HomeMy Public PortalAboutWell #9 Tank Project Change Order Pay RequestDirector Brona D.Steele City of Crestview Department of Public Services 715 Ferdon Boulevard North Crestview, Florida 32536 PROJECT MEMORANDUM TO: Elizabeth Roy, City Clerk FROM: Fred Cook, City Engineer DATE: April 15, 2014 Tuesday COPY: File SUBJECT: Well #9 & Tank Project Pay Request #13 (Speegle Construction) Telephone No. (850) 682-6132 Fax No. (850) 682-7359 E-Mail: fredcook@citvofcrestview.orq Here is Pay Request #13 on this project, approved by Wayne as noted. Please process this for payment. Thank -you. Director Brona D. Steele City of Crestview Department of Public Services 715 Ferdon Boulevard North Crestview, Florida 32536 INTEROFFICE MEMORANDUM PUBLIC SERVICES DEPARTMENT TO: Wayne Steele FROM: Fred Cook DATE: April 15, 2014 Tuesday COPY: File SUBJECT: Well #9 & Tank Project Pay Request #13 (Speegle Const.) Telephone No. (850) 682-6132 Fax No. (850) 682-7359 E-Mail: fredcook@citvofcrestview.orq Here is the Contractor's Pay Request #13. This request includes finishing work on the well building, elevated tank, and site work. If you have any questions, let me know. Please process this for payment. Cvi9 C Via E-mail April 8, 2014 TETRA TECH Wayne Steele Public Services Director City of Crestview 715 N. Ferdon Blvd. Crestview, Florida 32536 Subject: Old Bethel Road Part I Pay Request No.13 Dear Mr. Steele: /Re,c.— C Tt No. 200-08540-12001 Enclosed, please find Invoice Application No. 13 from Speegle Construction, Inc. We have reviewed the invoice and recommend payment in the amount of $109,139.53 be placed in line for payment. This amount includes the work performed within the period ending March 31, 2013. Should you have questions or need additional information, please call. Sincerely, Tim Vanderwalker, PE, Tetra Tech Cc: Michael Bomar, PE, Tetra Tech Fred Cook, PE, City of Crestview Tetra Tech, Inc. 12815 Emerald Coast Parkway, Suite 110, Destin, FL 32550 850.837.9278 Fax 850.837.7269 www.tetratech.com P:\2011\Crestview Well and Tank\Construction\Review-Approval \PayApps\Part I\Part I Pay App No. 13 - Recommendation.docx. April 4, 2014 Tetra Tech 12815 Emerald Coast Pkwy, Suite 110 Destin, FL 32550 Attention: Tim Vanderwalker Dear Tim, 0o a ❑00 000 ❑00 ❑00 000 ❑OOOOO_ 000 00a00000 SCONSTRUCTION INC. CGC-062489 PEEGLE Re: Crestview Well No. 9 Pay Application 1002-13 through March 31, 2014 Included with this letter are the following documents for your use and review: • Application for Payment 1002-013 for work completed through March 31, 2014 with updated schedule of values. • Executed Contractor's Certification. • Updated Construction Schedule dated April 4, 2014. • Current Change Order Log. • Progress photos. Reimbursement in this pay application reflects the following activities: • Supervision. • Delivery of majority of originally scheduled rip rap. • Completion of the asphalt/gravel base course (test report attached). • Delivery of (3) wheel stops. • Building insulation, complete. • Completion of painting work associated with the building and DIP. • Completion of painting of the elevated storage tank. • Completion of plumbing system. • Completion of the well pump. • Completion of the chemical feed (chlorine) system. • Completion of the elevated storage tank (e.g. cathodic protection, lightning protection and FAA light). • Completion of electrical work. • Completion of the tank level controls. • Work associated with Change Order No. 9-Underground Discharge Line. We expect that work during the month of April 2014 will include the installation of the chain link fence, landscaping and sod, asphalt, additional rip rap associated with Change Order No. 10 and moving towards final closeout of the project. If you have any questions or concerns, please let me know. Sincerely, Dan Carruth Project Manager Speegle Construction, Inc. General Contracting PO Box 1325 Niceville, FL 32588-1325 Site Work APPLICATION AND CERTIFICATE FOR PAYMENT FORM Application No.: 13 Progress X Final Engineer's Project No.: 200-08540-12001 Project: City of Crestview, Florida City of Crestview Well No. 9 and Elevated Storage Tank Contractor: Speegle Construction, Inc. NTP Date: February 26, 2013 Contract for: Crestview Well No. 9 Application Date: April 4, 2014 For Period Ending: March 31, 2014 Change Order Summary Change Orders Approved in ADDITIONS DEDUCTIONS previous months by OWNER TOTAL Approved this month Number Date Approved 1 04/30/13 $ - $ (4,275.00) 2 06/25/13 $ - $ (4,112.00) 3 07/22/13 $ - $ (5,848.00) 4 09/23/13 $ 20,893 $ - 5 09/10/13 $ 108,214 $ - 6 10/29/13 $ (66,674.00) 7 12/03/13 $ 6,298 $ - 8 02/26/14 $ 6,599 $ - 9 03/24/ 14 $ 5,106 TOTALS $ 147,110 $(80,909.00) Net Change by Change Orders 1 2 3 4 5 6 7 8 9 ORIGINAL CONTRACT SUM Net Change by Change Order CONTRACT SUM TO DATE (Line l and 2) TOTAL COMPLETED AND STORED TO DATE RETAINAGE: (Column I & N, Forms 00845 and 00846) a. 0% of Completed Work After 50% Complete $ - b. 10% Retainage on 1st 50% (Approx.) of Project $ 116,605.11 Total Retainage (Line 5a and 5b) $ 116,605.11 TOTAL EARNED LESS RETAINAGE (Lure 41ess Line 5 Total) $ 1,878,307.89 LESS PREVIOUS CERTIFICATES FOR PAYMENT (Line 6 from prior Certificate) $ 1,769,168.36 AMOUNT DUE THIS APPLICATION $ 109,139.53 BALANCE TO FINISH, PLUS RETAINAGE $ 153,553.11 (Line 3 less Line 6) $ 1,965,660.00 ✓ / $ 66,201.00 $ 2,031,861.00 ✓ $ 1,994,913.00 Contractor's Certification The undersigned Contractor hereby swears under penalty of perjury that (1) all previous progress payments received from the Owner on account of Work performed under the contract referred to above have been applied by the undersigned to discharge in full all obligations of the undersigned incurred in connection with Work covered by prior Applications for Payment numbered 1 through 12 inclusive; and (2) all materials and equipment incorporated in said Project or otherwise listed in or covered by this Application for Payment are free and clear of all liens, claims, security interest and encumbrances; (3) all Work covered by this Application for Payment is in accordance with the Contract Documents and not defective as that term is defined in the Contract Documents. Dated March , 2014 Speegle Construction (Contractor) By: Daniel Canrttth (Name) Project Manager (Title) COUNTY OF C%✓, tom` STATE OF f LoetbA Before me on this 4114 day of APtZIL , 20)__ personally appeared 'DAN A129-kr14' , known to me, who being duly sworn, deposes and says that (s)he is the ` olt-ar .1.41A,A6761-- of the Contractor above mentioned; that(s) he executed the above Application for Payment and statement behalfpf said Contractor; and that all of the statements contained therein are true, correct and niplete. 441 NOTARY PUBLIC BrAOA� • Engin JOHN KYSEL COMMISSIONS EE876208 EXPIRES Feb.19, 2017 COWANY BONDED THROUGH • on My Commission Expires 2- h qNotary }iu fic // (l' Payment of the above AMOUNT DUE THIS APPLICATION is recommended. thorized Signature) MAD/slm/specs/s-1 /00844 Tt#200-08540-12001 Date: 4/ ! �� 00844-2 050412 Owner's Approval By: —� oe-di eta c� (Title) Acct. No. Date: 2s)�y END OF SECTION MAD/slm/specs/s-1 /00844 Tt#200-08540-12001 00844-3 050412 Schedule of Values Pay Es imate No.: 13 Pr. ect: Cs • of Cresh izw Weil No. 9 and El rated Storage Tank I For Period Fading: 3/31/20 W Prepared In Dan Carmth 1 A D C D E F O H t ITEM DESCRIPTION OF WORK Bid Una Bid C Complete Waco( Qe°61 L.1:0�' ^� Amount Iltrou i kerns Iaa Period This Period Completed Quoddy Pxcem Quantity Pared This Period General Cand(tions Moblkallon Deniotali anion Mobilization, Setup Jobsne and Trailer 1 LS S 14,O130.00 f 34,00O.00 S 34,000 100% T 34,000 100% S - Sn•ision S 35,000.00 L 35,000.00 S 33,950 97% S 35,000 100% t IOw.00 =- - General ' s uirements I 1S f 19 500.00 S 19,500.00 S 19,500 100% S 19 500 100% f - Indemnification 1 LS f 1,000.00 f I,000.00 S 1.000 100% f 1,000 S - Maintenance of Traffic EN f 3,OOO.00 S 3,000.00 f 2,940 98% f 2,940 98% S - 5 Locate Utilities m Advance of Construction r S 1,7WW . S 1,700.00 S 1,700 100% t 1,700 WO% f - I 9 .- 6 Surface Cosine 21-inch black steel Installed 200 LF f 197.95 S 39,500.00 S 39,500 I00% f 39,300 i - Final Well Casing (18-inch, black steel), Installed (Final Qty of 500 LF) el S 149.10 f 59,920.00 S 74,900 125% S 74,900 125% f - Cement Grout, Installed (Final Qty of 18 CY) S 428.00 T 23,112.00 S 7,704 33% S 7,704 t 0.00 9 Pilot Hole Drilling (6-inch) S 42.80 S 34,240.00 S 34,240 100% S 34,240 i r f - 1 to Open Hole Drilling (18-inch) (Final Qty of 300 LF) f 48.15 S 20,223.O0 f 14,445 71% t 14,415 S (0.00) Geophysical Logging (Pilot) LS $ 5,3w.W S S,Sw.W S 33w 100% S 5.3w 100% S - Video Logging (Pilot)1 LS f 2,675.W S 2,675.W S 2,673 100% S 2,673 I00% S - Install and Remove Discharge Pigand Appurtenances LS f 2,675.W S 2,673.W S 2.675 10W/. f 2.673 100%f - Well Devel0imen 1 IS S iD 7W.W t 107W.W S 107W 100% S 10,700 IOOA f - 15 Step Drmvdmm Test f 2,675.00 S 2.675.00 S 2,675 100% S 2,675 f - �M 16 Geophysical Logging (Final) LS f 3,350.00 S 5,150.00 S 5,330 100./e S 5,350 100% t - Video Logging (Final) 1 LS S 2,673.W T 2,673.W S 2,675 100%S 2,673 100%S - i& Ca 'Iv Tat INS IOtS t 2.568.W S 2,368 100% f 2,36E S - _ 19 Well Disinfection 1 LS T 1,605.0O S I,605.00 t 1,605 IOW/. S 1,605 IOOY. S - Plumbness end Alignment Test t l,Sao.W t l,280.W T 4,280 100°/. f 4,280 IOOX S - Well Flange Ca. S 2,IJI1.W S 2,IlU.W f 2,I10 IOU°/. S 2,IJU 100% S - All work, equipment, and materials not included above to complete the General Requirements and Potable Supply Well No. 9 (Bid Items 1-21), in accordance with the Contract Documents 1 S 83,593.00 S 83,393.00 t a3,393 I O% f 83,593 100% S 23 Site Work _ Chain Link Fence S IO,SW.W t IO,SW.W f VA VA f• 0% S - Clear RGrub, Grade Site, Fill/Import, Cut/Balance, Export LS S 37,IW.W S 37,IW.W S 37,IW 100% S 77,IW IOOX t - Elli�fical Pipe and Rip Rapes Ditch LS f 7,SOO.W S 7,3W.W S G,7w 90X S 7,123 93•/. S 373.W Base Material ,r?, Gravel Parking and Asphalt LS f a,501.W S a,50r.W f 6,378 75% S a,3oJ 100% f 2,126.W Asphalt and Wheel Stops I.S f I,SIIO.W S 1,3W.W f - 0% S 223 5Y. f 223.W Gravid Parkin LS f I,SW.W f 1,S110.W S - 0% f - W/. f - Landscaping $ 6,SW.W f 6.w0.W S - 0% S - 0% S - Bollards S 1,SOO.W S I.500.W f 1.5W 100Y. S 1,500 100% S - Silt Fence f I,w0.W f I,SOO.W t 1,5W f 1,500 ItBYS: f - 11 .1 Y Yard Pipit' f 37,O00.00 WW S J7,O. t 37,O00 100%W X S 370 100%f ---= Pump CAenNrn! Building _= Concrete Foundation/Slab 1 S 13,209.W f 13,209.W S 15,209 IOOK f 15,209 100% f - Mason 1 S 12,J1k0.W S 12,500.W f IS,J00 100% f I2,SW ZOOS: f - Wood Framing, Soffit Fascia 1 f l,8W.W S I,aW.W t 1,8W IOU% f J,BW IOOK f - FoaminsulalioninWalls 1 $ 6W.W S 6W.W f - 0% f 6W I00% S 6W.W Foam Insulation at Roof 1 f I6W.W S 1,6W.W f - 0% f 1,6W 100% S I,6W.W Roof 1 LS f 6,l00.W f 6,SW.W f 6,SW 100% f 6,500 100% f - FRP Doors k Frames and Glazing 1 LS f 10,730.00 S 10,7w.W f 10,7w 100% t lU,7w 100X T - Paint IS t i000.W S S,000,W S 5�W 65X S 000 100% S 2,aW.W Plumb_Og LS I I3,2w.W f 11,2w.W f 11,263 aSX T 13,2w 100% f 1987.50 NVAC LS t 7,WO.W S 7,OW.W S 7,OW 100% T 7W0 100% f - 26 IVe!/Pnrnr _ Well Pump I LS f 80,250.00 S 80,230.00 S 77843 97% t 110,250 S 2,407.30 DIP Inside Bldg 1 !S f 20,750.00 f 20.730.00 S 20.750 IW'h S 20.750 100% f - A B C U E F O li 1 ITEM DESCRIPTION OF WORK Bid Unit Bid Complete Complete Value of NO. Panty units Rae Amount Thrnunh Though Fenn . Lai Period This Period Cmpksed Quantity Pement Qmnliw• Perot Tins Period 27 Chemical Feed Systems I LS S 24.600.00 S 24,600.00 S - 0% S 24,600 100% S 24,600 00 28 _ Elevated (pater Storage Tank Elevated %Water Storage Tank System 1 LS S 1,090,300.00 S 1,090,300.00 S 1,057,591 97% S 1,090300 100% S 32,709.00 Lightning Protection System, FAA Light 1 LS $ 12,674.00 S 12,67J 00 S 6,451 51% S 12,040 95% S 5,589.23 29 Generator and Fuel Stony e 1 LS S 70,035.00 S 70,035.00 S 68,634 98% S 70,035 100'A S 1.400.70 30 Electrical, Security, Instrumentation, Controls, and Telemetry Systems 1 LS If 52,257.00 $ 52,257.00 $ 4I,106 80% S 52,257 100% $ 10,451.40 31 All work, equipment and materials not Included above to complete Other (pork Bid Items 23-30, In accordance with the Contract DOCIIMOVS Submittals 1 LS S 16,500.00 S 16,500.00 S 16,170 98% S 16,335 99% S 165.00 Closeout Documentation 1 LS S 2,500,00 $ 2,500.00 S - 0% S - 0% S - 32 SCADA Service Coordination Allowance 1 1S S 2,000.00 S 2,000.00 S 575 29% S 575 29% S - CHANGE ORDERS No. 1 - FDEP Electrical Recisions; Lover Inlet Pipe in Riser 1 LS $ (4,275.00) S (4.275.00) S (2,138) 50.4 S (4,275) 100 S (2,137.50) No. 2- Reconfigure Inlet/Outlet Piping 1 LS S (4,112.003 S (4,112.00) S (4,112) 100% S (4,112) 10Ct% S - No. 3 - Credit for Tank- Railing 1 LS S (5,1148.00) $ (5,848.00) S (5,848) 100% S (5,848) 100% S - No. i - Automatic Level Controls 1 LS S 20,293.00 $ 20,893.00 0% S 20,893 100% S 20,89100 No. 5 - Increase Surface Casing Depth 1 LS $ 108,214.00 S 108,214.00 S 108.214 100% S 108,214 100% S - No. 6 - Delete 200 LF of Surface Casing: Shot of Cement Slurry 1 IS S (66,674.00) S (66,674.00) S (06,674) 100% S (66.674) 100% S - No. 7- Stage Grouting 1 LS S 6,298.00 S 6,298.00 S 6,298 100% S 6,298 100% $ - No. 8 - Increase Pump Column Depth; Delete Tank Shrouding 1 LS $ 6,599.00 S 6,599.00 S 6,599 100% S 6,599 100% S - No. 9 - Underground Discharge Line I Is $ 5,106.00 S 5306.00 O% S 2,298 45% S 2.297.70 Totals s 2,031,1161.00 S 1,11e5,771 51,971,913.00 S 109,139.53 Crestview Well No. 9 Change Order Log Original Contract Amount March 31, 2014 $ 1,965,660 Approved Sent to Accepted Amount of Change COR Number Description Owner Y/N? Approval Date Request Amount Contract Amount Notes 1002-01 FDEP Electrical Changes; Lower Inlet Pipe 04/08/13 Y $ (4,275) $ (4,275) $ 1,961,385 1002-02 Yard Piping Revisions 05/06/13 Y 06/13/13 $ (4,112) $ (4,112) $ 1,957,273 1002-003 Tank Railing Credit 07/02/13 Y 07/22/13 $ (5,848) $ (5,848) $ 1,951,425 1002-004 Add Well Pump Automatic Controls 08/07/13 Y 09/23/13 $ 20,893 $ 20,893 $ 1,972,318 1002-005 Increase Well Surface Casing 08/23/13 Y 09/23/13 $ 108,214 $ 108,214 $ 2,080,532 1002-006 Delete 200' Surface Casing; Cement Slurry Shot 10/14/13 Y 10/29/13 $ (66,674) $ (66,674) $ 2,013,858 1002-007 Grout Casing in Multiple Stages 11/01/13 Y 12/03/13 $ 6,298 $ 6,298 $ 2,020,156 1002-008 Increase Pump Depth 12/23/13 Y 02/26/14 $ 6,599 $ 6,599 $ 2,026,755 1002-009 Add Underground Discharge Line 03/17/14 Y 03/24/14 $ 5,106 $ 5,106 $ 2,031,861 Total $ 2,031,861 _1-11 L �. SPEEGLE PROJECT: CRESTVIEW WATER IMPROVMENTS WELL NO. 9 PROJECT NO. PROJECT SCHEDULE 1002 DATE:04/04/14 i ! escri 'tion t U /dric :: E i ": ........... Dec Dec Dec Dec Dec Jan Jan Jan Jan Feb Feb Feb Feb Mar Mar Mar Mar Mar Apr p Apr P Apr P Apr p May Y May Y 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 TANK PAINTING CONSTRUCT RETENTION POND BLDG PAD FRP PUMP HOUSE FOOTINGS FORM PUMP HOUSE S.O.G. PLUMBING/ ELECTRICAL U.G.R.I. PLACE S.O.G. MASONRY WALLS ELECTRICAL RI ROOF TRUSSES/ SOFFIT FRAMING ROOF SHEATHING/ METAL ROOF INSULATION YARD PIPING INSTALL DOORS AND FRAMES PRIME AND FIRST COAT WALLS INSTALL WELL PUMP MOTOR PUMP HOUSE PIPING HVAC SYSTEMS INSTALL CHLORINATION EQUIPMENT ELECTRICAL TRIM OUT PLUMBING TRIM OUT FINAL COAT WALLS/ PIPE/ FLOOR GENERATOR PAD ASPHALT WHEEL STOPS INSTALL FENCE AND GATE RIPRAP LANDSCAPE SET GENERATOR TESTING GC PUNCHLIST OWNER PUNCHLIST FINAL CLOSEOUT ear �o�� �. 5cneauie asea on matenals tieing reaaily avanaole trom suppliers 111.11=Work complete Work not yet complete 12/23/2013 Current Substantial Completion 1/22/2014 Current Final Completion 4/14/2014 Substantial Completion Date Thru Owner CO 9 5/14/2014 Final Completion Date Thru Owner CO 9 NOVA ENGINEERING ANC) ENVIRONMENTAL FIELD DENSITY TEST REPORT Project Name: Crestview Well No. 9 Report Date: 3/15/2014 Nuclear Density Gauge Info (If applicable): Make: CPN Model: MC-1 Serial Number. 8437 Daily Standard Counts: Density: 3425 Moisture: 5165 Remarks: 0 elevation= finished grade �'� Observations: 'ie Copies to: Project No.: 8113073 Client: Speegle Construction, Inc TEST INFORMATION Lab Proctor No FIELD TEST Required Compaction CA) Test Result No. Test Date Tech. Fill Type EIevJ Depth (ft.) Location Test Method Test Depth Om) Dry Density (pc0 Moisture (%) Compaction (%) 3 3/18/2014 K. Russell 4 0 Entrance Lane Center 4iLl b ct v-e4 IkeP-1 D2922-96e1 8 115.6 8.0 / 102 `�/ 95 �% Pass 4 3/18/2014 IC Russell 4 0 Parking Arca Center SLOG atVG�41e P-1 D2922-96e1 8 114.0 7.6 101 �/ 95 v Pass 5 3/182014 iC. Russell 4 0 Center of Entrance Lane bo, sc_ row C-1 D2922-96e1 6 135.1 5.2 99 / 98 ` Pass 6 3/18/2014 K. Russell 4 0 Center of Parking Area IQ exse_ e—catAL C-1 D2922-96e1 6 135.9 4.9 100 t/ i 98 ✓ Pass LABORATORY PROCTOR TEST REIERENCE Lab Proctor No. Test Method Mater ial Description Maximum Dry Density (pcf) Optimum Moisture (%) P-1 AASHTO T 180 Method A Modified Tan/brown SAND 112.8 8.4 C-1 AASHTO T 180 Method A Modified Crushed Concrete 136.2 6.7 This report is the property of NOVA Engineering and Enviromnental, LLC. Reproduction or reuse of this report without the express written approval of NOVA is prohibited 77te test results included herein are representative of the specifc location; depths and times at which the tests were conducted Conditions at other locations, depths and times may varyfrom those noted FILL TYPE 1. Structural Till 2. Utility Backfill 3. Mise Backfill 4. Finished Subgrade 5. Stone Base Course 6. Disc. Other