HomeMy Public PortalAbout2005.004 - LUARESOLUTION NO. 2005.004
"A RESOLUTION OF THE LYNWOOD UTILITY AUTHORITY OF THE CITY
OF LYNWOOD AWARDING A CONTRACT TO WANG MILESTONE
CONSTRUCTION INC., IN THE AMOUNT OF $2,173,000.00 FOR THE
LYNWOOD SENIOR CITIZEN CENTF,R, IMPROVEMENT PROJECT,
PROJECT NUMBER OS-5297, AND AUTHORIZING THE PRESIDENT TO
EXECUTE THE AGREEMENT".
WHEREAS, the Lynwood Senior Citizen Center improvement Project, Project
No. OS-5297 is scheduled for completion during the FY 2004-2005; and
WHEREAS, the Lynwood Senior Citizen Center Improvement Project is fimdcd by
Lynwood Utility Authority (L.U.A) and by Community Development Block Grant (CDBG)
funds; and • ~•,
WHEREAS, the bid opening was held on February 23, 2005 and Wang
Milestone Construction Inc. was the apparent lowest bidder al $2,173,000.00; and
WHEREAS, a reference check has revealed that this contractor has the necessary
experience for this type of project.
NOW THEREFORE, the Lynwood Utility Authority of the City of Lynwood
does hereby find, proclaim, order and resolve as follows:
Section 1. That the contract for the Lynwood Senior Citizen Center Improvement
Project, project Number OS-5297 be awarded Wang Milestone Construction Inc. for its low
bid of $2,173,000.00
Section 2. That the President is hereby authorized to execute the agreement
between the Lynwood Utility Authority and Wang Milestone Construction Inc..
Section 4. This resolution shall take effect immediately upon its adoption.
PASSED, APPROVED and ADOPT ,D this th day of ar~005.
Ramon Rodr~ ez, President
A.i...:S~S
Andrea L. 1looper, Secretary
APPROVED AS TO FORM
Cit~Attorncy
Aut ority Counsel
APPROVED AS TO CON'1'EN"f:
~. ~ ~'7Hv
Jos ph Wang, t ,xecutivc
erector
r~%~•~
Yadollah Parhadi, P.E
Director of Environmental Services/
City Engineer