HomeMy Public PortalAbout4e Resolution 2017-01-05 Approving partial reduction in surety Elk Creek 2TOWN OF FRASER
RESOLUTION NO. 2017-01-05
A RESOLUTION APPROVING A PARTIAL REDUCTION IN THE SURETY PURSUANT TO
THE SUBDIVISION IMPROVEMENT AGREEMENT (SIA) FOR ELK CREEK AT GRAND PARK
FILING NO. 2.
WHEREAS, Grand Park and the Town of Fraser entered into a SIA, Reception #
2016003566, to ensure completion of certain infrastructure and which SIA provides for
reductions in surety requirements, and
WHEREAS, Grand Park has requested a partial reduction in surety (irrevocable letter of
credit SLCPPDX06878) because these improvements are substantially complete and the Town
Staff and Engineer have reviewed the request and have determined it to be in conformance with
the provisions of said agreement.
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF TRUSTEES OF THE TOWN OF
FRASER, COLORADO THAT:
1. The Town Board of Fraser, Colorado hereby authorizes a reduction in the surety required
under the terms of the SIA from $157,886.00 to $72,948.00, releasing $84,938.00 to
Grand Park Development LLC.
READ, PASSED AND ADOPTED BY THE BOARD OF TRUSTEES THIS 18th DAY OF
JANUARY, 2017.
BOARD TRUSTEES OF THE
TOWN OF FRASER, COLORADO
BY:
Mayor
ATTEST:
S E A L)
Town Clerk
MEMORANDUM
JRS ENGINEERING CONSULTANT, LLC
TO: Catherine Trotter, Fraser Town Planner
CC: Allen Nordin, Fraser Director of Public Works
FROM: James R. "Jim"Swanson, P.E.
DATE: January 10, 2017
SUBJECT: GP Elk Creek Filing 2 Surety Release Request#1
This memorandum summarizes my review of the Grand Park letter request for partial release of the
irrevocable Letter of Credit, held by Fraser for the Grand Park Elk Creek Filing No. 2, dated December 29,
2016. Grand Park is requesting a partial release of the US Bank letter of credit surety related to the Elk
Creek at Grand Park Filing No. 2 Improvements from the initial Performance Guarantee amount of
157,886.00 to an amount equal to$72,948.00.
Review of this request is performed in accordance with the terms and conditions included in the
Subdivision Improvements Agreement(SIA) between Fraser and Grand Park for the above referenced
project; Reception#2016003566.
Based on my review of Grand Park's request, no exception is taken to their requested reduction of the
performance guarantee surety for this project. This recommendation is based on my understanding of the
current project status, of the constructed improvements, from the periodic site observation reports received
from Bowman Consulting.
6013 E. Briarwood Drive-Centennial, CO 80112 303) 726-5577
trp A pr./ ;RANI5VARK
Aide, (1)10 fle
December 29,2016
Sent Via E-mail
Town of Fraser
Attn: Catherine Trotter
P.O. Box 120
Fraser, CO 80442
Re: Elk Creek at Grand Park Filing No. 2 -Improvements Surety Release Request
Number 1
Dear Catherine,
Please accept this letter as a request to the Town of Fraser("Town")for a partial release
of the US Bank letter of credit surety held relating to the Elk Creek at Grand Park Filing
No.2 (SIA Reception#2016003566 recorded 5/24/16) Improvements completed to date
as noted on the attached Exhibit A less the 20%warranty surety for the completed items.
In addition we are requesting the Town release the cash grading permit surety in the
amount of$9,206.25 associated with the grading permit that was pulled prior to entering
into the Subdivision Improvement Agreements for the project.
The SIA surety amount for this project currently held by Fraser is$157,886 including
warranty and completion surety. This is the first surety release request for this project.
Upon release, the Town will have a surety balance of$72,948 representing the
uncompleted work with a 25%completion surety and the 20% warranty surety for the
completed work all as shown on the attached Exhibit A.
Thank you for your consideration of this request.
Sincereiv
Clark. scomb,
President
Cc: Jeff Durbin
mA IN 771\ 861111 FAX 9711 771. HA3:1
h` hIF OFF-ICE ',i7(I 77A u701 I ori ;'i{L1f IIIIN4)11.II 1: •171' 77r, x1(1'1
1t55"I (*' ( it NM 111 1%I' I•) 1'.SKk t't?l1Ik.'iIIII HJi }.'
EXHIBIT A
Engineer's Cost Estimate for Public Improvements
Project 15117- Elk Creek PHASE 2
Date-9/28/2015
CONSTRUCTION COSTS Quantities/Pricing Cost
Roadways Qty Unit Price cost
1 Asphalt Pavement 1,712.00 Sy $ 27.00 $ 46,224.00 Complete2MountableCurbandGutter1,452.00 LF $ 18.00 $ 26,136.00 Complete3Crosspan507.00 SF $ 12.00 $ 6,084.00
4 Sidewalk 2,761.00 SF $4.00 $ 11,044.00
5 Signs(Stop Sign,Speed Limit,No Parking,Warning Sign) 4.00 EA $ 120.00 $480.00
6 Street Lights 1.00 EA $ 500.00 $500.00
Total
90,468.00
Sanitary Sewer Qty Unit Price Cost
1 8"PVC 694.00 LF $ 35.00 $ 24,290.00 Complete2Manholes13.00 EA $ 3,000.00 $ 39,000.00 Complete34"PVC Service Taps 13.00 EA $ 800.00 $ 10,400.00 Complete
4 4"PVC Services 370.00 IF $ 25.00 $ 9,250.00 Complete
Total
82,940.00
Water Qty Unit Price Cost
1 8"Water(PVC) 228 IF $ 40.00 $ 9,120.00 Complete
2 12"Water(PVC) 503 IF $ 55.00 $ 27,665.00 Complete
3 Fittings 13 EA $ 400.00 $ 5,200.00 Complete
4 8"Gate Valves 2 EA $ 2,000.00 $ 4,000.00 Complete
5 12"Gate Valve 3 EA $ 2,700.00 $ 8,100.00 Complete
6 Fire Hydrant Assembly's 2 EA $ 5,000.00 $ 10,000.00 Complete
7 3/4"Water Service Taps 12 EA $ 800.00 $ 9,600.00 Complete
8 3/4"Water Services 593 LF $ 21.00 $ 12,453.00 Complete
Total
86,138.00
Erosion Control Qty Unit Price Cost
1 Erosion Control log 1,636.00 LF $3.75 S 6,135.00 Complete2RevegetationEA $ 4,200.00 $
Total
6,135.00
Roadway Grading Qty Unit Price I ( cost
2 Net(Fill) 1,996.00 CY $2.00 $ 3,992.00 Complete
Total
3,992.00
Total Uncompleted Work Cost Before Contingency 18,108
Town of Fraser 25%51A Contingency 4,527
Surety Held for Work to be Completed 22,635 •1
Completed Work
251,565 Complete
W:\Planning Area SW-Elk Creek\02 Elk Creek Sub Docs Filing 2 2016\Acceptance Folder\Elk Creek Surety Release Cost Est.12-
28-16 Page 1of 1
EXHIBIT A
Engineer's Cost Estimate for Public Improvements
Project 15117-Elk Creek PHASE 2
Date-9/28/2015
CONSTRUCTION COSTS Quantities/Pricing Cost
Roadways Qty Unit Price Cost
1 Asphalt Pavement 1,712.00 SY $ 27.00 $ 46,224.00 Complete
2 Mountable Curb and Gutter 1,452.00 LF $ 18.00 $ 26,136.00 Complete
3 Crosspan 507.00 SF $ 12.00 $ 6,084.00
4 Sidewalk 2,761.00 SF $ 4.00 $ 11,044.00
5 Signs(Stop Sign,Speed Limit,No Parking,Warning Sign) 4.00 EA $ 120.00 $480.00
6 Street Lights 1.00 EA $ 500.00 $500.00
Total 90,468.00
Sanitary Sewer Qty Unit Price Cost
1 8"PVC 694.00 IF $ 35.00 $ 24,290.00 Complete
2 Manholes 13.00 EA $ 3,000.00 $ 39,000.00 Complete
3 4"PVC Service Taps 13.00 EA $ 800.00 $ 10,400.00 Complete
4 4"PVC Services 370.00 LF $ 25.00 $ 9,250.00 Complete
Total 82,940.00
Water Qty Unit Price Cost
1 8"Water(PVC) 228 IF $ 40.00 $ 9,120.00 Complete
2 12"Water(PVC) 503 LF $ 55.00 $ 27,665.00 Complete
3 Fittings 13 EA $ 400.00 $ 5,200.00 Complete
4 8"Gate Valves 2 EA $ 2,000.00 $ 4,000.00 Complete
5 12"Gate Valve 3 EA $ 2,700.00 $ 8,100.00 Complete
6 Fire Hydrant Assembly's 2 EA $ 5,000.00 $ 10,000.00 Complete
7 3/4"Water Service Taps 12 EA $ 800.00 S 9,600.00 Complete
8 3/4"Water Services 593 LF $ 21.00 $ 12,453.00 Complete
Total 86,138.00
Erosion Control Qty Unit Price Cost
1 Erosion Control Log 1,636.00 LF $3.75 $ 6,135.00 Complete
2 Revegetation EA $ 4,200.00 $
Total 6,135.00
Roadway Grading Qty Unit Price I I Cost I
2 Net(Flit) 1,996.00 CY $2.00 5 3,992.00 Complete
Total 3,992.00
Total Uncompleted Work Cost Before Contingency S 18,108
Town of Fraser 25%SIA Contingency 4,527
Surety Held for Work to be Completed 22,635
Completed Work 251,565 Complete
W:\Planning Area 5W-Elk Creek\02 Elk Creek Sub Docs Filing 2 2016\Acceptance Folder\Elk Creek Surety Release Cost Est.12-
28-16 Page lof 1