Priority "A+" for FY 2004/05
PriorityStatusFuture Action/Timeline
Affordable/Workforce housing studies & Draft seasonal housing needs assessment and Strategic Plan for Implementation. Including GP
projects land use inventory report complete. housing elements
PC-2 APPROVED - 225 affordable housing Schedule meeting with Staff, Placer County, and
units under construction. Nevada County for Implementation plan.
Historic Resources Inventory & Standards Standards Adopted certified local government Incentive criteria to be presented to Council in
status received, national register status under August
consideration at State.
Corporation Yard Relocation Site selection complete, base mapping Approve interagency agreement to fund master
complete. Master planning under way. planning, summer 2004.
Mill Site Grant Grant received. Property purchase completed, Reports to Council as work progresses.
phase 1 of millsite plan underway
River Revitalization Planning Will move forward late this year. Scope of work to be approved by Council.
Recommend a “land use/processing Staff to develop policies for Council
schedule” consistent with the Town’s consideration this summer and fall.
ability to review, process and deliberate on
development proposals and other Town
policy matters.
General Plan Update General Plan update in process. On-going
Airport District CLUP Council approved comment on plan Committee formation in process
Siller Appeal Appeal filed with Placer County Board of Public hearing Scheduled October 4, 2004 in
Supervisors Kings Beach
Items as of August 2004
Page 1
Town of Truckee
Priority "A" for FY 2004/05
PriorityStatusFuture Action/Timeline
Pioneer Trail/Bridge Street Extension EIR Consultant Selected Conduct EIR technical work concurrent with General Plan
Update
AB 1600 Facilities Fees & Waiver Draft facilities fee study complete Meetings with interested groups – ongoing
Policies Council consideration – July 04
SR 89 Corridor Study and “Mouse On hold pending state funding Monitor state budget.
hole” Provide to the Lobbyist to pursue Council to work with State Legislature.
SR 89 / I-80 Roundabouts Design work continuing Construction Summer 2004
Downtown Parking Analysis Underway Consideration of paid parking and centralized parking
management policies in August
Lighting Guidelines and Specs per Awaiting Available staff resources.
General Plan
Development Applications – PC1, 2, & In progress Provide Council with an expected timeline to process the
3; Hilltop; McIver Hill; Deerfield applications utilizing current staff levels.
Land Use Application Processing Schedule.
Brockway Road Design Configuration, Proceed with design work on Brockway Rd. 2005
NC/PC Relationships Regional Issues Nevada County agreement complete. Placer Complete and adopt Placer County Agreement – fall 2004
County agreement underway for Traffic
Impacts
Solid Waste Property Tax Dennis Crabb, Steve and Alex negotiating Recommendation for actions Winter 04
with Nevada County
River Trail Planning – Additional Environmental for phase III underway. Phase II Ribbon Cutting 7/31/04, remaining phases under
Phase & Trail Maintenance Program Phase-II Construction Complete in process
Open Space Committee working on polling Recommendations to Council summer 04
Measure A projects for prioritization Creating a list of potential projects for Council Anticipated to be before Council fall 2004 as part of CIP
to prioritize. Process.
Trout Creek Restoration Project Environmental document complete. Begin construction plans and phased implementation.
(Moved from on-going to an A priority)
Provide to Lobbyist for potential Prop. 50
funding.
Green Building Committee assignment General Plan Draft Review input
Items as of August 2004
Page 2
Town of Truckee
B” Priorities for FY 2004/05
“
PriorityStatusFuture Action/Timeline
Gann Limit Budget an election 05/06
Civic Center Presence in Downtown Will address in Millsite/River Front plan
Street Sanding Guidelines (Air Awaiting prioritization for staff resources.
Quality)
Downtown Mello-Roos/PBID On hold pending merchants polling Dependant on outcome of poll
SR 267/Downtown Pedestrian Construction planned for summer of 2005, and or
Crossing concurrent with the Downtown Mello Roos district.
Gateway Entrance Signs, Bypass Working with Chamber of Commerce and Continue collaborative efforts on signage.
Signs, Monument Signs, Tourist Caltrans to identify signage modifications
Signs Town-wide funding.
Strategy for Addressing Issues Faced Spanish translations of the newsletter Published bi-lingual newsletter spring 04
by the Hispanic Community distributed. General Plan outreach to
continue when the draft is released.
Translate Council agendas for positing.
Items as of August 2004
Page 3
Town of Truckee
"C" Priorities
(Deferred for Future Years)
PriorityStatusFuture Action/Timeline
Business License Evaluate potential as a mechanism to verify
Contractors licensing and insurance.
Sphere of Influence/General Plan LAFCO project – pending Lafco action and
Amendment General Plan Update.
Items as of August 2004