.
Transportation Director Kami declared that Mountain View had already taken
that action, so staff would reach out to Mountain View to determine the path
they took that provided them with a response from Caltrain, and staff would
take a similar path.
Council Member Cormack inquired if that could be an agenda item for the
December meeting, which there could be a discussion and a
recommendation, if appropriate, to City Council.
ACTION MINUTES
Page 4 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Transportation Director Kami believed Mountain View conducted a feasibility
analysis, which Palo Alto needed to do in order for Council take action, but
Council would also need to weigh in on doing a feasibility study.
Vice Mayor Kou was concerned timing was a factor and wanted Caltrain to
wait for the Committee’s considerations before making a determination. She
asked if it was possible to get a timeline of where Mountain View or Caltrain
were in their approval process and what would be coming up for approval, so
the Committee could reprioritize or re-look at the planning in order to be on
a similar timeline and so Caltrain would have both cities to consider. She
wanted to see timelines provided with emphasis on the matters that would
have an impact on Palo Alto in terms of decisions, approvals, or requests
made by Mountain View to Caltrain, which would allow Palo Alto time to
provide a request.
Transportation Director Kami expressed that Mountain View was moving
forward, and it seemed Caltrain and Mountain View City Council had
approved it, although they were waiting on confirmation. As far as timing,
staff would not be able to have a report for the Rail Committee Meeting in
December, but they could provide an update at the meeting. They would
work on getting Mountain View and Caltrain’s timeline. They were
significantly further ahead of Palo Alto in their project and were in final
design and nearing construction.
Mayor Burt requested it be agendized in a way that a referral could be made
to Council.
Council Member Cormack asked if Mountain View was ahead on Rengstorff.
Sharing schedules with everyone would be helpful.
Transportation Director Kami answered it was not as far ahead as Castro but much further ahead than Palo Alto.
Mayor Burt did not think Mountain View was ready for construction due to
having to apply for additional funds, so the timeline was not known.
Nadia Naik requested a link to the last VTA Ad Hoc meeting be put on the
agenda for the Rail Committee. Mountain View and Sunnyville had presented
the full alternatives, cost, etc., and those cities had an MOU with Caltrain,
which she believed Caltrain would ask Palo Alto for next month. She
suggested policymakers watch the meeting before the next Committee
meeting when an MOU may be requested.
Council Member Cormack requested it be sent to the Committee in advance
of the next meeting, so it could be reviewed.
ACTION MINUTES
Page 5 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Public Comment Item 1
Gregory Conlin had been on the Rail Committee in Atherton for 20 years. He
addressed the quiet zone and quad gates. He was an advocate of grading
the right of way and a trench from Palo Alto through Atherton, although
Atherton was not receptive to it. He offered to help with the plan.
2. Study Session to review comments received from various stakeholders to
refine conceptual plans for Partial Underpass Alternative at Churchill
Avenue and Underpass Alternatives at Meadow Drive and Charleston
Road. (Continued from Oct 19, 2022)
Senior Engineer Ripon Batia noted there was a correction from a previous
conversation [inaudible 50:58] cross section at Kellogg Avenue with the train
section.
AECOM Consultant Peter DeStefano stated the minimum lane width required
for fire vehicle access was a minimum of 16 feet, not 10½ feet. This would
require roadway widening and removal of a landscape strip and some of the
trees. An exhibit was provided.
Senior Engineer Batia mentioned it was the same width on Seale, Kellogg,
and Churchill Avenues and would have the same impacts to the roadway and
pedestrian structures.
Council Member Cormack believed that losing trees with the 16 feet argued
for a steeper slope.
Discussion ensued regarding a 10-foot versus 12-foot ped/bike ramp,
removing the landscaping strip, removing trees and community feedback,
and replanting. It was concluded that 10 versus 12 feet would not make a
difference for the landscape since 16 feet was needed for the lane width; the
trees were on the City right of way, but community feedback may have been solicited; and the only opportunity for replanting would be relocating the
sidewalk further into private property.
Mayor Burt opined that more time should not be spent on the Kellogg option
as issues had been raised at the City/School Liaison Committee meeting in
reference to the landing area for the underpass taking land from the Paly
High School, and there had been no discussion with Paly. He inquired why
this location was being considered if Seale or that vicinity was a better
location for a landing in Peers Park, etc.
ACTION MINUTES
Page 6 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Transportation Director Philip Kami noted the issue existed at Seale and
Kellogg and believed they would create concepts for Seale as well as
Kellogg.
Nadia Naik of CARRD questioned how the 16-foot lane width was missed
previously, if it was a requirement, and if it would be more cost effective to
buy smaller fire trucks than fix the City. Regarding Kellogg and Seale, both
corners of Seale and Alma were RM30 properties and Kellogg was not zoned
RM30, so there would be less impacts on neighbors at the Seale property
and would allow the City to build housing.
Council Member Cormack proposed not ruling either out until both were
researched and the pros and cons of each evaluated.
Transportation Director Kami anticipated more information would be
available soon regarding pros and cons of both locations. A request had been
made for dot maps. He was not sure how the 16-foot lane width was missed,
but part of the nexus for the consideration came from car-free streets
dealing with 16-foot requirements from the Fire Department. Whether it
would be cheaper to buy smaller fire trucks would be another discussion, but
they had the same conflict with the car-free streets and dealing with an
emergency fire lane and was more than Transportation expected. The 16-
foot lane width was a requirement. It could be negotiated, although there
was no authority to do so.
Vice Mayor Kou stated the issues were on the east side of Alma on Kellogg
and Seale and on Kellogg. She asked if there would be a problem on the
west side of Seale since it was Palo Alto’s land.
Transportation Director Kami voiced it would not necessarily be a problem,
but the implications of using park land for a bike path would be discussed with Legal. He did not think a vote or a rededication would be a hurdle.
Senior Engineer Batia remarked Item 163, which was on the comments
spreadsheet, could be discussed toward the end of the discussion of design
attributes related to the peak pedestrian traffic for signalized intersections.
Council Member Cormack thought it addressed bicycles, and the queues
needed to be designed and agreed to for peak usage. She questioned if
bikes being grouped at queuing was a concern.
Senior Engineer Batia explained how queues worked. Free-flowing crossings
were currently at Meadow and Charleston, and there were no recommended
traffic control [inaudible 1:08:45], but it was suggested that a HAWK or RFB
signal or some improvement be considered, which they would explore. He
ACTION MINUTES
Page 7 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
explained how bikes and pedestrians would be prioritized to have a
continuous flow, so there would be a minimum amount of stop time. Extra
storage could be looked into for being stopped at a crossing. A study had not
been done for pedestrian and bike traffic peak usage.
Transportation Director Kami clarified what would happen as far as grouping
with a light queuing at an intersection, but there would be no grouping with
free-flowing.
Assistant Transportation Director Sylvia Star Lack described how the tunnel
would work.
Council Member Cormack asked if the design meant grouping would not
happen in the future.
Transportation Director Kami confirmed that was correct.
AECOM Consultant Millette Litzinger moved to Slide 18 of the presentation
regarding intersection layouts and vehicle turning radiuses on Alma and
Charleston. She addressed the design and widths of the intersections and
recommended leaving the conceptual design as it was.
AECOM Consultant DeStefano explained why it was relatively wide.
Discussion ensued regarding lane widths, elevations, turning radiuses,
pedestrian and bike crossings and paths, sidewalks, parking strips, private
versus City property, fencing, shifting of turning lanes and eliminating a
right-hand turn lane, and alternatives related to the design focusing on
larger (40-foot) vehicles. It was decided measurements would be considered
in future phases. Utilizing property of San Antonio to East Meadow as an off-
road bike path would not be possible. The fencing would have to be modified
to relocate the sidewalk. Eliminating the right-hand turn lane could be
discussed with Gary Black and shifting of the roadway discussed with Caltrain. Future slides would be labeled with directional arrows to avoid
confusion and would also include information related to potential private
property impacts.
AECOM Consultant Litzinger presented Slide 19 related to options for safety
improvements for pedestrians and bicyclists at the Alma and Charleston
intersection and referenced shorter crosswalk lengths and turning
movements. Consideration could be given to improvements in the next
phase of the design to help with pavement width and making pedestrian
crossings shorter.
ACTION MINUTES
Page 8 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Discussion arose referring to the options for the area being used as a
mountable curb for busses, etc., and an area for pedestrians with shorter
crosswalks, which may have been applied at some point. Staff recommended
this type of improvement be considered at a future stage of planning.
AECOM Consultant DeStefano continued with Slide 20 with regard to
roadway grade/slope and discussed grade percentages. Due to contrasting
comments received regarding flattening versus steepening grades, various
considerations were contemplated, which he presented. One of the first
things done in the layout was determining the design speed, and based on
that they would try to minimize the cost and the footprint for that design
speed.
Discussion ensued related to the slope of the bike and pedestrian ramp and
roadway grades of 10% and 12%. Bike and pedestrian ramps were
determined to be 5% or less.
AECOM Consultant DeStefano furnished examples of 5% to 8% grades and
would return to the Committee with the grade of Oregon Avenue.
Discussion occurred related to bridge thickness, grades, and federal and
state grant requirements in terms of design speeds.
AECOM Consultant DeStefano did not recommend a lower speed and steeper
grade but keeping the design profiles as they were, which provided a
balance of design, speed, safety, and cost, and staff recommended keeping
the proposed design speed and grade at this phase of the conceptual design.
Public Comment Item 2
Greg Conlin referred to there being much traffic and bicyclists at the
Charleston intersection and requested an explanation of Slide 20
regarding the train, the grade, the underpass, and bicyclists.
AECOM Consultant DeStefano provided clarification of Slide 20. He
proceeded with Slide 21 regarding signage for pedestrians and bicyclists,
which several comments from stakeholders had been received. It was an
important part of the design and would develop in more detail in
subsequent phases of the project.
Council Member Cormack opined signage with larger images and smaller
lettering was easier to comprehend.
Vice Mayor Kou wanted ground signage to be considered.
ACTION MINUTES
Page 9 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
AECOM Consultant DeStefano remarked they would try to design for
pavement markings as well. He proceeded with Slide 22 related the loss
of the landscape strip, which concerned some stakeholders. He addressed
loss of the landscape strip and the proposed condition removing the
landscape strip on Alma, similar to Kellogg and Seale.
Discussion ensued regarding a buffer, barrier, and/or visual deterrent,
which AECOM was requesting direction on modifying the design layout,
being cognizant of bike handlebars with a taller structure, for the
approximate 1/4-mile stretch on Churchill, which included right-of-way
impacts. A potential design solution would be to slow the design speed to
25 MPH starting earlier on Northern California Avenue. There could not be
a continuous barrier due to the curb cuts. ADA compliance also needed to
be considered.
Transportation Director Kami inquired if the concepts needed further
refining to include the buffer.
The Committee agreed further refining was needed.
Council Member Cormack indicated it should be done at a later stage in the
process.
AECOM Consultant Litzinger noted the Committee already selected this
alternative, so it would be refinement of the selected design versus the ones
from Meadow and Charleston with the trench and the hybrid.
AECOM Consultant DeStefano continued with Slide 23 concerning the two-
lane roundabout on Charleston, which a lot of stakeholders were concerned
with bicyclists traversing through and had asked if a single-lane roundabout
would suffice. He explained why the traffic engineer recommended a two-
lane roundabout. AECOM recommended performing a more detailed review of the roundabout geometry to possibly refine the diameters slightly and
proposed widening the bike/ped path on the north side.
Senior Engineer Batia noted an email was received from Elizabeth Alexis
regarding extending the bike path to the Carlson intersection, but it
would remove the landscaping strips. He expressed why he recommended
extending only to Mumford.
Public Comment Item 2
Elizabeth Alexis commented she assumed the bike/ped path would go to
Carlson and voiced her reasoning for it being an opportunity. The project
ACTION MINUTES
Page 10 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
was presented one way to the Bike/Ped Committee, and they could have
been more effective if shown different options.
Bruce [Arthur 2:19:06] expressed his reasoning for the two-lane
roundabouts and the existing crosswalks not being good designs. He and
most of the bike community did not like the plan, and moving the
crossing to Charleston would not improve it. The plan should be optimized
for vehicles, pedestrians, and cyclists, not just vehicles.
Rachel Croft stated she had not been aware Council had chosen the partial
underpass for Churchill and was not aware closure was no longer an option.
She was against removing all the trees on Alma. Going back to the first
recommendation of putting the through northbound traffic along with the
southbound lanes may have been a way to retain some of the trees and
eliminate putting the sidewalk next to traffic.
Eric Holm from Palo Alto Unified School District (PAUSD) commented the
widening of the right of way on Kellogg for the bike path was not a viable
option as it would require removal of the bleachers for the football field,
which would require moving the football field.
Vice Mayor Kou asked if a request had been submitted to PAUSD for the dot
maps.
Transportation Director Kami remarked staff was requesting dot maps.
Eric Holm declared they would provide them.
Nadia Naik of CARRD commented the underpass design was the only one
that passed the traffic studies, and the other designs left Meadow and
Charles with a greater F intersection rating than the underpass. There was a
lot of consternation on XCAP regarding the two-lane roundabout, but that
made it work in the traffic study. She inquired if it was possible to reduce it to a one-lane traffic circle and see if it would pass the traffic study. The two-
lane was not first choice for the cyclists but was the only one that offered
cyclists and pedestrians not stopping at Alma.
Transportation Director Kami commented that Gary Black said it failed with
the one-lane roundabout.
Senior Engineer Batia specified there was discussion about weaving length
required to merge traffic, and the two-lane roundabout was needed.
ACTION MINUTES
Page 11 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Nadia Naik of CARRD wanted to make sure everyone watching understood a
selection had been made by Council and recommended more community
outreach be done through the process.
Mayor Burt requested the slide from last month be pulled up related to the
impacts on the Paly side of the Kellogg crossing to make sure everyone
understood.
Discussion arose that Slide 8 presented last month avoided encroaching on
the bleachers for Paly High School, but the updated configuration impacted
the bleachers and was another case for Seale versus Kellogg.
Mayor Burt questioned if from a process standpoint the Committee needed
to recommend to the Council focusing on Seale rather than Kellogg for bikes
and pedestrians.
Transportation Director Kami noted they were collecting the dot maps and
doing initial analysis under the BPTP and expected information soon, which
would help in the decision of Kellogg versus Seale. As far as being agendized
in December enabling a referral to Council, they were prepared to make a
concept for Seale, and no additional direction was needed currently. The
item was needed this week for the December Rail Committee, and there
would be nothing new in the meantime.
Mayor Burt was interested in comparisons of the one- versus two-lane
roundabout and wanted to see the basis for the two-lane roundabout
decision.
Transportation Director Kami proposed it could be evaluated further if the
alternative should progress.
Elizabeth Alexis expressed that it needed to be determined if the one-lane
option would work and suggested taking the approach of being in a constrained environment and going backward to see what could be changed
to make it work, such as a steeper grade, a dedicated right-hand turn lane,
adjusting light signals, etc. If there was no acceptable combination, it may
have to be two lane. She indicated it was more of a turnaround facility than
a roundabout, and questioned if the concept of the road having many short
merges would facilitate faster merging.
Mayor Burt also considered it more of a turnabout rather than a roundabout
with traffic coming from four directions and wanted to ensure the traffic flow
was looked at that way.
ACTION MINUTES
Page 12 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Transportation Director Kami thought staff’s recommendation would be to
consider ways to reduce the size of the roundabout in future phases.
Regarding the slope being increased, he suggested cyclists use the
underpass instead of crossing the street several times. Having a bike/ped
path on both sides would restrict movement.
Discussion ensued regarding two bike/ped underpasses inhibiting [inaudible
2:43:20].
Council Member Cormack stated regarding the turnabout there would be
little traffic coming from the left and should help traffic flow. She questioned
if the plan was optimizing for vehicles and making sure it worked for bicycles
and pedestrians or if it was something else.
AECOM Consultant DeStefano proceeded with Slide 24, which stakeholders
had concerns of breaking north/south continuity for cyclists at Park
Boulevard. He provided suggestions to remove the circuitous movement and
recommended keeping the configuration as it was to minimize property
acquisitions and recommended keeping the grade as it was using a 25 MPH
design for reasons described on Slide 20.
Nadia Naik of CARRD thought a suggestion made by XCAP was to move the
bike path from Park Boulevard to Wilkie Way.
Discussion ensued regarding moving the bike path to Wilkie Way.
AECOM Consultant Litzinger furnished Slide 25 regarding bridge depth
thickness. She noted what the concept designs were based on. There had
been suggestions to fine-tune the structured depth to reduce the footprint. It
was recommended the current depth remain as presented to allow for
flexibility as design decisions were made.
Discussion occurred regarding bridge depth flexibility and structure type to minimize bridge depth.
Vice Mayor Kou voiced the alternative was being considered, not
determined to be the path forward and suggested leaving it open for
consideration as stages of the project developed.
Transportation Director Kami remarked the aspirational goal was to
reduce as much as possible the length of the roadway, property
acquisition, and depth thickness.
AECOM Consultant Litzinger presented Slide 26 related to vertical
clearance, which there had been suggestions to reduce clearance to
ACTION MINUTES
Page 13 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
lessen the project footprint. She referenced Caltrans’ clearance
requirements and recommended keeping the clearances as they were
because they met the standards. The slide indicated it was Caltrain’s
standards, but it was actually Caltrans’ standards.
Vice Mayor Kou asked if Caltrans’ standards had to be followed.
[AECOM Consultant Litzinger 3:06:29] confirmed Caltrans’ standards had
to be followed.
AECOM Consultant DeStefano thought Caltrain’s standards had to be
followed. If guidance was based on Caltrans, that is what they would use.
There was no flexibility with roadway vertical clearance but there was
with pedestrian vertical clearance. Caltrans desired 10 feet for pedestrian
clearance, but 8 feet was minimum.
Mayor Burt was inclined to use the flexibility for the pedestrian clearance.
AECOM Consultant Litzinger displayed Slide 27 related to aesthetics, and
there had been suggestions to enhance the aesthetics of the alternatives
as shown in the renderings. She recommended keeping the alternatives
as they were. After selection of a preferred alternative, consideration
could be given to the iterations of updating the renderings meeting the
desired aesthetics.
AECOM Consultant DeStefano presented Slide 28 regarding raising the
rail, which some had suggested raising the rail profile to reduce the
extent of the roadway lowering, which could reduce the project footprint
and the grades. While acknowledging there would be benefit and
advantages of that, he furnished reasons for keeping the rail at the
existing elevation and recommended no change to the rail profile for the
underpass options.
Transportation Director Kami provided Slide 29 in reference to the
summary of refinements and covered what was listed on the slide.
Direction was not needed regarding this, and they could proceed if there
were no issues. Under Council direction, they were to collect feedback
and proceed with design refinements for the underpass alternative.
Nadia Naik of CARRD opined there should be no refinement to the
alternative of the Charleston and Meadow underpass separating the bike
path to each side of the street.
ACTION MINUTES
Page 14 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Mayor Burt recommended no work be done with regard to Kellogg until
receipt of the dot maps and not proceeding on Kellogg unless the maps
showed it was a superior location.
Transportation Director Kami noted they could hold on the refinement of
Kellogg until Seale was determined.
Nadia Naik of CARRD inquired if feedback was being gathered and then
AECOM would provide an estimate or if AECOM was proceeding with the
refinements, and asked how it interlaced with Caltrain’s technical
requirements. She had a phone call, which indicated Caltrain might have
something as early as February regarding the things they were aware of,
so she questioned how that would change the alternatives, including
alternatives the Committee did not talk about.
Transportation Director Kami declared the current contract with AECOM
was to do the design refinements, which could be initiated after the
Committee meeting. He provided Slide 29 from the last Rail Committee
meeting noting the items requiring the Rail Committee’s direction.
Council’s direction was to proceed with stakeholder feedback and refine
the designs, so without additional scope they could proceed. They were
developing updated plans, exhibits, and renderings for the underpass
alternatives. AECOM was working on geotechnical studies for subsurface
conditions to evaluate the feasibility of the proposed trenching, etc. A
peer review cost estimate and design assumptions for the trench
alternative was in progress. Completion of that was anticipated by the
summer of 2023 at which time the Rail Committee could review and
recommend to City Council preferred alternatives for the other crossings.
The caveat was technical issues and design criteria were pending. At some point, the Committee needed to make a determination regarding
whether to proceed with the information currently available or if the
timeline should be extended in order to wait for Caltrain’s criteria, which
they may or may not get in February. Caltrain wanted to discuss a service
agreement with the Committee at the next meeting. They could proceed
with some of the refinements, but some of the alternatives could be
impacted by Caltrain’s responses.
Mayor Burt asked if the Committee needed to identify the design
standards that mattered most to the Committee and in a targeted
discussion with Caltrain get their responses and see if there should be
more alignment before making a decision of what to proceed with.
Transportation Director Kami expressed that was reasonable. Caltrain
would be at the next meeting.
ACTION MINUTES
Page 15 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Vice Mayor Kou inquired if it would be limited to an agreement. Decisions
were in flux, and Caltrain would have to formulate and analyze all the
standards before coming back to the Committee with answers.
Transportation Director Kami did not think the corridor-wide strategy
would be finalized by Caltrain at the next meeting. The meeting would be
related to the service agreement needed to move forward with selecting
[an LPA 3:23:27], etc.
Mayor Burt mentioned Caltrain wanted an MOU, and the Committee
wanted answers.
Vice Mayor Kou asked what was needed from the Committee.
Transportation Director Kami indicated no action was needed. They
needed to know if refinements should be proceed with or if they should
wait for Caltrain’s schedule. Moving on Caltrain’s schedule would delay
what was currently scheduled.
Mayor Burt wanted to see the mapping of the design refinements that
mattered the most to the Committee and then have a discussion with
Caltrain, not necessarily at the next meeting, to get a sense of where
they would be headed before giving an official position.
Transportation Director Kami shared they had mentioned to Caltrain
many times (including a formal letter) the things delaying the City.
Nadia Naik of CARRD highlighted that Caltrain’s answer to the four-tracks
for South Palo Alto may take longer than an answer to Churchill, even
though the Committee had prioritized Meadow and Charleston above
Churchill, so part of it was perhaps having a visualization of if something
cannot be moved forward, then moving forward with something else. It
would be helpful to know the impacts of each design, understanding they may have to be taken in a different order.
Transportation Director Kami stated the City’s designs required some
Caltrain right of way, and he expected Caltrain would be very protective
of that right of way.
Senior Engineer Batia would develop a list of five or six items [inaudible
3:36:32], look at how they would be applicable, and develop a matrix
providing [inaudible 3:26:41].
Mayor Burt noted the bike path behind Paly was in the Caltrain right of
way.
ACTION MINUTES
Page 16 of 16
Rail Committee Meeting
Action Minutes: 11/18/2022
Nadia Naik of CARRD asked when the geotechnical information was
expected, as it would be helpful for the decisionmakers to understand
when work already asked for was anticipated so it could be agendized
appropriately.
Transportation Director Kami commented the tasks he mentioned earlier
were expected to be completed by the summer of 2023, including the
geotechnical. The refinements of the alternatives was one of the tasks.
Public Comment Item 2
Adrian Brandt commented regarding the buffer/sidewalk topic that 35
MPH traffic should be avoided. He recommended a short wall preventing
vehicles from climbing the curb but still having [open ends for] [inaudible
3:28:52]. He addressed bridge thickness and raising the train tracks. He
urged a viaduct, which would address grades, traffic movement, etc.
Vice Mayor Kou asked Transportation Director Kami if they could talk
about the agenda for December. She requested community input and
feedback regarding Item 2.
Next Steps and Future Agendas
Discussion and a recommendation, if appropriate, to City Council voting on
the four tracks at the Castro Station.
Dot maps and initial analysis under the BPTP in reference to the decision of
Kellogg versus Seale for the bike/ped path impacting the bleachers of Paly
High School.
Discussion of a service agreement with Caltrain.
Adjournment: The meeting was adjourned at 4:22 P.M.