RESOLUTION NO. 2017-01-03
A RESOLUTION APPROVING A PARTIAL REDUCTION IN THE SURETY PURSUANT TO
THE SUBDIVISION IMPROVEMENT AGREEMENT (SIA) FOR THE WILLOWS AT GRAND
PARK FILING NO. 2 AND FILING NO.3.
WHEREAS, Grand Park and the Town of Fraser entered into a SIA, Reception #
2016006985, to ensure completion of certain infrastructure and which SIA provides for
reductions in surety requirements, and
WHEREAS, Grand Park has requested a reduction in surety because these
improvements are substantially complete and the Town Staff and Engineer have reviewed the
request and have determined it to be in conformance with the provisions of said agreement.
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE TOWN OF
FRASER, COLORADO THAT:
1. The Town Board of Fraser, Colorado hereby authorizes a reduction in the surety required
under the terms of the SIA from $512,114.00 to $332,818.00, releasing $179,296.00 to
Grand Park Development LLC.
READ, PASSED ON ROLL CALL VOTE, AND ADOPTED BY THE BOARD OF TRUSTEES
THIS 18th DAY OF JANUARY, 2017.
Votes in favor:
Votes opposed:
Absent:
Abstained:
BOARD TRUSTEES OF THE
TOWN OF FRASER, COLORADO
BY:
Mayor
ATTEST:
S E A L)
Town Clerk
MEMORANDUM
JRS ENGINEERING CONSULTANT, LLC
TO: Catherine Trotter, Fraser Town Planner
CC: Allen Nordin, Fraser Director of Public Works
FROM: James R. "Jim"Swanson, P.E.
DATE: January 4, 2017
SUBJECT: Willows at Grand Park Filing 2& 3 Surety Release Request#1
This memorandum summarizes my review of the Grand Park letter request for partial release of the
irrevocable Letter of Credit, held by Fraser for the Willows @ Grand Park Filing No's 2 & 3, dated
December 29, 2016. Grand Park is requesting a partial release of the US Bank letter of credit surety
related to the Willows at Grand Park Filing 2 & 3 Improvements from the initial Performance Guarantee
amount of$512,114.00 to an amount equal to $323,749.00, a release of$188,365.00.
Review of this request is performed in accordance with the terms and conditions included in the
Subdivision Improvements Agreement(SIA) between Fraser and Grand Park for the above referenced
project; Reception#2016006985. Specifically:
SIA Paragraph 11.1 Requests for Partial Release of Performance Guarantee: states "No reduction
of the Performance Guarantee shall be allowed which would reduce the amount of collateral to less
than one-hundred twenty-five percent(125%) of the estimated cost of any remaining or incomplete
improvements; and the final twenty percent(20%) of the initial Performance Guarantee may not be
released until all of the improvements have been preliminarily accepted, the one-year warranty
period has run, the Sub-divider has complied with all requirements specified in Section 7 hereof
and the Improvements are finally accepted by the Town."
Based on my review of Exhibit A—Engineer's Estimate for Public Improvements attached to Grand Park's
December 29, 2016 letter, the cost estimate line item status of construction completion was identified by
Grand Park. I concur that$230,395 of the improvements remain to be constructed, based on my
understanding of the current project status, from the periodic site observation reports received from
Bowman Consulting.
I am not in concurrence with Grand Park's calculation and request to Fraser for the release of$188,365.00
and retainage equal to $323,749.00.
My calculations, based on SIA Paragraph 11.1 are:
1. Retainage for"Work to be Completed" = 1.25 x$230,395 = $287,994.
2. Retainage for"Final 20%of Initial Performance Guarantee" = 0.20 x ($512,114 -$287,994) =
44,824.
The total retainage from this calculation is $332,818. This would reduce the letter of credit for the above
referenced project by $179,296.
It is my recommendation that Fraser approve reduction of Grand Park's letter of credit for the above
referenced project to $332,818.
6013 E. Briarwood Drive-Centennial, CO 80112 303) 726-5577
1 GRAND1ARK IF
foi-el -e-voJ ode
December 29,2016
Sent Via E-mail
Town of Fraser
Attn: Catherine Trotter
P.O. Box 120
Fraser, CO 80442
Re: Willows at Grand Park Filing No.2 &3-Improvements Surety Release
Request Number 1
Dear Catherine,
Please accept this letter as a request to the Town of Fraser("Town") for a partial release
of the US Bank letter of credit surety held relating to the Willows at Grand Park Filing
No. 2 &No. 3 (SIA Reception#2016006985 recorded 9/21/16) Improvements
completed to date as noted on the attached Exhibit A less the 20%warranty surety for the
completed items.
The SIA surety amount for this project currently held by the Town is $512,114 including
warranty and completion surety. This is the first surety release request for this project.
Upon release of the$188,365 associated with the completed work, the Town will have a
surety balance of$323,749 representing the uncompleted work with a 25%completion
surety and the 20% warranty surety for the completed work all as shown on the attached
Exhibit A.
Thank you for your consideration of this request.
7/7
Since,„--
C < 0 scomb,7
President
Cc: Jeff Durbin
klAIN 111.1.1(1. )Ill r'i rlf11111 l-AK 07I' '•:"1 IirtA.1
RI i I•} :`r`
lr• LII.4.1C1- cf7t1 1;;6471:4'' { IINC'I" 'CIt IIIA; Cil I II I '17Il ";''t '1(11
CM 0"1 c 11(1X 'ill WIN I '. I':1RK i•0'III{ 'InIfl ull-1-
EXHIBIT A
ENGINEERING, ..,
PH E LPS
Engineer's Cost Estimate for Public Improvements
Willows at Grand Park
14079
May 21,2015
Filing 2 Item Description Unit Unit Cost Est.Qty STATUS
Roadways Phase 2 Phase 2
Asphalt Pavement SY '-$ 24.00 2,290 $ 54,960.00
Mountable Curb and Gutter LF $ 16.00 1,634 $ 26,144.00
Crosspan SF $ 11.00 796 $ 8,756.00
Sidewalk SF $ 4.00 3,308 $ 13232.00
Sims(Stop Sign,Speed Limit,No Parking,Warning Sign) EA $ 96.00 ; 5 $ 480.00 '
Thermo-plastic Pavement Marking i Xwalk&Stop line) SF $ 2.50 50 $ 125.00
Street Lights EA $ 500.00 1 $ 500.00
Storm Sewer
2'Type'M'Soil Ricrac TON $ 88.12 10 $ 898.82 COMPLETE
Narrowleaf Ct.Channel LF $ 3.00 494 $ 1,482.00
Concrete Aprons SF $ 4.00 87 $ 348.00
Sanitary Sewer
8"PVC LF $ 31.20 322 $ 10,046.40 COMPLETE
Manholes EA $3,000.00 5 $ 15,000.00'COMPLETE
4"PVC Service Taos EA $ 800.00 12 $ 9,600.00 COMPLETE
4"PVC Services LF $ 25.00 778 $ 19,450.00 COMPLETE
Connect to Existing.. EA $ 750.00 2 $ 1,500.00 COMPLETE
Water
8"C900 LF $ 45.00 250 J $ 11,250.00 COMPLETE
Fittings EA $ 400.00 4 $ 1,600.00 COMPLETE
8"Gate Valves EA $2,000.00 1 $ 2,000.00 COMPLETE
Fire Hydrant Assembly's EA $4,800.00 1 $ 4,800.00 COMPLETE
3/4"Water Service Taps EA $ 800.00 12 $ 9,600.00 COMPLETE
3/4"Water Services LF ' $ 21.00 426 $ 8,946.00 'COMPLETE
Connect to Existing EA $ 750.00 1 $ 750.00 COMPLETE
Demolition
8"Sanitary Sewer LF $ 24.00 240 $ 5,760.00 COMPLETE
Sewer Manholes EA $ 520.00 2 $ 1,040.00 COMPLETE
Plugging 4"Sanitary Sewer Service Taps EA $ 200.00 9 $ 1,800.00 COMPLETE
4"Sanitary Sewer Services LF $ 12.00 230 $ 2,760.00 COMPLETE
8"DIP Water LF $ 14.00 167 $ 2,338.00 COMPLETE
Water Fittin.us EA $ 152.00 2 $ 304.00 COMPLETE
18"Gate Valves EA $ 152.00 1 $ 152.00 COMPLETE
Fire Hydrant Assembly's with 6"DIP and 6"Gate Valves EA $ 560.00 1 $ 560.00 COMPLETE
Plugging 3/4"Water Service Taps EA $ 150.00 9 $ 1,350.00 COMPLETE
3/4"Water Services LF $ 8.00 187 $ 1,496.00 COMPLETE
Cozen's Ditch(Private)
48"RCP LF $ 150.00
Cozens Ditch LF ' $ 3.00
Culvert Headwall LF $ 80.00
2'Type'M'Soil R crap TON $ 88.12
Water Feature Pond#1 SF $ 0.33
Water Feature Pond#2 SF $ 0.33
I I I
Roadway Grading
Erosion Control LF $ 4.00 I COMPLETE
Revegetation
mm
SF $ 0.09 3,200.0 $ 288.00
Cut/Fill CY $ 1.96 2,620.1 I $ 5,135.40 COMPLETE
Net(Fifa) CY S 1.96 1,245.2 5 2,440.59 COMPLETE
Filing 3 Item Description Unit Unit Cost STATUS
Roadways Phase 3 Phase 3
Asphalt Pavement SY $ 24.00 1,854 $ 44,496.00
Mountable Curb and Gutter LF $ 16.00 1,295 $ 20,720.00
Crosspan SF $ 11.00 540 $ 5,940.00
Sidewalk SF $ 4.00 2,820 $ 11,280.00
Signs Stop Sign,Speed Limit,No Parking,Warning Sign'
r
EA $ 96.00 3 $ 288.00
Street Lights EA $ 500.00 1 $ 500.00
Storm Sewer
2'Type'M'Soil Riprap TON $ 88.12 9 1 $ 768.64 COMPLETE
I
Sanitary Sewer
8"PVC LF ' $ 31.20 270 $ 8,424.00
Manholes EA $3,000.00 3 ' $ 9,000.00
4"PVC Service Taps EA $ 800.00 13 $ 10,400.00
4"PVC Services LF I $ 25.00 474 I $ 11,850.00
Connect to Existing EA $ 750.00 1 $ 750.00
Water
8"C900 LF $ 45.00 251 $ 11,295.00 COMPLETE
Fittings EA $ 400.00 4 $ 1,600.00 COMPLETE
8"Gate Valves EA $2,000.00 2 $ 4,000.00 COMPLETE
Fire Hydrant Assembly's EA $4,800.00 2 $ 9,600.00 COMPLETE
314"Water Service Taps EA $ 800.00 11 $ 8,800.00 COMPLETE
3/4"Water Services LF I $ 21.00 460 $ 9,660.00 COMPLETE
Connect to Existing EA $ 750.00 1 $ 750.00 COMPLETE
Demolition
8"Sanitary Sewer LF $ 24.00 52 $ 1,248.00 COMPLETE
Plugging 4"Sanitary Sewer Service Taps
W
EA $ 200.00 2 $ 400.00 COMPLETE
4"Sanitary Sewer Services LF $ 12.00 51 $ 612.00 COMPLETE
8"DIP Water LF $ 14.00 1 30 $ 420.00 COMPLETE
Water Fittings EA $ 152.00 3
4 $
456.00 COMPLETE
8"Gate Valves EA $ 152.00 1 $ 152.00 COMPLETE
Fire Hydrant Assembly's with 6"DIP and 6"Gate Valves EA $ 560.00 1 $ 560.00 COMPLETE
Cozen's Ditch(Private)
48"RCP LF $ 150.00
Cozens Ditch LF 1 $ 3.00
Culvert Headwall LF 1 $ 80.00
2'Type'M'Soil Riprap TON f $ 88.12
Water Feature Pond#1 SF I $ 0.33
Water Feature Pond#2 SF $ 0.33
Roadway Grading
Erosion Control LF I $ 4.00 COMPLETE
Revegetation SF I $ 0.09 4,800.0 $ 432.00
Cut/Fill CY I $ 1.96 5.6 $ 10.94 COMPLETE
Net Fill) CY 7 $ 1.96 4,013.5 $ 7,866.40 COMPLETE
Total Uncompleted Work Cost Before Contingency 230,395
Town of Fraser 25%SIA Contingency 57,599
Surety Held for Work to be Completed 287,994 `1
Completed Work 178,774 COMPLETE
20%Warranty Surety 35,755 *2
Total US Bank LOC Filing 2&3 512,114
Remaining LOC Surety Balance for Warranty and work to be completed 323,749 *1+*2
i US Bank LOC Surety Partial Release for Completed Work 188,365