RESOLUTION NO. 17 -2014
A RESOLUTION AUTHORIZING THE EXPENDITURE OF FUNDS
( "IMPROVEMENTS TO PUBLIC INFRASTRUCTURE WITHIN THE REDEVELOPMENT
AREA FOR THE CREATION OF A TRANSITIONAL CARE FACILITY ALONG
INDUSTRIES ROAD ")
WHEREAS, the City of Richmond Redevelopment Commission (hereinafter "Commission ") has
previously adopted a Declaratory Resolution, which has been amended, thereby
establishing a Redevelopment Plan by which certain projects may be funded with
excess Tax Increment Financing ("TIF ") revenue; and
WHEREAS, pursuant to I.C. 36- 7- 14 -39, such excess revenues may be used for the purposes
described therein; and
WHEREAS, pursuant to the above actions, the amended project list includes construction of new
and /or improvements to the City's infrastructure; and
WHEREAS, it has become necessary to make certain infrastructure improvements in the TIF
district as referenced in Attachment A to facilitate a transitional care facility along
Industries Road.
NOW, THEREFORE, BE IT RESOLVED by the Richmond Redevelopment Commission,
that such Commission hereby approves and agrees to reimburse the City of Richmond and /or pay for
necessary expenditures incurred in performing certain infrastructure improvements to facilitate a
transitional care facility along Industries Road. Such funding shall be paid from excess TIF revenues
received during the year 2014 and placed into the allocation fund, all of which is allowed pursuant to
the TIF Redevelopment Plan of 1989, as amended. previously adopted by the Commission.
BE IT FURTHER RESOLVED that the above reimbursement and /or expenditures shall not exceed
the lesser of $246,000 or the allowable excess amount following the retention of all necessary funds
for the reserve regarding the 2014 payments for Bond principal and interest payments.
THIS RESOLUTION IS ADOPTED this lb day 2014
RICHMOND REDEVELOPMENT COMMISSION
By
By
By
By:
By:
Resolution 17 -2014
Attachment A
See attached Redevelopment Commission Applications for Redevelopment Commission
Funding
Resolution 17 -2014
UT
�1 ,t
Dt P
City of Richmond
Redevelopment Commission
APPLICATION FOR REDEVELOPMENT COMMISSION
(TIF or CTP) FUNDING
Applicant Information
Date:
Name:
10/21/2014
Chris Alexander
/7 -Zay
Name of Organization: MS Richmond, LLC
Address: 14390 Clay Terrace Blvd., Suite 205 - Carmel, IN 46032
Email Address: calexander@maininvest.com
Phone: 317-582-6925
Is this a non - profit organization:
Project Information
Fax: 317- 420 -0206
YES x NO
Project Location: 400 Industries Road - Richmond, IN
Amount of Request: $ 246,000
Loan or Grant:
Duration of Funding:
One -Time
Multi- Period
Source of Funding requested:
?, TIF
CTP
Other (Explain):
Grant
Duration:
Page 1 of 4
Other sources of financing secured by the applicant (describe):
Applicant has secured mezzanine financing from an outside investor. Bank
lending may be obtained, but has not been finalized at this time.
Level of financial participation by applicant for the project (describe):
Equity participation will be 20% of the project cost.
Project Details
Purpose (Explain the project and attach drawings or plans if applicable):
The project would involve the construction of a 48,000 s.f. transitional
care center with 70 beds. A rendering of the exterior and the site plan is
attached.
Is the Project within the TIF or CTP District?
it Yes
No (If not, explain how it would serve or benefit the TIF /CTP District):
Explain how the project fits into existing community plans (such as the Comprehensive Plan,
Downtown Plan, Transportation Plan, Park Plan, etc...):
The project would provide a Next- Generation transitional care center for
aging Americans seeking short -term, post -acute care transitional care. With
the aging Baby Boomer population, this option will become only more
appealing and desired from prospective guests.
The project MUST fall within the parameters of the Redevelopment Commission Project List.
Describe how the project falls within one or more of the required criteria.
The grant would provide funding support for a water line extension.
Will local contractors be used for the project?
N Yes
L No (Explain)
Applicant's contractor will proactively make bidding opportunities available
to local contractors.
Page 2 of 4
Other sources of financing secured by the applicant (describe):
Applicant has secured mezzanine financing from an outside investor. Bank
lending may be obtained, but has not been finalized at this time.
Level of financial participation by applicant for the project (describe):
Equity participation will be 20% of the project cost.
Project Details
Purpose (Explain the project and attach drawings or plans if applicable).
The project would involve the construction of a 48,000 s.f. transitional
care center with 70 beds. A rendering of the exterior and the site plan is
attached.
Is the Project within the TIF or CTP District?
E Yes
❑ No (If not, explain how it would serve or benefit the TIF /CTP District):
Explain how the project fits into existing community plans (such as the Comprehensive Plan,
Downtown Plan, Transportation Plan, Park Plan, etc...):
The project would provide a Next- Generation transitional care center for
aging Americans seeking short -term, post -acute care transitional care. With
the aging Baby Boomer population, this option will become only more
appealing and desired from prospective guests.
The project MUST fall within the parameters of the Redevelopment Commission Project List.
Describe how the project falls within one or more of the required criteria..
The grant would provide funding support for a water line extension.
Will local contractors be used for the project?
29 Yes
J No (Explain)
Applicant's contractor will proactively make bidding opportunities available
to local contractors.
Page 2 of 4
RETURN ON INVESTMENT
Estimated Potential new TIF Revenue:
Estimated Employment Opportunity:
n New .lobs:
o Retained Jobs:
S 152,000 /year *
Approx. 70 permanent, including 50 FTEs
n/a
Other benefits to the community (Explain):
This transitional care center will provide a significant source of new property
tax revenue, as well as multi - million dollar annual local economic impact based
on similar studies commissioned in other markets.
Applicant Certification
1 understand that the submittal of this application does not guaranty funding and that the
Richmond Redevelopment Commission will consider the merit of your project based tip on the
benefit to the conmurnity, benefit to the TIF or CTP district, and how it complies with existing
community plans.
I understand that I it-ill need to appear before the Redevelopment Commission to represent this
request.
1 understand that my request is governed by state enabling legislation for Redevelopment
Commissions (IC ) andfor Certified Tech Parks (IC ) and that the local Richmond
Redevelopment Commission cannot consider a request that does not fall within those guidelines.
I understand that I may be required to submit receipts andlor other documentation to the City of
Richmond. Indiana State Board oj'Accounts or other sources as part oj'the project.
I understand that my request is considered public information and sources such as the local
media nu y have access to this application.
1 understand that if funded, memorandums of understanding andlor other agreements may need
to be drafted and,frrnding may only be available to on a reimbursement basis.
I understand that my application will be considered in accordance lvith the timelines attached to
this application and that timelines may be extended due to unforeseen circumstances.
Submitted By
(Signature): A, Date: to
Return completed application to Tony Foster, Department of Metropolitan Development,
50 North 5th Street, Richmond IN, 47374 or tfoster @richmondindiana.gov
Page 3 of 4
t Total construction hard costs (excluding land) of $9,500,000 assessed at 800
nultiplied by rate of 20 (cap applied to non - homestead residential property).
For Internal Use
Date Received:
Reviewed by Metropolitan Development: Date:
Reviewed by Mayor' Office: Date:
Project falls within one or more categories of the Redevelopment Plan: _Yes No
Project is complies with Redevelopment and/or CTP enabling legislation: Yes No
Application is eligible to be heard at the meeting.
Other:
2014 Meetings - All meetings will be held at 12:00 noon
Meeting Date
Application Deadline
January 22
January 8
February 26
February 5
March 26
March 5
April 23
April 2
May 28
May 7
June 25 June 4
July 30 July 2
August 27
August 6
September 24
September 3
October 22
October 1
November TBA
November 5
December TBA
December 3
Page 4 of 4