HomeMy Public PortalAbout06-10-2014 first reading Street and sidewalk loan order_201406061002087531Michael J. Driscoll
Town Manager
TOWN OF
WATERTOWN
Office of the Town Manager
Administration Building
149 Main Street
Watertown, MA 02472
Phone: 617-972-6465
Fax: 617-972-6404
www.watertown-ma.gov
townmgr@watertown-ma.gov
To: Honorable Town Council
From: Michael J. Driscoll, Town Manager
Date: June 5, 2014
RE: Agenda Item — Proposed Loan Order
As you are aware, as indicated in the Fiscal Year 2015 Budget Message, street and sidewalk
maintenance is one of the top priorities in the Honorable Town Council's Fiscal Years 2009 through
2015 Budget Policy Guidelines. Within the Fiscal Year 2015-2019 CIP, $91,515,000 is designated
for street and sidewalk improvements. The Fiscal Year 2015 General Fund Budget includes
$831,753 to augment projected Chapter 90 monies. Beginning in Fiscal Year 1999 and including
Fiscal Year 2015, the Honorable Town Council has approved $10,329,437 for the Street and
Sidewalk Improvements appropriation, an average of $607,614 for each of the seventeen fiscal years.
On March 11, 2014, the Honorable Town Council approved moving forward with street/road
improvements and overlays in Summer 2014 (see February 19, 2014 Committee on Public Works
Report and excerpt from March 11, 2014 Town Council minutes).
On May 13, 2014, the Honorable Town Council President indicated National Grid has informed
the Town that gas lines will be replaced on seven of the streets listed in the above mentioned March
11th action. The Honorable Town Council President requested a motion to refer the list of street/road
repairs back to the Committee on Public Works for review and updating (see excerpt May 13, 2014
Town Council minutes).
On May 27, 2014, the Honorable Town Council approved moving forward with the updated
Summer 2014 Roads Project list (see May 20, 2104 Committee on Public Works Report and excerpt
from May 27, 2014 Town Council minutes).
Therefore, given all of the above, I respectfully request the attached Loan Order totaling
$2,500,000 be placed on the June 10, 2014 Town Council Agenda as a First Reading.
Thank you for your consideration in this matter.
cc: Gerald S. Mee Jr., Superintendent of Public Works Steven Magoon, Director of Community Development & Planning
Karen Norton, Assistant Town Treasurer/Collector Thomas J. Tracy, Town Auditor
EDWARDS
WILDMAN
May 19, 2014
Peter B. Frazier, Senior Vice President
First Southwest Company
Municipal Advisory Group
54 Canal Street, Suite 320
Boston, Massachusetts 02114
EDWARDS WILDMAN PALMER RP
111 HUNTINGTON AVENUE
BOSTON, MA 02199
+1 617 2390100 main 41 617 2274420 Lox
edwardswildmon,con,
Kara K. Adams
+I 617 239 0387
fax +1 866 644 8575
kadams@edwardswildman, com
Dear Peter: (Town of Watertown — Road Bonds)
As requested 1 suggest the following form of revised loan order;
Ordered: that the following amount is appropriated for the following purposes:
Amount Purpose
$2,500,000 road, sidewalk and wheelchair ramp reconstruction, and for the
payment of other costs incidental or related thereto, including,
but not limited to drainage and water service improvements,
signing, pavement markings and related work as directed by the
Superintendent of Public Works
and that to meet this appropriation the Town Treasurer, with the approval of the Town
Manager, is authorized to borrow $2,500,000 under Chapter 44 of the General Laws or
any other enabling authority; that the Town Manager, Treasurer and the Superintendent
of Public Works are authorized to contract for and expend any federal, state or other aid
available for the projects; and that the Town Manager, Treasurer and the Superintendent
of Public Works are authorized to take any other action necessary or convenient to carry
out this vote.
The order must be published at least 5 days prior to the holding of a public hearing with respect to the
order and its final passage and require at least a two-thirds vote, as in the case of any other loan order for
bonds.
Please call me if there are any questions about the suggested proceedings.
SinF°rely,
471
a K. Adams
AM 33165480.1
o tA97i9RO • I I'.'x4G' K ''G • ISIAtI$UL
4'0 TAML)MD.
Q.' m .103 ANNALS • MIA/dl • 7e+{JP.!95tC�`la
)KY.l fWAH}1119010 rC. WPS4 PAt? BVAt sl
Excerpt from March 11, 2014 Town Council Minutes
Committee on Public Works report on a bog Park and Streets and Sidewalks — Cecilia Lenk,
Chair. Councilor Lenk read the committee reports. Councilor Woodland moved to approve the
report, seconded by Councilor Piccirilli and adopted by unanimous voice vote with Councilors
Aaron Dushku, Susan G. Falkoff, Anthony Palomba, Angeline B. Kounelis, Cecilia Lenk,
Vincent J. Piccirilli, Jr., Kenneth M. Woodland, Vice President Stephen P. Corbett and Council
President Mark S. Sider§ voting in the affirmative.
With respect to the dog park, it was noted by Mr. Magoon that the proposed dog park at Walker
Pond will happen regardless of a Council vote.
ACTION ITEMS AND VOTESi
Councilor Lenk moved that the Town present a detailed proposal, including a budget and
timeline, for the establishment of a dog park at How Park and that the Town continue to
investigate the possibility of establishing a dog park at Arsenal Park or Filippello, seconded by
Councilor Woodland and adopted by unanimous voice vote with Councilors Aaron Dushku,
Susan G. Falkoff, Anthony Palomba, Angeline B. Kounelis, Cecilia Lenk, Vincent J. Piccirilli,
Jr., Kenneth M. Woodland, Vice President Stephen P. Corbett and Council President Mark S.
Sideris voting in the affirmative.
Councilor Lenk moved the proposed list of street/road improvements and overlays, seconded by
Vice President Corbett.
Councilor Dushku asked if any of the streets on this list were holdovers from last years' list.
Councilor Lenk stated that the only road left was Union Street and indicated that the committee
tries to get the list of roads as early as possible and are on a different process now.
Councilor Palomba indicated that the list was designed to achieve the goal of completing all
streets/roads on the list.
The Chair indicated that he raised concern that last year Union Street did not get completed and
as a result the committee came up with an achievable plan.
The motion was adopted by unanimous voice vote with Councilors Aaron Dushku, Susan G.
Falkoff, Anthony Palomba, Angeline B. Kounelis, Cecilia Lenk, Vincent J. Piccirilli, Jr.,
Kenneth M. Woodland, Vice President Stephen P. Corbett and Council President Mark S. Sideris
voting in the affirmative,
Town of Watertown
Town Council Committee 011 Public Works
Wednesday, February 19, 2014 at 5:00 PM
Mastrangelo Council Chambers
The Public Works Committee met at 5:00 PM to continue the discussion of Fiscal Year 2015
Proposed Street and Road Improvements. Councilors Cecilia Lenk (Chair), Steve Corbett (Vice -
Chair) and Tony Palomba (Secretary) wore present as was Councilor Vincent Piccirilli, Public
Works Superintendent Gerry Mee, and DPW Clerk Mary Healy.
The Committee discussed a memo and revised listed of potential street and road improvements
presented by Mr. Mee (see attached).
Councilor Corbett made the following recommendation which was seconded by Councilor
Palomba and passed 3 -0.
The Committee on Public Works recommends that the Town Connell approve the list of street and road
improvements presented by Superintendent Mee (Attachment A) and approve a selected mill and overlay
permanent patch program valued at approximately $300,000.
Councilor Corbett made a motion to adjourn which was seconded by Councilor Palomba and
passed 3 — 0. The meeting adjourned at 6:00 PM.
Minutes Prepared by Councilor Palomba
February 20, 2014
TO:
TOWN OF WATERTOWN
DEPARTMENT OF PUBLIC WORKS
124 ORCHARD STREET
WATERTOWN, MASSACHUSETTS 02472
Tel: 017.072.6420
Fax: 617-972-6402
Michael. J. Driscoll, Town Manager
Public Works Sub -Committee My mbers
FROM: Gerald S. Mee, Jr,
DATE: February 20, 2014
RE: 2.014 Final Road Program
Attached you will find a copy of the 2014 roadway candidates chosen utilizing the road management
program.
The total cost for this program will be $2,490,106.43 or say $2.6M. There are 12 streets on this list
With various parameters set for each street as Well as various techniques used within selected
parameters. The last Item on the road spread sheet will be used for Selective Mill and Overlay of
various short sections in the range of 300 linear feet to address adverse affects from winter conditions.
This is a process we have used in the past which has worked extremely well .and has delayed the need
for other construction techniques.
We all know how valuable this road roahagemeht program is maintaining the Town's infrastructure and
I would like to thank you in advance for your cooperation and assistance In moving this program
forward.
AncAp mtAct°uytstzot4 cWMemo (oswn) comm. 2-2.0-14.doc
Capital Impr ovement Plan 2014
( Roadw ay Candidates )
Street Name
"
From
Construction
To Method
R oad Class
COST ESTIM ATE (16%
CONTINGENCY
INCLUDED)
P OLICE DETAILS
(11% OF
CONSTRUCTION
TOTAL COST
Fifield Street
Irving St reet
Perkins Sch ool R eclamation
LO
$ 131,130.43
$ 14,424.35
$ 145,554.78
Av on Road
Belmont Town li ne
Dead End Reclamation
LO
1
$ 114,99130
$ • 12,649.04
$ 127 ,640.35
Alden Ro ad
Belmont Town Line
Dead End Reclamatio n
LO
$ 104,904 .35
$ 11,539.48
$ 116,44323
Salisbu ry Ro ad
Maplewood Street
Edgecflff eR oad
Mill and Overlay
LO
$ 84,730.43
$ 9,320.35
$ 94 ,050.78
Priest Road.
Charles River Road
Riverside Street -
Reclamati on
LO
$ 163,408.70
$ 17,974.96
$ 181 ,383.65
Loomis Ave nue
O rchard Street
Br adshaw Street
Mill and Overlay
LO
BradshawStreet
Gertrude Street
Mill and Overlay
Ge rtrude Street
Downey Stre et
Mill and Overl ay
$ 126,08696
$ 13,869.57
$ 139,956.52
Duff Street
Madiso n Avenu e
Grant Avenu e
Mill and Overlay
LO
Grant Avenu e
Belmont Street
Mill a nd Overlay
$ 131,130.43
$ 14,42435
$ 145,554.78
Barna rd Avenue
Co lumbia Stre et
Orchard Street
Mill and Overlay
LO
Orchard Street
Bellev ue Road
Reclamati on
$ 449,87 &26
$ 49,486.61
$ 499,364.87
Lincoln Stre et
Mount Au burn Street
Waln ut Street
Reclamation
1.0
Spruce Street
Reclamation
LO
$ 284,45217
$ 31,289.74
$ 315,741.91
Dexter Avenu e
Wiilow Park
Nichols Ave nue
Reclamation
CO
Nichols Avenue
Olive r Road
Re clamation
Olive r Road
Mount Auburn Street
Reclamation
$ 265,286.96
$ 29,18] ..57
$ 294,46832
Ka therine Roa d
Common Stre et
Church Stree t
Reclamation
LO
$ 102,886.96
$ 11,317 .57
$ 114,20452
Cushman Street
Oak Place
Fayette Stre et
Reclamation
LO
$ 88,765.22
$ 9,764.17
$ 98,529.39
Sele ctiv e Mill & Ov erlay
$ 21771753
Total
$ 2,047,652.17 $
225,241.74 $ 2490,106.44
SAY $ 2,500 ,000.00
Excerpt from May 13, 2014 Town Council Minutes
PRESIDENT'S REPORT: The Chair stated that with respect to the adopted $2.5 million loan
order for street/road repairs; the gas company has indicated that they would like to replace gas
lines on seven of those streets. Therefore, the Chair asked that the List be referred back to the
Public Works subcommittee so that it can be updated to reflect this. So moved by Vice President
Corbett, seconded by Councilor Lenk and adopted by unanimous voice vote with Councilors
Aaron Dushku, Susan G. Falkoff, Anthony Palomba, Angeline B. Kounelis, Cecilia Lenk,
Vincent J. Piccirilli, Jr., Kenneth M. Woodland, Vice President Stephen P. Corbett, and Council
President Mark S. Sideris voting in the affirmative.
Excerpt from May 27, 2014 Town Council Minutes
Public Works report and action on an updated Summer 2014 Roads Project List and
memorandum — Cecilia Lenk, Chair. Councilor Lenk read the committee report. Councilor
Woodland moved to accept the report, seconded by Councilor Kounelis.
Councilor Falkoff questioned the yearly evaluation of streets. Mr. Mee stated that it should be
updated yearly due to extreme winter conditions that have taken a toll on the roads.
Councilor Dushku asked about gas pressure line problems. Mr. Mee noted gas pressure problems
at the Lowell School and the Public Works facility and indicated that National Grid stated that
there is a problem with one of the lines which is being investigated and resolved.
Vice President Corbett inquired about an amendment to the report.
Councilor Lenk concurred and moved to approve the new list of streets for repair in 2014.
The report as amended was adopted by unanimous voice vote with Councilors Aaron Dushku,
Susan G. Falkoff, Anthony Palomba, Angeline B. Kounelis, Cecilia Lenk, Vincent J. Piccirilli,
Jr., Kenneth M. Woodland, Vice President Stephen P. Corbett and Council President Mark S.
Sideris voting in the affirmative.
ACTION ITEMS:
Councilor Lenk moved that the public works prepare a priority list of streets for 2015 and
forward this list to National Grid to complete gas work on these streets in 2014; and investigate
water main/sewer drainage needs, seconded by Councilor Kounelis and adopted by unanimous
voice vote with Councilors Aaron Dushku, Susan G. Falkoff, Anthony Palomba, Angeline B.
Kounelis, Cecilia Lenk, Vincent J. Piccirilli, Jr., Kenneth M. Woodland, Vice President Stephen
P. Corbett and Council President Mark S. Sideris voting in the affirmative.
Councilor Lenk moved to approve the Arlington/Orchard/School streets mill overlay as
recommended, seconded by Councilor Dushku and adopted by unanimous voice vote with
Councilors Aaron Dushku, Susan G. Falkoff, Anthony Palomba, Angeline B. Kounelis, Cecilia
Lenk, Vincent J. Piccirilli, Jr., Kenneth M. Woodland, Vice President Stephen P. Corbett and
Council President Mark S. Sideris voting in the affirmative.
Meeting of the Committee on Public Works
Tuesday, May 20, 2014, 5:00 PM
Mastrangelo Council Chambers
The Public Works Committee met to discuss updates to the summer 2014 road projects.
Committee Members Present: Councilors Lenk (Chair), Corbett (Vice -Chair) and Palomba (Secretary).
Attending: Councilor Kounelis, Public Works Superintendent Gerry Mee, Steve Magoon, Director of
the Department of Community Development and Planning, DPW Clerk Mary Healy, James Fitzgerald
of World Tech Engineering, and residents: E. Jane Smith, Ted Cocca, Elodia Thomas, Anni Clark, and
Sheppard Ferguson.
Mr. Mee explained that within the last week he was notified by National Grid that all the streets
scheduled to be repaired this summer per the approval of the Town Council were scheduled for gas
main repairs and replacements. This was particularly disturbing this Mr. Mee had informed National
Grid in February about the Town's plans for street repairs. In addition the bid for the 14 streets that
were to be repaired had been published and a company had been selected.
Recent negotiations with National Grid resulted in a commitment by National Grid to provide a
complete list of all Town -owed streets that require gas repairs. DPW would than prioritize which of
these streets National Grid should work on immediately. National Grid will initially assign two crews
to work in Watertown and eventually five crews and will work throughout the winter to complete the
gas -related repairs.
Mr. Mee then recommended that Arlington, Orchard, and Schools Streets (see attached) be repaired
this summer as replacements for the original streets selected for repair in February. The repairs would
be done by the same contractor following the same timeline. The estimated cost of the repairs is
$2,086,800. A number of questions were raised regarding Mr. Mee's recommendations by members of
the Committee and others attending the meeting. Mr. Mee explained that of the few streets that did not
need gas -related repairs, Arlington, Orchard, and School Streets were prime candidates for mill and
overlay repairs which would extend the life of the roads for seven to fifteen years.
Councilor Corbett made the following motion:
The Committee recommends that the Town Council request that the Department of Public Works
prepare a priority list of streets that the Town plans to reconstruct in during the Summer 2015
construction season and provide this list to National Grid so it can complete gas main repair and
replacement on these streets in 2014; Public Works will also investigate water/sewer/drainage needs
on these streets.
The motion was seconded by Councilor Palomba and passed 3 — 0.
-2 -
Residents of Marion Street stated the reasons (extensive use by those attending events at Victory Field,
areas with no curbing, parking on asphalt sidewalks, etc.) why they felt upper Marion Road should be a
priority for repair including replacing/repairing sidewalks and curbs. While Mr. Mee did not agree
with all the comments and concerns raised, he acknowledged that the present Road Program used to
determine what streets are priority (and for what type of repair) needs significant updating. In addition
to including that data about planned utility repairs (gas and water and sewer) the Road Program should
include the results of a visible review of each street and details about the past materials and technique
used to repair the street.
Following a discussion of the Committee's earlier recommendation (approved by the Council) that
DPW implement a "selected permanent patch program", the Committee requested the Mr. Mee expand
that number of streets that he had originallyselected for this type of repair.
Councilor Palomba made a motion to adjourn the meeting. The motion was seconded by Councilor
Corbett and passed 3 — 0.
Minutes were prepared by Councilor Palomba
May 22, 2014
2014 Roadway Rehabilitation (Conflict Resoluti on)
Street Name
From
To
Construction Method
R oad Class
C onstruction
Estimate (with
16 % Contingency)
P olic e D etails
(11 % of
Construction
Cost)
Total
Orchard Street
Lexington Street
Wa verl ey A venue
Mill/Overlay with F ull Depth Patch
AR
$ 188 ,000.00
$ 20 ,680.00
$
208,680 .00
Orchard Street
Waverley Avenue
Channing Road
Mill/O verlay with Full Depth Patch
AR
$ 309,000.00
$ 33 ,990.00
S
342,990.00
Orchard Stre et
Channing Road
Common Street
Mill/Overlay with Full Depth Patch
AR
$ 199,000.00
$ 21,890 .00
$
220,890.00
School Street
Belmont Street
Maplewood Street
Mill/O verlay with Full Depth P atch
CO
$ 242,000 .00
$ 26 ,620 .00
$
268,620.00
School Street
Maplewoo d Stre et
Mount Auburn Street
Mill/Overlay with F ull Depth Patch
CO
$ 211,000.00
$ 23,210 .00
$
234,210.00
Schoo l Street
M ount Auburn Street
Boylston Street
Mill/O verlay with Full Depth Patch
CO
$ 201,000 .00
$ 22,110.00
$
223 ,110.00
School Street
Boylston Street
Arsenal Street
Mill/Overlay with Full D epth Patch
CO
$ 266,000 .00
S 29,260.00
$
295 ,260 .00
A rlington Street
Belmo nt Street
Maplewood Street
Mill/O verlay with Full Depth Patch
CO
S 175 ,000.00
$ 19 ,250.00
$
194,250.00
A rlington Street
Maplewood Street
Mount Aubu rn Street
Mill/Overlay with Full Depth Patch
CO
$ 89,000 .00
$ 9,790 .00
$
98,790.00
T otal
$ 1,880,000 .00 $ 206 ,800 .00
2,086,800.00
Selective Mill and Overlay
300,000.00
2,386,800.00
Gerald S. Mee Jr.
Superintendent
TOWN OF WATERTOWN
DEPARTMENT OF PUBLIC WORKS
124 ORCHARD STREET
WATERTOWN MA 02472
TO: Michael Driscoll, Town Manager
Public Works Sub Committee
FROM: Gerald S. Mee, Jr.
Superintendent
DATE: May 27, 2014
RE: 2014 Final Road Program
(P) 617-972-6420
(F) 617-972-6402
Sir,
As you are aware there has been a tremendous level of interaction recently with
NGRID regarding the formulation of the 2014 Road Program. On February 20, 2014 we
submitted a road program list consisting of 12 streets with various parameters.
Unfortunately as the discussion with NGRID continued I opted to incorporate a section in
our road management program to reflect the need for gas main repair or replacement.
Through adding this section it became very obvious that the capital needs of NGRID for
the underground infrastructure within Watertown was much greater than anyone could
have ever imagined.
NGRID's underground infrastructure in Watertown consists of approximately 85
miles of main constructed of various products such as cast iron, unlined steel main, lined
steel main and plastic mains. All of these products carry various levels of concern as
related to our road program especially vibration through our means of road bed
compaction. This vibration has the potential for creating gas leaks within all products
excluding the plastic.
We continued investigating numerous streets for potential addition to our road
program only to continually be rejected due to the underground gas needs, unfortunately
all of the plastic gas mains which hold the highest level of integrity are either on streets
we have already reconstructed or lie underneath multiple private ways which are
ineligible for our road program.
C:UsersVhand. WA TER TO WNAppData'tLocaItMicrosoffttMndowsTernporaty Internet Files'Content.Outlook11TM8B11 L12014
Final Road Program.doc
With great frustration and disappointment, and the inability to address the surface
needs we questioned NGRID's commitment of the capital needs in Watertown. I
strongly expressed disappointment with past road programs we have operated without
any knowledge of the underground gas needs, even though every street on our road
program we solicited input from the gas company which ultimately yielded the necessity
for the gas company to excavate newly paved streets to repair gas leaks.
NGRID has committed to working off of a priority list created by the Public Works
Department to address the underground infrastructure gas needs prior to the 2015 Road
Program. The gas company currently is operating three gas main relay crews in
Watertown and has committed to increase that level to five crews and has also shown
their commitment to eliminate the needs for excavation through newly paved streets with
their commitment of five crews addressing the gas main and service laterals prior to our
road program.
Although I am very frustrated and very disappointed with this process I think we
have to take a positive look at the gas company's commitment which ultimately
addresses many of the things we have been complaining about for years.
In short, we need to allow the five gas company crews to get ahead of our planned
road program which will allow us to advance a road program each and every year upon
completion of the gas work. In the short term we were faced with how to operate a 2014
Road Program which we all know is critical that each and every year we make major
attempts to address surface conditions in an attempt to stay ahead of the road surface
needs as stated in the road management program.
Fortunately the gas company issues may very well serve to work in our favor as it
is very difficult to try and address some of our semi -main streets to prolong the life
expectancy without the need for the most costly full depth reconstruction. Given
consideration of the traffic volumes on these streets, our investment this year of a mill
and overlay in my mind will serve extremely effective and have a positive result.
Therefore, attached is the latest, greatest 2014 Road Program which will consist of
various segments of three streets with varying parameters. The cost of these three
streets is currently estimated at $2,086,800.00. In the previous road program we had a
section referred to as selective mill and overlay of various short sections in the range of
300 linear feet; this section shall also remain in the latest 2014 Road Program. In the
original approved program the mill and overlay section referred to a total value of
$217,212.53. Under the new program this same section is adjusted to $300K for a total
combined cost of $2,386,000.00. Also the department plans to potentially add an
additional technique to maintain the integrity of the road by using asphalt embedded
fabric on various lateral cracking. Therefore it is my request that between the current
estimated road program, the mill and overlay of 300 foot sections - various locations, and
the potential additional cost from fabrics that we maintain the projected $2.5M road
program.
C:1Usersvhand.WATERTOWMAppDatalLocallMicrosoftlWindowslTemporary Internet Files\Content. OutlOOkIl TM8B11 L12014
Final Road Program.doc
A visual inspection of the three streets to receive treatment show lateral cracking,
spider cracking, various levels of delamination and these three locations are extremely
prone to potholes which has required a substantial amount of attention by the department
over the years.
Just to be very clear there are three sections on School Street where a visual
inspection gives the appearance that the surface is in good condition unfortunately this
appearance is misleading and the three sections are relatively short sections which in
years past has seen some interim repairs performed to prolong a given section's life.
This maintenance technique has served us well as it has prolonged the life to this point
where I am proposing a mill and overlay of the entire section as described in the road
program list to treat the street as one entire section with a consistent asphalt wearing
surface throughout.
It is my professional opinion given all the factors stated in this memo that the
Town's best investment in 2014 would be to proceed with the attached recommended
2014 Road Program List.
C:1 Users yhand.WATERTOWMAppDataQocallMicrosoftllMndowslTemporary Internet Files1Content.Outlook11 TM8811 L12014
Final Road Prograrn.doc
2014 R oadw ay Rehabilitation (Conflict Resol ution)
Street Name
From
To
Construction Method
Road Class
Constr uction
Estimate (with
16 % C ontingency)
Police Details
(11 %of
Construction
Cost)
Total
Orchard Street
Lexington Street
Waverley A venue
Mill/Overlay with Full Depth Patch
AR
$ 188 ,000.00
$ 20 ,680 .00
$
208,680.00
Orchard Street
Wav erley Avenue
Channing Road
Mill/O verlay with Full Depth Patch
AR
$ 309 ,000 .00
$ 33 ,990.00
$
342,990.00
Orchard Street
Channing Road
Common Street
Mill/O verlay with Full Depth Patch
AR
$ 199 ,000 .00
$ 21 ,890 .00
$
220,890 .00
Schoo l Street
Belmont Street
Maplewood Street
Mill/Overlay with Full Depth Patch
CO
$ 242 ,000 .00
$ 26 ,620 .00
$
268,620.00
School Street
Maplewoo d Street
Mount Auburn Street
Mill/Overlay with Full Depth Patch
CO
$ 211 ,000.00
$ 23,210.00
$
234,210.00
School Street
Mou nt Auburn Street
Boylsto n Street
Mill/O verlay with Full Depth Patch
CO
$ 201,000.00
$ 22,110.00
$
223,110 .00
Scho ol Street
Boylston Street
Arsenal Street
Mill/Overlay with Full Depth Patch
CO
$ 266,000.00
$ 29 ,260 .00
$
295,260 .00
Arlingto n Street
Be lmo nt Street
Maplewood Street
Mill/Overlay with Full Depth Patch
CO
$ 175,000 .00
$ 19,250.00
$
194,250.00
A rlington Street
Maplewood Street
Mount Auburn Street
Mill/Overlay with Full Depth Patch
CO
$ 89 ,000.00
$ 9,790 .00
$
98,790.00
Tot al
$ 1,880,000.00 $ 206,800 .00 $
2,086,800 .00
Selective Mill and Overlay
300,000.00
2,386,800.00