HomeMy Public PortalAboutCouncil Priority List - July 2005
Town of Truckee
Priority "A+" for FY 2004/05
PriorityStatusFuture Action/Timeline
Affordable/Workforce programs and
Housing Element Implementation
1. Inclusionary Housing 1. AHWG preparing Draft Ordinance. 1. Ordinance to PC & Council Winter 05.
2. Housing Linkage Program 2. AHWG preparing Draft Ordinance. 2. Ordinance to PC & Council Winter 05.
3. Development Code 3. Staff preparing code amendments. 3. Amendments to PC & Council Winter 05.
4. Housing Element Implementation 4. Town received $3.6 million home grant to
assist Gray’s Crossing. Staff is assisting
Stoneridge to apply for BEGIN grant. Town
other grants applications being considered
by the state.
5. Local Affordable Housing Funding 5. Council approved $10,000 grant to WHATT
Source and Organization for business plan. Staff providing
assistance to WHATT.
6. PC2 Alder Drive Affordable Housing 6. Staffs review of alternatives. AHWG
discussion.
Historic Preservation Program
Implementation
1. National Register District Application. 1. Application submitted Aug 2004. 1. Application to be considered by State Winter
05.
2. Town Grants 2. Grant applications to be accepted Summer 05.
2. Staff preparing guidelines & procedures.
Staff identifying high priority properties for
assistance.
3. Staff preparing handouts on regulations and
3. Outreach and information. 3. Distribution to Downtown property owners
financial assistance.
Spring 06.
Corporation Yard Relocation Site selection complete, base mapping Approve interagency agreement to fund master
complete. Master planning under way. planning. Begin Public review process.
Railyard Redevelopment Grant received. Property purchase completed, Reports to Council next month. Phase 2 to begin.
phase 1 of millsite plan underway
River Revitalization Planning Plan Underway Recommendations to Council 3/31/05.
Required planned communities comply Complete Complete
with general plan update
General Plan Update General Plan update in process. Draft General Plan published 4/05
Town Manager Recruitment Complete Complete
Air Quality Implementation
1. Joint Financial Assistance Program. 1. Scheduled Winter 06.
Items as of April 2005
Page 1
PriorityStatusFuture Action/Timeline
1. Consultants submitted draft study to Town
2. Guidelines for removal of non-certified and Placer County. Staff review and
wood stoves. recommendations to TC & Placer Board. 2. Administrative guidelines to Council Winter 05
2. Staff preparing recommended guidelines.
Medicinal Marijuana Ordinance
General Plan, Development Code and
Zoning changes to conform with the
CLUP
BMP’s for erosion control for single family
construction
Legend
Completed Priorities
New Priorities since 2004 Priority setting
Items as of April 2005
Page 2
Town of Truckee
Priority "A" for FY 2004/05
PriorityStatusFuture Action/Timeline
Pioneer Trail/Bridge Street Extension EIR Consultant Selected Conduct EIR technical work concurrent with General Plan
Update
AB 1600 Facilities Fees & Waiver Complete Complete
Policies
SR 89 Corridor Study and “Mouse On hold pending state funding Monitor state budget.
hole” Provide to the Lobbyist to pursue Council to work with State Legislature.
SR 89 / I-80 Roundabouts Project Funded. Construction Summer 2005
Downtown Parking Solutions Approved, operations plan to implement paid Staff to present proposed job description for new Parking
parking being developed Manager February 06. Fall 05 target for paid parking
initiation.
Development Applications –Hilltop; In progress Provide Council with an expected timeline to process the
Sierra College; applications utilizing current staff levels.
Land Use Application Processing Schedule.
Brockway Road Design Configuration, Proceed with design work on Brockway Rd. Pending staff resources
NC/PC Relationships Regional Issues Nevada County agreement complete. Placer Complete and adopt Placer County Agreement – Spring
County agreement underway for Traffic Summer 2005. Design a collaborative framework.
Impacts
Solid Waste Property Tax Dennis Crabb, Steve and Alex negotiating Negotiations ongoing.
with Nevada County
River Trail Planning – Additional Environmental for phase III underway. Begin Receive Council Direction regarding staffing. Agendize an
Phase & Trail Maintenance Program Phase IV? item to discuss proceeding with phase IV concurrently with
phase III.
Open Space Polling returned positive. Awaiting polling Recommendations to Council spring 2005.
report from Consultant 1/05.
Measure A projects for prioritization Creating a list of potential projects for Council Anticipated to be before Council Spring 2005.
to prioritize.
Trout Creek Restoration Project Environmental document complete. Redesign to incorporate Rail yard Development. Construct
Trout Creek Bridge at Donner Pass Road 2005.
Green Building Committee established. Input on General Brochure to be completed 4/05.
Plan update provided
Donner Pass Rd. Bike Lane Project Preliminary design complete. Need Direction from Council on whether to delay or scale
back project.
Mitigation fee program for single
family homes
Items as of April 2005
Page 3
Town of Truckee
B” Priorities for FY 2004/05
“
PriorityStatusFuture Action/Timeline
Gann Limit Budget an election 06/07 Assumes Town exceeds appropriations limit at the end of
FY 05-06
Civic Center Presence in Downtown Will address in Millsite/River Front plan
Street Sanding Guidelines (Air Awaiting prioritization for staff resources.
Quality)
Downtown Mello-Roos/PBID including Preparation of financing spread under way. Use financing spread as basis for merchants polling.
SR 267/Downtown Pedestrian Construction planned for summer of 2005, and or
Crossing concurrent with the Downtown Mello Roos district.
Gateway Entrance Signs, Bypass Working with Chamber of Commerce and Continue collaborative efforts on signage.
Signs, Monument Signs, Tourist Caltrans to identify signage modifications
Signs Town-wide funding.
Strategy for Addressing Issues Faced Spanish translations of the newsletter Council Direction on budgeting for translation of Council
by the Hispanic Community distributed. General Plan outreach to agendas. Add $ to 2005-06 budget for Spanish Translation
continue when the draft is released. of Council Agendas.
Translate Council agendas for positing.
Lighting Guidelines and Specs per Awaiting Available staff resources.
General Plan
Street sanding guidelines
Items as of April 2005
Page 4
Town of Truckee
"C" Priorities
(Deferred for Future Years)
PriorityStatusFuture Action/Timeline
Business License Evaluate potential as a mechanism to verify
Contractors licensing and insurance.
Sphere of Influence/General Plan LAFCO project – pending Lafco action and
Amendment General Plan Update.
Items as of April 2005