C HAPTER 7 | IMPLEMENTATION & PHASING J OERGER RANCH SPECIFIC PLAN
1 | Introduction
Th is section is intended to identify the orderly
development implementation and phasing of
the Joerger Ranch Specifi c Plan infrastructure.
Th e Joerger Ranch Specifi c Plan area is divided by
state and local roadways that create four separate
and distinct quadrants. Market demand, economic
conditions and fi nancing will all factor into the
incremental implementation and phasing of uses.
2 | Common Infrastructure
Th e overall Joerger Ranch Specifi c Plan has
common infrastructure improvements that
benefi t all properties within the plan area. Th ese
improvements are needed to be constructed as
major portions of the plan area develop. Interim or
incremental improvements may be allowed by the
Town Engineer on a case by case basis (see Chapter
5). Th e common infrastructure improvements are
categorized into three separate areas:
1. Highway 267 / Brockway Road / Soaring Way
Intersection Improvements
Th e fi rst property owner to develop in either the
BIZ or CR zone shall be required to construct
the following Highway 267 intersection
improvements (see Figure 7-1) prior to
recordation of any parcel or fi nal maps or
issuance of any temporary or fi nal occupancy
of any buildings:
a. Soaring Way - Widen and construct
left turn lane, right turn lane, west-bound
& east-bound through lanes, Class II bike
lanes, curb/gutter, sidewalk, and crosswalk.
b. Highway 267 - Widen Highway 267
and construct northbound right turn lane,
crosswalks and all necessary striping.
c. Brockway Road - Widen and construct
right turn lane, left turn lane, east-bound
and west-bound through lanes, Class II
bike lanes, curb/gutter, sidewalk, Class I
bike path, and all necessary striping.
FIGURE 7-1: HIGHWAY 267 / BROCKWAY ROAD / SOARING WAY INTERSECTION IMPROVEMENTS
7.3
J OERGER RANCH SPECIFIC PLAN I MPLEMENTATION & PHASING | C HAPTER 7
All future construction shall be required to pay
their “fair share” portion of actual infrastructure
costs and provide proof of payment to the
Town prior to issuance of building permits or
recordation of parcel or fi nal maps.
2. East Side: (East of Highway 267) Soaring
Way / Joerger Drive Improvements
Th e fi rst property owner to develop east of
Highway 267 shall be required to construct
the following improvements (see Figure 7-2)
prior to recordation of any parcel or fi nal maps
or issuance of temporary or fi nal occupancy
of any buildings. If the fi rst development is
proposed within the CR zone, the infrastructure
requirements outlined in #1 above shall also
apply. All future new construction shall be
required to pay their “fair share” portion of
actual infrastructure costs and provide proof
of payment to the Town prior to issuance of
building permits or recordation of any parcel
or fi nal maps.
a. Soaring Way - Construct roundabout at
Soaring Way & Joerger Drive intersection,
widen Soaring Way east of roundabout
and construct sidewalks, on-street parking,
curb/gutter, Class II bike lanes, public
transit stop, and all necessary utilities.
3. West Side: (West of Highway 267) Brockway
Road / Martis Drive and Hope Court
Improvements
Th e fi rst property owner to develop west of
Highway 267 shall be required to construct the
following improvements (see Figure 7-3) prior
to recordation of any parcel or fi nal maps or
FIGURE 7-2: SOARING WAY / JOERGER DRIVE IMPROVEMENTS
7.4
C HAPTER 7 | IMPLEMENTATION & PHASING J OERGER RANCH SPECIFIC PLAN
issuance of temporary or fi nal occupancy of any
buildings. If the fi rst development is proposed
within the BIZ zone, the infrastructure
requirements outlined in #1 above shall also
apply. All future new construction shall be
required to pay their “fair share” portion of
actual infrastructure costs and provide proof
of payment to the Town prior to issuance of
building permits or recordation of any parcel
or fi nal maps.
a. Brockway Road - Construct necessary
improvements along Brockway Road
(including Class II bike lanes & Class
I bike path), construct Martis Drive
(including Class I bike path), construct
improvements at Brockway Road/Martis
Drive intersection and Brockway Road/
Hope Court intersection, crosswalks, and
all necessary utilities. All improvements
and alignments shall be re-evaluated upon
a specifi c development application for
Parcel 4 and shall be determined by the
Town Engineer.
b. Hope Court - Construct Class I bike
path along Hope Court, construct necessary
roadway & striping improvements, and all
necessary utilities (fi nal alignment to be
determined by Town Engineer).
FIGURE 7-3: BROCKWAY ROAD / MARTIS DRIVE IMPROVEMENTS
7.5
J OERGER RANCH SPECIFIC PLAN I MPLEMENTATION & PHASING | C HAPTER 7
Th e existing winery is a “legal non-comforming
use” which will allow the winery to continue
its current operation without being subjected
to the west side infrastructure requirements as
outlined in this Specifi c Plan. If the winery use is
discontinued, expands or substantially changes its
operations or characteristics, the new use would be
subject to the provisions of this Specifi c Plan.
Th e non-profi t center proposed on Hope Court
would be solely responsible for and only subject
to the utility, roadway, and Class I bike path
improvements along Hope Court. If the non-
profi t center is not constructed, any new use on
the parcel will be responsible for all additional
common infrastructure improvements per #1 and
#3 above.
TABLE 7-2A: PHASING & IMPLEMENTATION
Note:
1. Interim improvements can be considered by the Town Engineer as set forth in Chapter 5, Section 2.2.
7.6
C HAPTER 7 | IMPLEMENTATION & PHASING J OERGER RANCH SPECIFIC PLAN
3 | Workforce / Inclusionary Housing
Th e 2007-2014 Housing Element requires that all
new residential and non-residential projects provide
aff ordable housing to meet Truckee’s housing needs.
General Plan Housing Element program H-1.2.3
requires that all new residential development allocate
at least 15 percent of the units as aff ordable to very-
low, low-, and moderate-income households. For
non-residential projects that create jobs, Housing
Element program H-1.3.4 requires the construction
of aff ordable housing for at least 50 percent of the
projected very low-, low- and moderate-income
workforce.
To ensure General Plan consistency, approximately
4.0 acres of the Joerger Ranch Specifi c Plan area
is zoned RMW-20 which allows multi-family
residential at a minimum density of 18 units/acre
and maximum density of 20 units/acre. Th e RMW-
20 zone is intended to capture the workforce housing
needs of all future buildout of the Specifi c Plan.
Because housing needs for the entire project will
be met with the development of the RMW-20 zone,
future land uses are not required to demonstrate
consistency with Development Code Chapters
18.214 (Inclusionary Housing) or 18.216 (Workforce
Housing). Th e construction of housing outside of
the RMW-20 zone is permitted (airport restrictions
excluded) but is not required.
Joerger Ranch was primarily created for non-
residential uses and has several site constraints that
limit compatible locations for new residences (ie.
airport restrictions, highway location, drainage
areas, etc.). As an incentive for one developer to
construct a single housing project on the RMW-20
zoned parcel, future development on the RMW-
20 site will not be required to provide inclusionary
housing and deed restrictions will not be required.
Additional information about the RMW-20 parcel
is discussed in Chapter 4 (Residential Multi-family
RMW-20 Zoning District).
Th e Joerger Ranch workforce housing requirement/
calculation is shown in Table 7.4A. Based on an
estimated 0.25 Floor Area Ratio (FAR) and using the
employee generation assumptions in Development
Code Chapter 18.216 (Workforce Housing), jobs
would be created for approximately 578 full-time
equivalent employees, if maximum buildout was
achieved. Th is equates to a demand of approximately
82.7 workforce housing units. Th e RMW-20 zoning
district can accomodate up to 80 workforce housing
units, excluding any density bonuses permissible
by Development Code Chapter 18.212 (Density
Bonuses, Concessions and Incentives). Since it is not
likely that Joerger Ranch will develop at a maximum
density of 0.25 FAR, zoning for 80 residential units
in teh RMW-20 zone is considered suffi cinet for
complying with General Plan workforce housing
requirements. No additional housing units or in-
lieu fees are required for future development projects
within the Joerger Ranch Specifi c Plan Area.
7.7
J OERGER RANCH SPECIFIC PLAN I MPLEMENTATION & PHASING | C HAPTER 7
TABLE 7-3A. Workforce Housing Calculations by Zoning District
Zoning DistrictLand Area
within B1/B2
Airport Zone
(Acres)
Land Area
Outside Airport
Zone (Acres)
Development
Potential
(0.25 FAR)
Full-Time
Equivalent
Employees
# of Workforce
Housing Unit
Regional Commercial (CR)016.3177,50735550.7
Lifestyle Commercial (CL)04.751,18310214.7
Manufacturing/Industrial (M1)1.08.592,5659313.3
Business Innovation Zone (BIZ)8.62.628,314284.0
Multi-family Residential (RMW-20)04.0000
Open Space (OS)6.814.1000
Total16.450.2349,569 SF57882.7
Note:
1. Th e number of required workforce housing units is based on the maximum development potential with a
fl oor area ratio of 25%. Land area that is zoned Open Space plus land area that falls within the B1/B2 Airport
Zone are not included in the “development potential” calculations.