HomeMy Public PortalAboutResolution 01:230 No. 01-230 Date tit Ad,)ption duly 19, _2001
APPROVING CHANGE ORDER NO. 2 - DOROTHY STREET PUMP
STATION IMPROVEMENTS
WHEREAS, the Governing Body of the Borough of Carteret awarded a contract
to Maple Construction Co. in the amount of $367,000.00 for improvements to the
Dorothy Street Pump Station; and
WHEREAS, the Borough's Consulting Engineer for the project, T & M
Associates, has advised the Governing Body that a modification of the contract is
reasonable and necessary and has recommended that the aforesaid contract be
modified in accordance with Contract Change Order #2 (see attached letter); and
WHEREAS, Change Order #2 includes increases in the cost of the contract due
to the recommended purchase of a new generator versus upgrading the existing
generator and for the cleaning, repairing, and sealing of the Flow Meter Manhole;
as well as a reduction in the contract price due to the deletion of pump spare parts
and the deletion of landscaping ~vork which was not required, with the net impact
of said supplemental ~vork resulting in a reduction of $14.90 in the original
contract price; and
WHEREAS, Change Order #2 also includes a 70-day extension of time to allow
for the ordering, delivery and installation of the ne~v generator; and
WHEREAS, the Borough's Consulting Engineer, T & M Associates has certified
that said changes and/or modifications were unforeseen at the time of the award
of the contract.
NOW, THEREFORE, BE IT RESOLVED by the Mayor and Borough Council
of the Borough of Carteret as follows:
1. Contract Change Order #2 is hereby approved.
2. The appropriate Borough Officials are hereby authorized to
execute Change Order #2.
Adopted this 19th day on July
and certified as a true copy of the
original on July 20, 2001.
KATHLEEN M. BARNEY, RMC/CMC
Municipal Clerk
RECORD OF COUNCIL VOTE
FAZEKAS RIOS
QUINONES SANTORO
REIMAN SOHAYDA
X - Indicate Vo;¢ AB - Absent NV. Not Voling XOR - Indicalcs Voic lo Ovcrrt~lc Vcm
Adopted at a meeting of lhe Municipal Council I"