HomeMy Public PortalAboutAB00-146CITY COUNCIL City Of McCall
AGENDA BILL 216 East Park Street
Number AB 00-146 McCall, ID 83638
Date December 14, 2000
ITEM INFORMATION
SUBJECT:
Original Agenda
Date & Bill No.
Department/Committee/Individual
Initials
Remarks
Art Roberts Park
A
Mayor / Council
Dock Replacement grant
P
City Manager
P
City Treasurer
R
City Attorney
O
City Engineer
V
City Planner
A
Public Works
L
Golf Course
COST IMPACT: $111,390
S
Parks & Recreation
FUNDING
SOURCE:
City Clerk
$88,290 IDPR, $23,100 local
Airport Manager
TIMELINE: Construction
Librarian
completed by July, 2002
Police Chief
SUMMARY STATEMENT:
See
attached sheet.
RECOMMENDED ACTION:
Authorize the Mayor to sign the application for a Waterways Improvement Fund grant from the Idaho Dept. of Parks & Recreation.
RECORD
OF COUNCIL ACTION
Meeting Date
Action
AB 00–146
Art Roberts Park Dock Replacement Grant
SUMMARY STATEMENT:
The existing docks at Art Roberts Park are in poor condition. They offer an unrealized opportunity for public access
to the Lake and increased short-term public boat mooring. The Idaho Dept. of Parks & Recreation (IDPR) provides grant funding under the Waterways Improvement Fund program. Funds are
available for activities that increase or enhance motorized boating opportunities on waters of the State.
The attached draft IDPR grant application seeks grant funding of $88,290 for
replacement and expansion of the docks at Art Roberts Park. As the attached site plan shows, the eastern dock will be replaced, including the Sheriff’s Dept. mooring slips. The western
dock will be extended to provide room for additional short-term public moorings.
The total budget for the project is $111,390. 20% of the project cost will be provided in local match.
The Valley County Waterways Board will provide $14,000 direct cash match toward the project. City labor for the removal and disposal of the existing docks will be provided as an in-kind
match. Because the Valley County Waterways match funds are not available until 2002, the project will be constructed in early 2002. The construction estimates have been provided by Inland
Marine.
The dock design was developed with input from Dan Pillard and Bob Peckham. Peter Johnson, Big Payette Lake Water Quality Council; the Idaho Department of Lands; the Valley County
Waterways Board; and the Valley County Marine Patrol have all been consulted on the design. The Parks & Recreation Committee will be reviewing the proposed dock expansion on Monday December
11. Their recommendation will be available at the Council meeting.
These IDPR funds can only be used for activities related to motorized boating, and so are not available for work at
Mill Park.