HomeMy Public PortalAboutWell #9 & Tank Project Change Order #7Director
Brona D. Steele
City of Crestview
Department of Public Services
715 Ferdon Boulevard North
Crestview, Florida 32536
INTEROFFICE MEMORANDUM
PUBLIC SERVICES DEPARTMENT
TO: Wayne Steele
FROM: Fred Cook
DATE: November 13, 2013 Wednesday
COPY: File
SUBJECT: Well #9 & Tank Project
Change Order #7
Telephone No. (850) 682-6132
Fax No. (850) 682-7359
E-Mail: fredcook@citvofcrestview.orq
Here is Change Order #7. This change order is to add the cost of staged grouting of the 18"
casing instead of continuous grouting — due to conditions encountered in the ground. If there
are any questions, let me know.
Please process this to Ms. Roy for the change.
C�'
TETRA TECH
Via E-mail
November 5, 2013
Tt No. 200-08540-12001
Wayne Steele
Public Services Director
City of Crestview
715 N. Ferdon Blvd.
Crestview, Florida 32536
Subject: Old Bethel Road Part I
Change Order No. 7
Dear Mr. Steele:
Enclosed, please find Change Order No. 7 from Speegle Construction, Inc. (Speegle). Unforeseen conditions
found between 400' and 500' below land surface (Ns) have necessitated the 18" production casing be set 100'
deeper than was originally estimated in order for it to be set in stable strata. This, in addition to a loss zone at 403'-
407' bls which caused a partial, but manageable, collapse of the borehole, and required a cement shot, has
caused the driller to re -assess the method in which they prefer to perform the final grouting. The driller proposes to
move forward with a staged grouting approach that consists of grouting in two stages with time in between the
stages (stage grouting) to allow for partial setting of the first lift of grout. This allows for safer, reduced pressures at
the loss zone. If the grouting were performed in one single lift under the current conditions, the pressure could
potentially create a problem by blowing out the borehole.
Change Order No. 7 covers Speegle's need to order additional casing and take additional time to perform the
stage grouting. Quantity adjustments to items included in the Contract are not included in this Change Order such
as the additional 100 LF of 18" production casing, the actual amount of grout used, and the reduced length of
open -hole drilling from 420 LF to 300 LF. These are unit price line items in the Contract and the actual amounts
used will appear in future Pay Applications after the work is performed. In all, we anticipate the noted adjustments
in the unit price quantities will credit approximately $3,000 back to the Contract.
Change Order No. 7 amounts to an addition of $6,298 to the Total Contract Price and seven (7) days to the Total
Contract Time. We have reviewed the proposed Change Order provided by Speegle and find it acceptable.
Should you have questions or need additional information, please call.
Timothy A. Vanderwalker, PE
Project Manager
Cc: Michael Bomar, PE, Tetra Tech
Fred Cook, PE, City of Crestview
Tetra Tech, inc.
12815 Emerald Coast Parkway, Suite 110,
Destin, FL 32550 850.837.9278
Fax 850.837.7269 www.tetratech.com
P:\201 I\Crestview Well and Tank \Constructionaeview-Approval\ContractorCOs\Part I\Part I Change Order No. 7.docx.
SCONSTRUCTION INC.
CGC-062-189
l
PEEGLE
November 1, 2013
Mr. Tim Vanderwalker
Tetra Tech
12815 Emerald Coast Pkwy, Suite 110
Destin, FL 32550
Dear Sir,
Speegle Construction, Inc. Tel: (850) 729-2484
210 Government Avenue Fax: (850) 729-1993
Niceville, Florida 32578 www.speegleconstruction.com
Dan Carruth
Project Manager
RE: Crestview Well No. 9
COR 1002-007, Revised - Grout Casing in Multiple Stages
Speegle Construction, Inc. respectfully submits the attached estimate for changes associated with grouting the 500 LF of
18" well casing in mulitple (2) Ilifts. The first grout lift will be from the bottom of the casing (500' BLS) to ten 10' above the
area which received the cement slurry (390' BLS), as suggested by Rowe Drilling. This estimate is based on our best
understanding of the changes that are necessary to the scope of work. In the event that additional work is required due to
unforseen conditions or impacts to other systems due to changing the size of the well, Speegle reserves the right to revisit
this estimate. While this will result in more grout, it is unknown at this time what the total quantity of grout required will be
or if we will exceed the originally scheduled 54 CY.
Total estimate for the above work: $ 6,298
Additional contract Extension: 7 Calendar Days
p^K •
Should you require any additional information, please do not hesitate to contact Dan Carruth at
850-729-2484 or email dcarruth@speegleconstruction.com
Sincerely,
Dan Carruth
cc: file Project Manager
SECTION 00843
CHANGE ORDER FORM
Project: City of Crestview
Part I - Well No. 9 and Elevated Storage Tank
DATE OF ISSUANCE:
EFFECTIVE DATE:
OWNER'S CONTRACT NO.:200-08540-12001
CHANGE ORDER NO. 07
CONTRACTOR:Speegle Construction, Inc.
ENGINEER: Tetra Tech
The following changes are hereby made to the Contract Documents:
CHANGE IN CONTRACT PRICE:
Original Contract Price
$ 1,965,660.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial Completion: 12/23/2013
Ready for final payment: + 30 Days
days or dates
Net changes from previous Change Orders No. 1 to
No. 6
$ 48,198.00
Net change from previous Change Orders No. 1
No. 6
80
to
Contract Price prior to this Change Order
$ 2,013,858.00
Contract Times prior to this Change Order
Substantial Completion: 3/13/2014
; Ready for final payment: + 30 Days
days or dates
Net Increase (grease) of this Change Order
$ 6,298.00 ✓
q
Net Increase Change Order
(decrease) of this
7 V
days
Contract Price with all approved Change Orders
$ 2,020,156.00 V'
Contract Times with all approved Change Orders
Substantial Completion: 3/20/2014
Ready for final payment: + 30 Days
days or dates
MAD/slm/specs/s-1 /00843
Tt#200-08540-12001
00843-1
l "*
050412
FOR CONSTRUCTION INCLUDING ADDENDUMS 1, 2, 3, 4 & 5
1 /29/2013
CHANGES ORDERED:
I. GENERAL This change order is necessary to cover changes in the work to be
performed under this Contract. The General Conditions, Supplementary Conditions,
Specifications and all parts of the Project Manual listed in Article 1, Definitions, of the
General Conditions apply to and govern all work under this change order.
Change Order No. 7
II. REQUIRED CHANGES: Grout 18" casing in multiple stages/lifts.
III. JUSTIFICATION:
Rowe Drilling recommended that the casing be grouted in multiple stages,
or lifts, which will result in a reduced amount of pressure on the area which
previously received a shot of cement slurry (390' BLS). Request 7 calendar
days added to contract (3 of which are compensated and associated with
stage grouting and additional time to order additional 18" casing and 4 of
which are uncompensated and related to additional days necessary to
reach suitable rock formation and confirm final 18" casing depth)
IV. PAYMENT:
MAD/s1m/specs/s-1 /00843
Tt#200-08540-12001
00843-2 050412
FOR CONSTRUCTION INCLUDING ADDENDUMS 1, 2, 3,4 & 5
1 /29/2013
V. APPROVAL AND CHANGE AUTHORIZATION:
Acknowledgments:
The aforementioned change, and work affected thereby, is subject to all provisions of the
original contract not specifically changed by this Change Order; and,
It is expressly understood and agreed that the approval of the Change Order shall have no
effect on the original contract other than matters expressly provided herein.
Change Order Request by:
Change(s) Ordered by:
RECOMMENDED BY:
Tetra Tech
oed Signature) t(Date)
Project Manager
(Title)
APPROVED BY:
ACCEPTED BY:
Speegle Construction, Inc.
Contractor)
11/1/2013
(Date)
Vice -President
City of Crestview, Florida
c� (Owner)
By:/L.eat.4 mil / 2-73 /26
(Authorized Signature) (Date)
END OF SECTION
MAD/sl m/specs/s-1 /00843
Tt#200-08540-12001 00843-3
(Title)
050412
FOR CONSTRUCTION INCLUDING ADDENDUMS 1, 2, 3, 4 5
1 /29/2013
REQUEST for CHANGE ORDER SUMMARY
DESCRIPTION: Grout Casing in Multiple Stages
REASON FOR CHANGE: UnforSeen Conditions
ARCH RFP#
SCI RCO#
QUOTE DATE
0
1002-007
11/1/2013
DIV
SCOPE DESCRIPTION
NOTES
LABOR
MATT
EQUIPT
SUBCONT
SCI COSTS TOTAL
SUBCONTRACTED TOTAL
GRAND TOTAL
1
General Conditions
$ 573.32
$ 179.28
$ -
$ -
$ 752.60
$ -
$ 752.60
2
Sitework & Demolition
$ -
$ -
$ -
$ 4,720.00
$ -
$ 4,720.00
$ 4,720.00
3
Concrete
$ -
$ -
$ -
$ -
$ -
$ -
$ '
4
Masonry
$ -
$ -
$ -
$ -
$ -
$ -
$ -
5
Steel
$ -
$ -
$ -
$ -
$ -
$ -
$ '
6
Carpentry, Wood & Plastic
$ -
$ -
$ -
$ -
$ -
$ -
$ -
7
Thermal & Moisture Protection
$ -
$ -
$ -
$ -
$ -
$ -
$ -
8
Openings
$ -
$ -
$ -
$ -
$ -
$ -
$ '
9
Finishes
$ -
$ -
$ -
$ -
$ -
$ -
$ '
10
Specialties
$ -
$ -
$ -
$ -
$ -
�$
$ -
11
Equipment
$ -
$ -
$ -
$ -
$ -
$ -
$ -
12
Fumishings
$ -
$ -
$ -
$ -
$ -
$ -
$ '
13
Special Construction
$ -
$ -
$ -
$ -
$ -
$ -
$ '
14
Hoisting & Conveying
$ -
$ -
$ -
$ -
$ -
$ -
$ '
15
Fire Sprinklers
$ -
$ -
$ -
$ -
$ -
$ -
$ '
Plumbing
$ -
$ -
$ -
$ -
$ -
$ -
$ -
HVAC & Controls
$ -
$ -
$ -
$ -
$ -
$ -
$ -
16
Electrical
$ -
$ -
$ -
$ -
$ -
$
$ -
17
Commissioning
$ -
$ -
$ -
$ -
$ -
$ -
$ '
SubTotals
Payroll Burden
Sales Tax
Sub Bond
SubTolals
General Liability Insurance
Property (Builders Risk) Insurance
P & P Bond
Gross Receipts Tax (City Bus Lic)
SUBTOTAL
Overhead/Profit
Overhead/Profit
SUBTOTAL
GRAND TOTAL
Extended General Overhead
$ 573.32
$ 179.28
$ -
$ 4,720.00
$ 752.60
$ 4.00
$ 5,472.60
45%
$ 257.99
$ 257.99
$ -
$ 257.99
6%
-:
$ 10.76 I $ -
$ 10.76
$ -
$ 10.76
0.00%
$ -
$ -
$ -
$ -
$ 831.32 $ 190.04 I $ -
$ 4,720.00
$ 1,021.35
$ 4,720.00
$ 5,741.35
0.4200%
of Subtotal
of Subtotal
of Subtotal
$ 11.50
$ 19.82
$ 31.32
0.6500%
$ 17.81
$ 30.68
$ 48.49
1.0000 %
$ 27.40
$ 47.20
$ 74.60
0.0000 %
$ -
$ -
$ -
$ 1,078.06
$ 4,817.70
$ 5,895.77
15.00%
$ 161.71
$ -
$ 161.71
5.00%
$ -
$ 240.89
$ 240.89
$ 1,239.77
$ 5,058.59
$ 6,298.36
$ 1,239.77
$ 5,058.59
$ 6,298.36
$ -
$ -
$ -
$ -
$ -
$ -
$ 1,240
$ 5,059
$ 6,298
Time Extension
'This Proposal is for only the work identified by the above change description.
• See reservation of rights language on the Detail backup.
7 Calendar days
9/(
DETAIL PROPOSED CHANGE ORDER ESTIMATE
DIRECT COST ASSOCIATED WITH CHANGE ORDER
DESCRIPTION: Grout Casing in Multiple Stages
REASON: Unforseen Conditions
ARCH RFP #
SCI RCO#
QUOTE DATE
1002-007
11/1/2013
CODE
SCOPE DESCRIPTION
QUANT
units
L / U.P.
LABOR
M / U.P.
MAT'L
EQUIPMENT
SUBCONT
TOTAL
1
GENERAL CONDITIONS
Project Manager 33%
0.43
wks
1,730.00
$ 246.90
$ -
$ 246.90
Project Manager's Truck/Insurance/Gas 33%
0.10
months
$ -
650.00
$ 21.45
$ 21.45
Superintendent 33%
0.43
wks
1,550.00
$ 221.43
$ -
$ 221.43
Superintendent's Truck/Insurance/Gas 33%
0.10
months
$ -
650.00
$ 21.45
$ 21.45
Office Trailer
0.10
months
$ -
200.00
$ 20.00
$ 20.00
Superintendent Cell Phone 33%
0.10
months
$
150.00
$ 4.95
$ 4.95
Temp Toilets
0.10
months
$ -
150.00
$ 15.00
$ 15.00
Asbuilt documentation
2
HRS
25.00
$ 50.00
$ -
$ 50.00
RFP Preparation
1
HRS
50.00
$ 50.00
$ -
$ 50.00
Temp Utilities
0.10
months
50.00
$ 5.00
$
$ 5.00
Backhoe
0.43
wks
$
75.00
$ 32.14
$ 32.14
Loader/Dozer
0.43
wks
$
150.00
$ 64.29
$ 64.29
Copying & Specifications
$
$
$
Mail & Express Postage
$ -
$
$ -
Layout & Field Engineering
$ -
$ -
$ -
Crane & Hoisting
$ -
$
$ -
Schedule Study & Modification
$
$ -
$
Prepare Fragnet
$
$ -
$ -
Material Handling Equipment
$ -
$
$ -
Safety
$ -
$ -
$
Clean-up & Debris Handling
$ -
$ -
$ -
Dumpster Pulls
$ -
$
$ -
Equipment Rental
$
$ -
$ -
Trucking & Hauling
$ -
$ -
$ -
Small Tools
$ -
$ -
$
Other
$ -
$ -
$ -
$
$ -
$ -
Division 1 Subtotal
$ 573.32
$ 179.28
$ -
$ -
$ 752.60
2
SITEWORK & DEMOLITION
Rowe Drilling - Stage Grouting (See Quote)
1
LS
$ -
$
$ 4,720.00
$ 4,720.00
Division 2 Subtotal
$ -
$ -
$ -
$ 4,720.00
$ 4,720.00
3
CONCRETE
0
EA
0.00
$ -
$ -
$
$ -
$
$ -
Division 3 Subtotal
$ -
$ -
$ -
$ -
$ -
4
MASONRY & STONE
$ -
$ -
$ -
$ -
$
$
Division 4 Subtotal
$ -
$
$ -
$ -
$ "
5
STEEL & METALS
EA
$ -
$ -
$
$ -
$ -
$
Division 5 Subtotal
$ -
$ -
$ -
$ -
$ -
6
WOOD & PLASTICS
$ -
$
$ -
$ -
$ -
$ -
$ -
Division 6 Subtotal
$ -
$ -
$ -
$ -
$ -
7
THERMAL & MOIST PROTECT
$
$
$
$ -
$
$ -
Division 7 Subtotal
$ -
$ -
$ -
$ -
$ "
8
OPENINGS
$
$ -
$ -
$ -
$ -
$ -
Division 8 Subtotal
$ -
$ -
$ -
$ -
$ -
9
FINISHES
$ -
$ -
$ -
$ -
$
$ -
Division 9 Subtotal
$ -
$ -
$ -
$ -
$ -
10
SPECIALTIES
$ -
$ -
$ -
$ -
$ -
$ -
Division 10 Subtotal
$ -
$ -
$
$ -
$ -
DESCRIPTION:
REASON:
DETAIL PROPOSED CHANGE ORDER ESTIMATE
DIRECT COST ASSOCIATED WITH CHANGE ORDER
Grout Casing in Multiple Stages
ARCH RFP #
SCI RCO#
QUOTE DATE
1002-007
Unforseen Conditions
11/1/2013
CODE
SCOPE DESCRIPTION
QUANT
units
L / U.P.
LABOR
M / U.P.
MAT'L
EQUIPMENT
SUBCONT
TOTAL
11
EQUIPMENT
$ -
$
$ -
$ -
$
$
Division 11 Subtotal
$ -
$ -
$ -
$ -
$ -
12
FURNISHINGS
$ -
$ -
$
$ -
$ -
$
Division 12 Subtotal
$ -
$
$ -
$ -
$ -
13
SPECIAL CONSTRUCTION
$ -
$ -
$
Division 13 Subtotal
$ -
$ -
$ -
$ -
$ -
14
HOISTING & CONVEYING
$
$ -
$
$
$
$ -
Division 14 Subtotal
$ -
$ -
$ -
$ -
$ -
15
FIRE PROTECTION
$
$ -
$ -
$
$ -
$ -
Division 15 Fire Subtotal
$ -
$ -
$ -
$ -
$ -
15
PLUMBING
$ -
$ -
$
$ -
$ -
$ -
Division 15 Plumb Subtotal
$ -
$ -
$ -
$ -
$ -
15
MECHANICAL & HVAC
$
$ -
$
$ -
$ -
$ -
$ -
Division 15 HVAC Subtotal
$ -
$ -
$ -
$ -
$ -
16
ELECTRICAL
$
$
$ -
$ -
$
$ -
$
Division 16 Subtotal
$ -
$ -
$ -
$ -
$ -
17
COMMISSIONING
$
$ -
$
$ -
$
$
Division 17 Subtotal
$ -
$ -
$ -
$ -
$ -
SubTotals
$ 573.32
$ 179.28
$ -
$ 4,720.00
$ 5,472.60
(v14
ROWE DRILLING COMPANY, INC.
WATER WELL CONTRACTORS
WATER WELLS & PUMPS, SALES AND REPAIR SERVICES
885 Herod Hwy Dawson GA 39842 Ph.# 229-894-6959 Fax# 229-995-4737
10/21/2013
Dan Carruth
Speegle Construction Inc.
210 Government Ave.
Niceville, FL 32578
Via Email: dcarruth@speegleconstruction.com
Dan,
Yes, you heard right that Friday 10/18/2013 we encountered what appeared to be suitable rock formation
to seat the 18" well casing. We contacted dense brown lime rock at 489'. We continued to drill this
formation to a depth of 500'. Samples of the formation from 489' to 500'were collected for Tetra Tech's
inspection and approval and a comparison to a State of Alabama well competition report supplied by
Tetra Tech to another City of Crestview's well located close by. I knew that this week would be spent
preparing the drill site and the 18" casing for installation so I took the liberty Friday of last week getting
the remaining 18" casing required started this way so as not to hold things up.
Again, you heard right regarding the need to stage grout the 18" casing. As you are aware the 400' zone
where we contacted the rock and incurred the loss of our drilling fluid return had to be grouted in order to
continue the test hole. Our concern is that if an attempt to grout to the surface in a single pumping session
is tried, the pressure would be to great on the patch we have on the loss zone and will break out and allow
the cement slurry to travel out into the lost zone and not return to the surface. If we lose the cement slurry
to the lost zone the hydrostatic pressure will drop in the hole allowing the soft sands above 400' to cave in
and make having a continuous casing seal of slurry unobtainable. Our suggestion would be to allow us to
make the first session of pumping slurry to seal the casing be from the end of the casing 500' to 10' above
the lost zone or 390'. That would greatly reduce the pressure at that critical point in the bore hole and
provide a 10' plug above the lost zone to enable the second pumping something to seat on and greatly
increase our chances for a successful casing seal from bottom to land surface. We have listed our
additional cost and estimated time increase for installing the 18" deeper. Please do not hesitate to contact
if you have any questions regarding our request of additional time and cost.
Installing Additional 18" Well to 500'
1. 100'-0" Additional 18" Well Casing Installed @ $140.00 / ft.
2. Additional Rig & Crew Expense to Stage Grout 18" Casing
$14, 000.00
$4,720.00
Estimated Total of Additional Cost $18,720.00
Thank you for allowing Rowe Drilling Company to be of service.
Respectfully
Cliff Freeman