HomeMy Public PortalAboutORD16143BILL NO. 2021-018
SPONSORED BY Councilmember Fitzwater
ORDINANCE NO. I CD 14
AN ORDINANCE OF THE CITY OF JEFFERSON, MISSOURI, AUTHORIZING THE
MAYOR AND CITY CLERK TO EXECUTE AN AGREEMENT WITH COLE COUNTY,
SETTING PROCEDURES FOR THE MSP JOINT CITY AND COUNTY CAPITAL
IMPROVEMENT PROJECT.
NOW, THEREFORE, BE IT ENACTED BY THE COUNCIL OF THE CITY OF
JEFFERSON, MISSOURI, AS FOLLOWS:
Section 1. The Mayor and City Clerk are hereby authorized and directed to execute
an agreement with Cole County regarding setting procedures for the MSP Joint City and
County Capitol Improvement Sales Tax Project.
Section 2. The agreement shall be substantially the same in form and content as
that agreement attached hereto as Exhibit A.
Section 3. This Ordinance shall be in full force and effect from and after the date
of its passage and approval.
Passed: i
i
Presiding Officer
ATTEST:
"N' F_0 0A . ffl"'JM��
Approved: 22 202J
Mayor Carrie Tergin
APPROVED AS TO FORM:
City Att#6ey
Agreement Setting Forth Procedures for the
MSP Development
Joint City and County Capital Improvements Sales Tax Project
THIS CONTRACT, made and entered into this I � of 2021 by and
between the City of Jefferson, Missouri hereinafter called "City" and the County of Cole,
Missouri hereinafter called "County".
1. Proiect: The project includes the construction of roadways within the MSP
development including but not limited to the extension of Chestnut and a
roadway serving the proposed hotel development. The project will also
include the preparation of commercial pad sites, stormwater controls,
pedestrian accommodations, lighting, and landscaping.
2. Timing: The design of the project will be undertaken in 2021 with project
construction anticipated to begin in 2022.
3. Project Administration:
a. The City of Jefferson shall be responsible for all aspects of the project
administration.
b. The City shall establish accounts particular to the project from which all
costs are paid and tracked.
c. Any "in-house" staff services that are provided, such as engineering,
construction inspection, etc., shall not be charged to the project.
d. The City shall follow their normal purchasing, procurement
and contracting procedures.
e. The City and County Public Works Directors shall jointly
review the construction bids for the project and recommend
the lowest and best bid to the City Council and County
Commission for approval. The bid shall receive concurrence
from the County Commission prior to be awarded by the City
Council.
f. Information signage shall be erected by the City indicating the
work is a "Joint City and County Capital Improvement Sales
Tax Project".
Page 1 of 3
4. Financial Contributions: The County's contribution shall be $1,553,908.23 the
payment of which shall be made to the City within 30 days of the signing of this
agreement. The City will also contribute $1,446,091.77. The project will also
make use of $1,500,000 provided through an EDA grant. Any change order to
the contract will be paid or received at 100% by the City.
5. Participation: It is understood that the County portion of the funding for this
project will be used for the construction of the proposed roadways and
associated stormwater infrastructure.
6. Notices: All notices required or permitted hereunder and required to be in writing
may be given by first class mail. If to the City, notice shall be sent to the City
Administrator at 320 East McCarty Street, Jefferson City, MO 65101. If to the
County, notice shall be sent to the Cole County Commission at the Cole County
Courthouse Annex, 311 East High Street, Room 200, Jefferson City, MO 65101.
The date of the delivery of any notice shall be the date falling on the second full
day after the day of its mailing.
7. Agreement Binding: This agreement is to be binding on the successors and
assigns of the parties hereto and is not to be assigned by either party without
first obtaining the written consent of the other.
8. Applicable Law: The Laws of the State of Missouri shall govern the
validity, performance and enforcement of this agreement.
Page 2 of 3
IN WITNESS WHEREOF, the parties hereto have caused this agreement to be executed
on the day and year indicated below.
Executed this _ day of
2021
On behalf of the Commission of Cole
County Missouri
Executed this 2-)- day of J6CQIC*'�
2021
On behalf of the City of Jefferson, Missouri
6wY�La'I",
Sam Bushman, Presiding Commissioner Carrie Tergin, Mayor
County Clerk City Oerk
Cole County Auditor
1 certify that the a is a balance otherwise unencu bered to
the credit of the appropriation to which it is to be charged
and a cash balance otherwise unencumbered in the treasury
to the credit of the fund from which payment is to be incurred.
This funding is subject to accounting officer certification in
2015 after appropriation and encumbrance.
Approved as to form:
City Counslor