AUTHORIZING A PROFESSIONAL SERVICES CONTRACT FOR
ENGINEERING SERVICES WITH T&M ASSOCIATES -
CARTERET PARK POND RESTORATION PROJECT
WHEREAS, the Borough of Carteret, ("Borough"), is in need of specialized
engineering services with regard to the engineering design, preparation of bid
documents and construction contract documents, processing of the bid submittals,
recommendation of the award of a contract and construction administration with
regard to the Carteret Park Pond Restoration Project; and
WHEREAS, the Borough's Engineers, T&M Associates, possess the requisite
skill and expertise to provide said services; and
WHEREAS, T &M Associates has submitted a proposal to provide said
engineering services at a total cost not to exceed $110,000.00; and
WHEREAS, the Mayor and Council have reviewed said proposal;
WHEREAS, the Chief Financial Officer has certified that funds are or will be
available for said purpose.
NOW, THEREFORE, BE IT RESOLVED by the Mayor and Council of the
Borough ofCarteret, County of Middlesex, State of New Jersey, as foIlows:
1. That the proposal from T &M Associates for professional
engineering services related to the engineering design,
preparation of bid documents and construction contract
documents, processing of the bid submittals,
recommendation of the award of a contract and
construction administration with regard to the Carteret Park
Pond Restoration Project, at a total amount not to exceed
$110,000.00, billable in accordance with T&M Associates'
existing contract with the Borough, is hereby approved;
2. That annexed hereto is a copy of said proposal;
3. That this action is approved as an award of a professional
servIces contract pursuant to NJ.S.A. 40A:II-5(l)(a).
I
,
~
COUNCILMAN YES
BELLINO X
DIAZ
;-
, X
I
Aòopted this 9'" day of February, 2006
and certified as a true copy of the
original on February 10, 2006.
KATHLEEN M. BARNEY, RMC/CMC
Municipal Clerk
RECORD OF COUNCIL VOTE
NO NV A.B. COUNCILMAN YES NO NV A.B.
NAPL
R 0
~
X
x - lr1dicate Vote AB - Absent NV - Not Voting XOR - Indicates Vote to Overrule Yeto
Adopted at a meeting of the Municipal Council
C F.K
¡j
ih1nrnu£4 nf (fu¡rf.erd
MIDDLESEX COUNTY
.N,W ;JJ "..~
OFFICE OF
KATHLEEN M. BARNEY, RMClCMC
MUNICIPAL CLERK
TEL (732) 541-3800
FAX (732) 541-8925
61 COOKE AVENUE
CARTERET, NEW JERSEY 01008
Date February 17. 2006
TO: Patrick J. DeBlasio, Treasurer
Borough of Carteret
REQUEST FOR CERTIFICATION OF A V AILABLE FUNDS:
For:
PROFESSIONAL ENGINEERING SERVICES
~.ARTF.RF.T PARK POND RESTORATION PROJECT
Name of Account: T&H Associates
--
AMOUNT TO BE ENCUMBERED:
Not to exceed $110,OOO.00:at an hourly rate
accord~ng to schedU~~ -:P. , _.I-U
/ílt:d /"1"-.../'97;, /----~
KATHLEEN M. BARNEY,
Municipal Clerk
CERTIflCATIONOFAVAILAB~ITYOFmœms
,
I, Treyl.!f~LQf..tJu,BQ'V'.¡g..t¡.cl'Carte<et,_dc hcr"€:by œrtify·tha~enr1ì:Joon\íàilií&leintlie cUITeni-=~
.. budget to enable the MunicipaJ Council to authorize the entering into a contract between the Borough of Carteret
and:
--1 ; ,;,.. 4-ð"Jx,
The funds available for this.contract are in the Budget, in the account of
V V
C. -<n·-~II·r.I).. ;20). -5)',;)(,/,).;).. Cocl_d.{ ",_).",(. S'."ìJ...,-H
.~
in the amount of /10, "'''"0, ~
,
By this certification. I have hereby encumbered the above named account t1 r the amount of the contract.
~
J, DeBLASIO, Treasurer
Date: ). /, ., I ~I.
KMBI
cp
'\~
.Jk / u '7;L
llV{fr; (fJ;kJ
cl/¿/(, r-r ~ 4i:llD ~ ro
~ '-t-- ~ -'
-
CART-01221
January 27, 2006
Mayor & Borough Council
c/o Ms, Kathleen M. Barney, Borough Clerk
Borough of Carteret
Municipal Building
61 Cooke Avenue
Carteret, NJ 07008
¡
c
Re: Carteret Park Pond Restoration
Contract Administration and Field Inspection Services
Deck and Walkway Design Services
\ tv'-~ \
The Borough is currently eva mg bids for the restoration of Carteret Park Pond, The estimated value
of the project work is $1 ,000, As you are aware, the project is partially funded by an NJDEP Green
Acres Program
Dear Mayor and Council Members:
T &M Associates provided supplemental design phase services, including but not limited to, design of a
new observation deck, perimeter walkway, pond reconfiguration, and lighting plans for the pond
restoration project The scope of services and fee for this work is presented below,
We will also assist the Borough in securing permits and with sediment disposal and fish relocation
activities, We will address NJDEP comments on the Borough's permit submissions and assist the
Borough in its efforts to identify a sediment disposal site within the Borough and in dealings with
Princeton Hydro and identifying a site for fish relocation,
T &M Associates will also provide contract administration and field inspection services for the project
Our Construction Services Division Manager and myself will coordinate project construction inspection
activities, The following is a description of the services we will provide, the anticipated performance
period for these services and the budget for the cost of same,
SCOPE OF SERVICES - CONSTRUCTION PHASE
The construction inspection effort will be accomplished in three phases ~ Pre-Construction, Construction
and Post Construction.
Pre-Construction Phase ~
T &M will request the contractor to prepare and submit its prop se b . line project schedule and detailed
cost breakdown for the lump sum items. Included in the ojec Ischedule will be the contractor's
submittal schedule outlining its plan for submission of shop d w gs, technical data sheets and other
submittal documents,
H:\Cart\QI 221\Com:spondcncc\Mayor & Council_DJN_Propos<Jl Conlrac\ Admin & Field Inspect Svcs.doc
Le:
Mayor & Borough Council
c/o Ms. Kathleen M. Barney, Borough Clerk
Borough of Carteret
CART4Jt22l
January 27, 2006
Page 2
Re: Carteret Park Pond Restoration
Contract Administration and Field Inspection Services
Upon receipt of contract documents and prior to the start of any site activity, we will conduct a pre-
construction meeting. All participants of the project team will be invited to this kick-off meeting _
Borough personnel involved in day-to-day operations that interface with the work; contractor; utility reps,
as required, and our construction team. At this meeting, among other topics, there will be an exchange of
requirements, needs and protocols necessary for the project. A police representative will be invited; and a
procedure for notifying local residents will be determined.
Construction
Our construction team, consists of individuals each with a specific role and responsibility in carrying out
the construction management plan. The Project Manager (PM) has day-to-day responsibility for contract
administration. He and his inspector will monitor performance with the baseline schedule and contracted
costs. The team will perform the required inspection and conduct periodic job meetings, as determined by
the PM necessary to discuss performance to-date, any design and contract issues and upcoming tasks and
plans for their implementation. We will produce and distribute minutes of all meetings.
Our staff will provide part-time construction coverage Monday through Friday. As necessitated by the
contractor's work schedule, on-site inspection will be provided, as required, beyond an eight-hour
workday and Saturdays. We will notify the Borough if we feel full-time inspection is needed. In the
field, our staff will monitor the construction activity including performing and documenting inspections
to determine if the work is done in general conformance with the contract plans and specifications. We
will notify the contractor in writing of any unacceptable work or material, track the deficient condition
and inspect the work until it meets the contract requirements.
We will monitor surrounding property owners and general public concerns that may arise during the
construction phase. We will work closely with the neighboring property owners attempting to minimize
disruption and inconvenience to the residents.
Monthly contractor payment requisitions will be processed by our office with a recommendation for
payment presented to the Borough. Pay items will be checked for accuracy with field measurements
taken during the month.
Post-Construction
During this phase, we will perform a final inspection of the work with involvement from the Borough as
desired, issue a punchlist to the contractor and track and check corrective work until completed.
Particular attention will be given to the restoration of adjacent property.
We will manage the contract closeout process, including execution of any affidavits, release of liens,
production of maintenance bond, warranties/guarantees, operations and maintenance manuals and other
technical data, as required.
¡ :\Carf"O 1221 \Correspondcnce\Mayor & Council_DJN _Proposal Contract Admin & field Inspect Svcs.doc
Le:
Mayor & Borough Council
c/o Ms. Kathleen M. Barney, Borough Clerk
Borough of Cartcret
CART -01221
January' 27, 2006
Page 3
Re: Carteret Park Pond Restoration
Contract Administration and Field Inspection Services
SCOPE OF SERVICES - DESIGN PHASE
We have conducted analyses of various alternative perimeter wall designs for the Carteret Park pond
project. The analyses considered various wall types and materials, including sheet piling to allow raising
the surface water elevation. In addition, alternative concept plans discussed and evaluated enlarging the
pond, pond depth, edge stabilization details, and associated park amenities.
In addition to the above described analyses, as a result of several project concept development meetings,
at your request, we are prepared to perform the following additional design tasks concerning the pond
restoration and dredging:
1. The pond perimeter will be expanded on the northwest side and an island created within the pond as a
result of the widening. Side slope stabilization rip-rap will be designed and installed along the new
pond edge and island. Rip-rap details will be developed. In order to widen the pond, the bocce court
adjacent to the pond will require relocation and a construction detail will be provided for a new bocce
court. The site plan will not include a location or grading plan for the relocated bocce court. The
Borough will determine the location in the field during construction.
2. A new at grade timber deck will be designed along the northeast side of the pond to surround the
existing tree of the general size discussed at our meeting (50' x 70'). A railing will be provided along
the edge of the pond (wooden railing with vertical rails used at Waterfront Park Pier, Phase I) and the
deck will be designed to be ADA accessible. No special features or amenities are included in the
design. A maximum of two alternative decking materials will be included in the contract.
3. The perimeter concrete walkway will receive a stamped and color coated asphalt overlay similar to
Waterfront Park Phase II. This work will include repair of the concrete walkway including
replacement of the bridge section with metal handrails along the southeast portion of the pond.
4. Lighting will be designed for the top of the piers for the proposed decorative wall around the pond.
This will require additional electrical service and distribution design and light fixture selection.
SCHEDULE
The contract performance period for the contractor is set by the contract documents at 200 calendar days
from Notice of A ward. Although the construction schedule outcome is influenced by many factors,
including the contractor's relative ability/management acumen, weather, material availability, and
unanticipated utility/subsurface conflicts, we find the 200 calendar day schedule to be reasonable. This
proposal is based on providing part-time inspection and contract administration services for a period of 6
1/2 months from the Notice of Award with construction.
H:\Cart\01221\Correspondence\Mayor & Council_DJN_Proposal Contract Admin & rield Inspect Svcs,doc
Le:
Mayor & Borough Council
c/o Ms. Kathleen M. Barney. Borough Clerk
Borough of Carteret
CART-OI221
January 27. 2006
Page 4
Re: Carteret Park Pond Restoration
Contract Administration and Field Inspection Senices
FEE
Design Phase - We propose to provide the design work and permit, sediment disposal and fish relocation
assistance, described above for a cost not to exceed $34,400. This fee includes our efforts to date to
perform concept revisions and the alternative analyses.
Construction Phase - Compensation for our services as set forth above is proposed on an hourly basis, to
be invoiced monthly. Fees are based on the rate schedule in our municipal engineering contract. Any
independent testing laboratory costs will be billed directly to the Borough. Based on the scope of work
described above, the assigned performance period (200 calendar days) and the applicable rates, I estimate
a budget cost of $94,500 for our services on this project.
The following is a summary of proposed project fees:
Design Services
Permit Assistance
Sediment Disposal and Fish Relocation
I
$ 26,100.00
$ 2,800.00
$ 5,500.00
----
i/i
o
o
Design Phase
Construction Phase
Construction Services
Base Bid
Alternate A-I
Alternate A-2
vf~
l?
'(;- ~p /;\)
'7;< f)
0)
"
00.00 /
Very truly yours,
TOTAL
If you have any questions or require additional information, please advise.
T &M ASSOCIATES
DONALD J. NORBUT, P.E., C.M.E.
CARTERET BOROUGH ENGINEER
DJNlhan
c: Patrick DeBlasio, Chief Financial Officer
Robert Bergen, Borough Attorney
1I:\Cart\OI 221\Correspondence\Mayor & Council_D.JN_Proposal Contract Admin & Field Inspect Svcs,doc
ELEVEN TINDAll ROAD MIDDLETOWN. N,j 07748-2792
(132) 671-6400 * ~ax í7:-J2) 671-73GS'- vV\,vvV tandmassociates com
-&M
ASSOCIATES
CART-01221
~
January 27, 2006
Mayor & Borough Council
c/o Ms. Kathleen M. Barney, Borough Clerk
Borough of Carteret
Municipal Building
61 Cooke Avenue
Carteret, NJ 07008
Re: Carteret Park Pond Restoration
Contract Administration and Field Inspection Services
Deek and Walkway Design Services
Dear Mayor and Council Members:
The Borough is currently evaluating bids for the restoration of Carteret Park Pond. The estimated value
of the project work is $1,500,000. As you are aware, the project is partially funded by an NJDEP Green
Acres Program.
T &M Associates provided supplemental design phase services, including but not limited to, design of a
new observation deck, perimeter walkway, pond reconfiguration, and lighting plans for the pond
restoration project. The scope of services and fee for this work is presented below.
We will also assist the Borough in securing permits and with sediment disposal and fish relocation
activities. We will address NJDEP comments on the Borough's permit submissions and assist the
Borough in its efforts to identifY a sediment disposal site within the Borough and in dealings with
Princeton Hydro and identifying a site for fish relocation.
T &M Associates will also provide contract administration and field inspection services for the project.
Our Construction Services Division Manager and myself will coordinate project construction inspection
activities. The following is a description of the services we will provide, the anticipated performance
periDd for these services and the budget for the cost of same.
SCOPE OF SERVICES - CONSTRUCTION PHASE
The construction inspection effort will be accomplished in three phases - Pre-Construction, Construction
and Post Construction.
I~ ~·-;t)6
Pre-Construction Phase (!~~ ~
T&M will request the contractor to prepare and submit its proposed baseline project schedule and detailetJi7)t2 <f(!,/
cost breakdown for the lump sum items. Included in the project schedule will be the contractor's
submittal schedule outlining its plan for submission of shop drawings, technical data sheets and other =-b
submittal documents. /~
H:\Cart\O 1221 \Corrcspondence\Mayor & Council__ OJN _Proposal Contract Admin & Field Inspect Svcs.doc ~ \ /" J t: ~ C t
ENGINEERS * PLANNERS * lANDSCAPE ARCHITECTS * ENVIRONMENTAL SCIENTISTS' SURVEYORS
CI\i¡1 ' E~~C: I Pi':Jd' E~J'./iR(JI\j\,1Lr"Ht"" 'k"1ECH!\~~ICþ'1 ' MJf\!iClP/Ii_" SITE" SOLID "/v'i\STE:: ' S Ir1UCTUP.i:\i._ TRi\FF:C" TH.~I\J~;I'Uí- 'ÄTiCi'.]
REGIO",AL OFf-ICtS IN TOMS RIVeR. MOOREST(J\^i.'J CLi\RK and SAèl jUAr~ PUERi 0 RiCO
Lc:
Mayor & Borough Council
c/o I\Is. Kathleen M. Barney, Borough Clerk
Borough of Carteret
~M
ASSr:lCIATFS
CAH.T-OI221
.January 27, 2006
Page 2
Re: Carteret Park Pond Restoration
Contract Administration and Field Inspection Services
Upon receipt of contract documents and prior to the start of any site activity, we will conduct a pre-
construction meeting. All participants of the project team will be invited to this kick-ofT meeting -
Borough personnel involved in day-to-day operations that interface with the work; contractor; utility reps,
as required, and our construction team. At this meeting, among other topics, there will be an exchange of
requirements, needs and protocols necessary for the project. A police representative will be invited; and a
procedure for notifying local residents will be determined.
Construction
Our construction team, consists of individuals each with a specific role anci responsibility in carryiog out
the construction management plan. The Project Manager (PM) has day-to-day responsibility for contract
administration. He and his inspector will monitor performance with the baseline schedule and contracted
costs. The team will perform the required inspection and conduct periodic job meetings, as determined by
the PM necessary to discuss performance to-date, any design and contract issues and upcoming tasks and
plans for their implementation. We will produce and distribute minutes of all meetings.
Our staff will provide part-time construction coverage Monday through Friday. As necessitated by the
contractor's work schedule, on-site inspection will be provided, as required, beyond an eight-hour
workday and Saturdays. We will notify the Borough if we feel full-time inspection is needed. In the
field, our staff will monitor the construction activity including performing and documenting inspections
to determine if the work is done in general conformance with the contract plans and specifications. We
will notif'y the contractor in writing of any unacceptable work or material, track the deficient condition
and inspect the work until it meets the contract requirements.
We will monitor surrounding property owners and general public concerns that may arise during the
construction phase. We will work closely with the neighboring property owners attempting to minimize
disruption and inconvenience to the residents.
Monthly contractor payment requisitions will be processed by our office with a recommendation for
payment presented to the Borough. Pay items will be checked for accuracy with field measurements
taken during the month.
Post-Construction
During this phase, we will perform a final inspection of the work with involvement from the Borough as
desired, issue a punchlist to the contractor and track and check corrective work until completed.
Particular attention will be given to the restoration of adjacent property.
We will manage the contract closeout process, including execution of any affidavits, release of liens,
production of maintenance bond, warranties/guarantees, operations and maintenance manuals and other
technical data, as required.
11:\Cart\01221\Corrcspondence\Mayor & Council_DJN_Proposal Contract Admin & Field Inspect Svcs.doc
~M
ASSOCIATES
Le:
\layor & Borough Council
c/o Ms. Kathleen M. Barney, Borough Clerk
Borough of Carteret
CART-Ot221
.January 27, 2006
l'agc3
Rc: Carterct Park Pond Restoration
Contract Administration and Field Inspection Services
SCOPE OF SERVICES DESIGN PHASE
We have conducted analyses of various alternative perimeter wall designs for the Carteret Park pond
project. The analyses considered various wall types and materials, including sheet piling to allow raising
the surface water elevation. In addition, alternative concept plans discussed and evaluated enlarging the
pond, pond depth, edge stabilization details, and associated park amenities.
In addition to the above described analyses, as a result of several project concept development meetings,
at your request, we are prepared to perform the following additional design tasks concerning the pond
restoration and dredging:
I. The pond perimeter will be expanded on the northwest side and an island created within the pond as a
result of the widening. Side slope stabilization rip-rap will be designed and installed along the new
pond edge and island. Rip-rap details will be developed. In order to widen the pond, the bocce court
adjacent to the pond will require relocation and a construction detail will be provided for a new bocce
court. The site plan will not include a location or grading plan for the relocated bocce court. The
Borough will determine the location in the field during construction.
2. A new at grade timber deck will be designed along the northeast side of the pond to surround the
existing tree of the general size discussed at our meeting (50' x 70'). A railing will be provided along
the edge of the pond (wooden railing with vertical rails used at Waterfront Park Pier, Phase I) and the
deck will be designed to be ADA accessible. No special features or amenities are included in the
design. A maximum of two alternative decking materials will be included in the contract.
3. The perimeter concrete walkway will receive a stamped and color coated asphalt overlay similar to
Waterfront Park Phase II. This work will include repair of the concrete walkway including
replacement of the bridge section with metal handrails along the southeast portion ofthe pond.
4. Lighting will be designed for the top of the piers for the proposed decorative wall around the pond.
This will require additional electrical service and distribution design and light fixture selection.
SCHEDULE
The contract performance period for the contractor is set by the contract documents at 200 calendar days
from Notice of A ward. Although the construction schedule outcome is intluenced by many factors,
including the contractor's relative ability/management acumen, weather, material availability, and
unanticipated utility/subsurface contlicts, we find the 200 calendar day schedule to be reasonable. This
proposal is based on providing part-time inspection and contract administration services for a period of 6
1/2 months from the Notice of A ward with construction.
H:\Cart\01221\Correspondence\Mayor & Council_DJN_Proposal Contract Admin & rield Inspect Svcs,doe
-nM
A!"iSOCIATES
CART-Ot221
January 27, 2006
Page 4
Le:
Mayor & Borough Council
c/o Ms. Kathleen M. Barney, Borough Clerk
Borough of Carteret
Rc: Carteret Park Pond Restoration
Contract Administration and Field Inspection Services
FEE
Design Phase - We propose to provide the design work and permit, sediment disposal and fish relocation
assistance, described above for a cost not to exceed $34,400. This fee includes our efforts to date to
perform concept revisions and the alternative analyses.
Construction Phase - Compensation for our services as set forth above is proposed on an hourly basis, to
be invoiced monthly. Fees are based on the rate schedule in our municipal engineering contract. Any
independent testing laboratory costs will be billed directly to the Borough. Based on the scope of work
described above, the assigned performance period (200 calendar days) and the applicable rates, ¡estimate
a budget cost of $94,500 for our services on this project.
Thc following is a summary of proposed project fees:
Design Phasc
Design Services
Permit Assistance
Sediment Disposal and Fish Relocation
$ 26,100.00
$ 2,800.00
$ 5,500.00
Construction Phase
Construction Services
Base Bid
Alternate A-I
Alternate A-2
$ 67,100.00
$ 12,500.00
$ 14.900.00
TOTAL
$128,900.00
If you have any questions or require additional information, please advise.
Very truly Y0urs"
I' &M AS
DONALD J. NORBUT, P.E., C.M.E.
CARTERET BOROUGH ENGINEER
DJN/han
c: Patrick DeBlasio, Chief Financial Officer
Robert Bergen, Borough Attorney
H:\Cart\O 122 l\Correspondence\Mayor & Council_DJN_Proposal Contract Admin & Field Inspect Svcs.doc