HomeMy Public PortalAbout2023-111 Resolution Approving Change Order #3 for the City Hall Parking Lots Reconstruction ProjectRESOLUTION 2023-111 Resolution Approving Change Order #3 for the City Hall Parking Lots Reconstruction Project WHEREAS, KE Flatwork was awarded a contract for the City Hall Parking Lots Reconstruction project via Resolution 2023-043 Resolution Awarding a Contract to KE Flatwork for the City Hall Parking Lots Reconstruction Project, approved June 13, 2023, in the amount of $375,957.25; and, WHEREAS, Change Order #1 was approved on September 12, 2023, via Resolution 2023-082 Resolution Approving Change Order #7 for the City Hall Parking Lots Reconstruction Project; and, WHEREAS, Change Order #2 was approved on November 14, 2023, via Resolution 2023-107 Resolution Approving Change Order #2 for the City Hall Parking Lots Reconstruction Project; and, WHEREAS, it is necessary to make the following additional changes to the project as described in Change Order #3 provided by MSA Professional Services: Original Award: $ 375,957.25 Adjustments per Change Order #1 (approved 09/12/2023): + $ 17,000.00 Adjustments per Change Order #2 (approved 11/14/2023): + $ 27,388.53 Adjustments per Change Order #3: Reduction in costs for sawcut breakout line, sawcut tree root, PCC pavement removal, SW removal PCC, trench backfill, abutting pavement joint rigid tie drilled, PCC pavement with integral curb, PCC sidewalk, signpost sleeve, driveway drop curb special, sawcut contraction joint, topsoil, landscape wood edging, joint sealing, joint sealing isolation joint, joint sealing expansion joint, paint line white, dumpster bollards - $ 14,210.40 New Amount of Contract with Change: $406,135.38; and, WHEREAS, the funding sources for this action are: #301-650-6499, General Fund, City Hall Buildings, Other Contractual Services #301-150-6499, General Fund, Fire, Other Contractual Services. NOW, THEREFORE BE IT RESOLVED by the City Council of the City of Riverdale, Iowa, that: Section 1. Section 2. Section 3. Change Order #3 is approved. The Mayor and Clerk are authorized to sign Change Order #3. KE Flatwork is authorized to begin work pursuant to Change Order #3 as of the date of this resolution. City of Riverdale, Iowa 110 Manor Drive, Riverdale, Iowa 52722 I (563) 355-2511 www.riverdaleia.org Passed and approved this 28th day of November 2023. APPROVED: Anthony Heddiesten, Mayor ATTEST: City of Riverdale, Iowa 110 Manor Drive, Riverdale, Iowa 52722 1 (563) 355-2511 www.riverdaleia.org Change Order No. 3 Date of Issuance: November 16, 2023 Project: City Hall Parking Lots Contract Riverdale City Hall Parking Lots Contractor. KE Flatwork Effective Date: November 16, 2023 Owner City of Riverdale Owner's Contract No • NIA Date of Contract June 26.202 Engineees Project No.: 10876102 The Contract Documents are modified as follows upon execution of this Change Order: Description: FINAL ADJUSTED QUANTITIES: PAY ITEM 1 - SAWCUT BREAKOUT LINE, 8" - 4 LF, -$40.00; PAY ITEM 2 - SAWCUT BREAKOUT LINE, 7.75" - 61 LF, $610,( PAY ITEM 3 - SAWCUT BREAKOUT LINE, 5" - 18 LF, $180.00: PAY ITEM 5 - SAWCUT TREE ROOT, 24" DEEP - 5 LF, $100.00: PAY ITEM 6 - PCC PAV'T REMOVAL, 8" - 9 SY, $135.00: PAY ITEM 7 - PCC PAVT REMOVAL, 7.75" - 7 SY, $105.00: PAY ITEM 8 - PAV'T REMOVAL 5" - 5 SY. 575.00: PAY ITEM 10 - SW REMOVAL, PCC - 12.8 SY, $192.00; PAY ITEM 30 - TRENCH BACKFILL - 28,75 TON, $802.50: PAY ITEM 33 - ABUTTING PAVEMENT JOINT RIGID TIE, DRILLED - 134 EA, $1,340,00; PAY ITEM 37 - PCC PAVEMENT WIINTEGRAL CURB, 8" - 9 SY, $900.00: PAY ITEM 39 - PCC PAVEMENT WITH INTEGRAL CURB, 6" - 47 SY, $3,384.00; PAY ITEM 41 - PCC SIDEWALK, 6" - 12 SY, $1,200.00: PAY ITEM 42 - SIGN POST SLEEVE - 1 EA, $250.00: CONTINUED ON NEXT PAGE TOTAL = $14,210.40 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: $ 375,957.25 Original Contract Times: Q Working days ® Calendar days Substantial completion (days or date): N/A Ready for final payment (days or date): [Increase] [Decrease] from previously approved Change Orders [Increase] [Decrease] from previously approved Change Orders No. 1 to No.: 2 No. to No. 3 44.3 8.53 Contract Price prior to this Change Order $ 420.345.78 - Inon tree} [Decrease] of this Change Order. $ 14.210.40 Contract Price incorporating this Change Orden s 406,135.38 Substantial completion (days): Ready for final payment (days): Contract Times prior to this Change Order. Substantial completion (days or date): Ready for final payment (days or date): [Increase] [Decrease] of this Change Order Substantial completion (days or date): Ready for final payment (days or date): Contract Times with all approved Change Orders: Substantial completion (days or date): Ready for final payment (days or date): RECOM ED: By. ngnter(Aulhonzea Signature) Date: November 17, 2023 Approved by Funding Agency (if applicable): ACCEP4 EI / ei 1)Isr ACCEP By: 8y: Owner (Authorized Signature) Contractor (Authorized Signature) Date: Date: 11/17/23 Date: EJCDC C-941 Change Order (2007 Edition) 00 63 63-1 Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute. FINAL ADJUSTED QUANTITIES (CONT.): PAY ITEM 51 DRIVEWAY DROP CURB SPECIAL - 8.2 LF, $246.00: PAY ITEM 52 - SAWCUT CONTRACTION JOINT - 418 LF, $836.00; PAY ITEM 54 - TOPSOIL - 0.5 CY, $25.00: PAY ITEM 58 - LANDSCAPE WOOD EDGING - 5 LF, $100,00; PAY ITEM 59 - JOINT SEALING - 418 IF, $1,254.00: PAY ITEM 60 - JOINT SEALING ISOLATION JOINT - 337 LF, 51,011.00' PAY ITEM 61 - JOINT SEALING EXPANSION JOINT - 20.5 LF, $102.50: PAY ITEM 62 - PAINT LINE - WHITE, 4" - 67.7 LF, $135.40: PAY ITEM 63 - PAINT LINE, WHITE, 6" - 1 5 LF, $6,00: PAY ITEM 71 - DUMPSTER BOLLARDS - 6 EA, $6,600.00 TOTAL = $14,210.40