HomeMy Public PortalAbout2005.05.04 Ltr Lakeport ManagementLAKEPORT MANAGEMENT
P.O. Box 927 • McCall, ID 83638
Telephone: (208) 634-2900
Fax: (208) 634-2952
May 4, 2005
City of McCall
City Manager: Lindley Kirkpatrick &
Council Members
216 E. Park Street
McCall, ID 83638
Re: Mile High Marina Construction schedule of docks
Dear Mr. Kirkpatrick & Council Members,
The management at Mile High marina is committed to replacing the entire dock system
with an estimated total replacement value at $400,000.00.
Currendy, we are under contract with Inland Marine Construction Inc. to replace the first
phase of three (3) stages by May 31, 2005.
Phase Two (2), is anticipated to be completed at the end of the 2005 season and the third
phase is scheduled for completion by Memorial Day weekend 2006.
Please refer to the attached schedule for more details.
Regards,
James G. erblick
slj
SCHEDULE A
Mile High Marina, LLC
Dock construction time -line
May 4, 2005
Phase One (1):
Estimated Date of Completion:
Phase Two (2):
Estimated Date of Completion:
Phase Three (3):
Estimated Date of Completion:
May 31, 2005
October 31, 2005
May 31, 2006