Route 9 Corridor Study
PARKVILLE + RIVERSIDE + MARC
MODOT + PLATTE COUNTY + PARK UNIVERSITY
ROUTE 9 CORRIDOR STUDY
2
ACKNOWLEDGEMENTS
We are grateful for the advisory contributions
from the Project Steering Committee. We espe-
cially appreciate the wonderful support from the
City of Parkville: Mayor Nan Johnston and City
Administrator Lauren Palmer, who helped facilitate
the study. The consulting team appreciates the
detailed input from interactions with local citizens at
public meetings and one-on-one meetings.
PROJECT PARTNERS
City of Parkville
City of Riverside
Missouri Department of Transportation
Platte County
Park University
CITY OFFICIALS
Honorable Nan Johnston
Alderman
Ward 1 - Diane Driver
Ward 2 - Kari Lamer
Ward 2 - Dave Rittman
Ward 2 - Jim Werner
Ward 3 - David Jones
Ward 3 - Douglas Wylie
Ward 4 - Greg Plumb
Ward 4 - Marc Sportsman
CITY STAFF
Lauren Palmer, City Administrator
Sean Ackerson, Assistant City Administrator/
Community Development Director
Tim Blakeslee, Assistant to City Administrator
MARC OFFICIALS
Stephen Lachky, AICP (MARC)
STEERING COMMITTEE
Voting Members:
Shelie Daniel (MoDOT)
Mike Duffy (Riverside)
Daniel Erickson (Platte County)
Nan Johnston (Parkville)
Laurie McCormack (Park University)
Advisory Members:
Susan Barry (MoDOT)
Ed Bradley (Main Street Parkville Association)
Daren Higerd (Parkville Area Chamber)
David Jones (Parkville EDC)
Dan Luebbert (Platte Co. Health Dept)
Alicia Stephens (Platte Co. EDC)
Matthew Van Hoesen (Park University)
Alternates:
Erik Bergrud (Park University)
Mike Kellam (Parkville EDC)
Beverlee Roper (Platte County)
Marsha Van Dever (Parkville Area Chamber)
CONSULTANT TEAM
Sabin Yanez, PE (CFS)
Project Manager/Principal in Charge
Rick Walker, PE (CFS)
Deputy Project Manager/Project Design Manager
Andrew Robertson, EI (CFS)
Richard Stegman (CFS)
Jim Schuessler, LEED AP (BNIM)
Streetscaping/Enhancement Design
Thomas Morefield (BNIM)
Public Engagement/Planning
Kimberly Pemberton, PE, ENV, SP (Trekk)
Tom Evans, PE, PTOE (Trekk)
Route 9 & Mattox Road Intersection Survey/Design
Craig Davis (MCD Associates)
Economic Analysis & Financing
3
ROUTE 9 CORRIDOR STUDY Table of Contents
SECTION 1: INTRODUCTION 5
SECTION 2: ANALYSIS 16
SECTION 3: DESIGN RECOMMENDATIONS 30
SECTION 4: PROJECT SEGMENTS 50
SECTION 5: PROJECT OUTCOMES 65
SECTION 6: IMPLEMENTATION STRATEGY 73
SECTION 7: APPENDICES 91
ROUTE 9 CORRIDOR STUDY
4
5
SECTION 1Introduction
The Mid-America Regional Council (MARC), with financial support from MoDOT, the City of Parkville, the City of Riverside, Platte
County, and Park University, sent out a request for a consultant team to analyze and make significant design improvements to
Route 9 from Mattox Road to Route 45. The selected consultant team was lead by CFS Engineers (civil engineering firm) and
included BNIM (architecture firm), Trekk Design Group (civil engineering firm), and MCD Associates (law firm). The team began
work on April 22nd, 2015 and completed their corridor study consisting of design and recommendations on January 16th, 2016.
Missouri Route 9 begins in downtown Kansas City at Interstate 35, crosses the Missouri River using the Heart of America Bridge,
follows along the river to downtown Parkville then heads north and ends at Interstate 29. Route 9 was established in 1922 under
the jurisdiction of the Missouri Department of Transportation (MoDOT).
The Missouri Route 9 Corridor Study is a continuation of the efforts of the City of Parkville to transform their community in a
visionary direction represented in Vision Downtown Parkville (2014) and Livable Communities Study (2013). The Route 9 corridor
is the “Main Street” of the downtown from a transportation standpoint, and it’s the City’s goal to re-create the corridor in a way
that it enhances all modes of transportation, including pedestrians, bicyclists and transit, while improving safety and mobility. The
stated purpose of the Route 9 Corridor Study was to go beyond planning and into preliminary design of future improvements
in which the City can plan and budget. The plans need to promote traffic safety, mitigate the growing congestion issues, include
complete street design elements, provide multimodal facilities, incorporate future land use goals, and enhance the local aesthetics.
The study condensed the 4-mile project into 12 prioritized project areas so sub-project costs and funding could be established.
The consultant team was provided with GIS Data, existing traffic data/studies, and existing plans for adjacent development.
The consultant subsequently performed a LiDAR survey on Route 9 from the Park University Entrance Drive to Route 45 and
at other major intersections along Route 9. Once the survey was scanned, the consultant created a CAD file base map from the
topographic information and merged the survey DTM with the GIS LiDAR DTM.
Once a typical cross-section of Route 9 was determined from three alternative designs, preliminary drawings were based on the
existing centerline and right-of-way boundaries. Based on one-on-one meetings with local business and property owners and two
public meetings, concerns of the locals were established and the design was altered to accommodate these challenges.
This report is the culmination of more than 25 one-on-one meetings with local property owners and stakeholders, six steering
committee meetings with input from civic organizations, several Board of Aldermen meetings, and two well attended public
meetings. The technical work was integrated with the values and concerns of the public to meet the goals for the project.
ROUTE 9 CORRIDOR STUDY
6
• Focus on making connections in all directions and at multiple
scales.
• Preserve and enhance the vitality of Downtown Parkville as the
economic and community center of the City.
• Respect the character of Parkville.
• Emphasize the long-term vitality of all proposed improvements
to the corridor.
• Minimize negative impacts on adjacent property owners.
• Appreciate the importance of parks and natural resources to
Parkville.
• Create and support opportunities for compatible economic
development.
• Balance the needs of commuters with local needs such as
pedestrian access, aesthetics, and convenient access to com-
mercial properties.
GUIDING PRINCIPLES
Vision Downtown Parkville, adopted in August 2014, prompted the Route 9 Corridor
Study to determine how best to improve highway safety and efficiently move traffic
while providing improved pedestrian access from 45 Highway to Downtown. The
Vision Downtown Parkville was developed with a tremendous amount of public
involvement and support from many of the same stakeholders, business leaders and
organizations involved in this study. It was clear these community leaders believed
the best chance for adoption of any future improvement plans needed to be built on
the vision already created.
THE THEME FOR THIS EFFORT IS:
“Preserving the character of Downtown, while capitalizing on opportunities to
enhance commerce, economic activity, and community interaction is critical to the
future success of Downtown Parkville.”
THIS IS ACCOMPLISHED BY:
7
• Mitigate safety and capacity issues, and minimize traffic
conflicts, on Route 9.
• Enhance aesthetics and pedestrian movements, particularly in
proximity to Downtown Parkville and Park University.
• Accommodate compatible new development and
redevelopment along the corridor.
• Reduce future construction costs by facilitating the reservation
of right-of-way for future improvements.
• Position the participating public entities to compete in future
transportation grant cycles for eligible improvements in the
corridor.
PROJECT GOALS
The goals and objectives established for the Missouri Route 9 Corridor Study were
developed with the Steering Committee at the Kick-off meeting, held on May 4,
2015. It was the direction of the steering committee to establish goals and objec-
tives that were specific and clear so as to guide the implementation of improve-
ments well into the future.
PREVIOUS STUDIES
The following pages outline the recommendations made from previous studies
in Parkville. The previous studies include the 2009 Master Plan, the Regional
Multimodal Access and Livable Community Study, and Vision Downtown Parkville.
The Vision Downtown Parkville outlines future land use, future sidewalks and trails,
and redevelopment scenarios of East Street.
ROUTE 9 CORRIDOR STUDY
8
KEY RECOMMENDATIONS
• Promote a built environment through building form, scale, placement and
architectural design to provide a sense of place and reinforce the street as
civic space.
• Provide a well-designed and interconnected mix of vibrant neighborhoods,
parks and green space, schools and civic institutions, businesses and
employment centers.
• Enhance the character downtown through its built environment, pedestrian
realm, streetscape, entrance gateways and intimate civic spaces.
• Strengthen the connectivity and relationship between downtown and
surrounding neighborhoods, educational institutions and riverfront park
spaces.
• Promote strategic residential development creating a critical mass for
downtown businesses.
• Promote strategic reinvestment.
• Provide a balanced interconnected street network that provides connectivity
between neighborhoods, provides multiple travel routes, reduces the number
and length of automobile trips and conserves energy through fewer and
shorter automobile trips.
• Provide alternative context-sensitive street design standards that respect
local topography, minimize the amount of impervious surfaces, conserve
open space and protect natural features and water quality.
• Provide convenient access to a framework of transportation alternatives,
including pedestrian and bicycle systems, public transit and multi-modal
transportation options that reduce dependence upon the automobile.
BUILDING ON THE 2009 MASTER PLAN
The 2009 Parkville Master Plan set the stage for improvements to the Route 9
Corridor, identifying focus areas for investment, outlining connectivity improve-
ments for all modes of transportation, and recommending detailed analysis for
Downtown, Route 9, and other strategic areas.
9
REGIONAL MULTIMODAL ACCESS
AND LIVABLE COMMUNITY STUDY
Completed in 2013, the Parkville Regional Multi-
Modal Access and Livable Community Study was
an effort to coordinate transportation and livability
improvements in a strategic way and to identify
solutions to traffic and other mobility challenges that
detract from the livability of Parkville. The multi-
modal study identified recent investments in parks,
trails, and Downtown Parkville and explored areas
of concern related to traffic congestion, safety, and
overall mobility.
The Community Study also identified the possibility of a poten-
tial squareabout to mitigate downtown congestion. Due to the
frequency of trains through downtown, adding a traffic signal at
the Route 9 / 1st Street / East Street intersection provided bet-
ter results for reducing travel times.
The Parkville Regional Multi-Modal Access and Livable
Community Study identified the intersection of Route 9 / 1st
Street / East Street at a location for a potential roundabout.
Peak Hour traffic demand exceeded the capacity of a round-
about upon further analysis.
In the development of a recommended roadway
design, the Route 9 Corridor study builds upon the
2013 multimodal study including its analysis of exist-
ing and historic traffic volumes, speed data, accident
data, and other information. Recommendations in
the multimodal study for trail opportunities, sidewalk
connections, community gateways, streetscape and
public space improvements, and railroad enhance-
ments also inform the ultimate design.
ROUTE 9 CORRIDOR STUDY
10
VISION DOWNTOWN PARKVILLE
In 2014 the city continued to refine its’ vision of what
their beautiful downtown could ultimately become.
The completion of Vision Downtown Parkville (VDP)
further set the stage and direction for the work of
the Route 9 Corridor study. The key points of VDP
are:
KEY RECOMMENDATIONS
• Expand the boundaries of the Downtown
commercial shopping district in a way that
complements the character and mix of uses that
already exist.
• Encourage the Downtown Commercial district
to provide a more balanced mix of services that
meet both the needs of the community and
out-of-town visitors.
• Improve connectivity by enhancing the pedes-
trian environment in Downtown Parkville.
• Preserve and protect vehicular flow in and
around Downtown.
• Prepare a Design Guideline that provides direc-
tion and guidance for the redevelopment of East
Street so that it fits with the desired Downtown
character.
• Evolve a streetscape redevelopment plan in the
commercial core of Downtown to address the
worn and tired existing streetscape.
“The preservation of the small town, historic
and charming character of Downtown, while
capitalizing on opportunities to enhance
commerce, economic activity, and community
interaction is critical to the future success of
Downtown Parkville.”
11
REDEVELOPMENT OF EAST STREET
Vision Downtown Parkville states that “the 9
Highway/East Street corridor, from 1st Street to
6th Street, represents an excellent redevelopment
opportunity that could serve as a catalyst for future
growth and investment in Downtown Parkville.
Given its significance within the transportation
network of Parkville, a reimagined East Street could
improve community connectivity, create additional
commercial critical mass by effectively doubling the
Downtown commercial area, and safely and ef-
ficiently move vehicular and pedestrian traffic, while
also helping 9 Highway fit better into the Downtown
character desired by the community.”
FUTURE LAND USE
Vision Downtown Parkville’s Future Land Use
strategy “identifies the recommended land use pat-
terns that should be used to guide future planning
decisions as they relate to development, redevelop-
ment and infill in the Downtown Parkville area.”
Because Route 9 passes through and connects the
Downtown Core, East Street redevelopment area,
residential transition areas, Park University, and
valued natural areas, it is critical to consider the op-
portunities and impacts of future roadway improve-
ments on the ultimate land use vision for Downtown
Parkville.
FUTURE SIDEWALKS AND TRAILS
Vision Downtown Parkville provides a number of
recommendations for sidewalk and trail improve-
ments for the Downtown area, including along Route
9. The recommended design for Route 9 incorpo-
rates these recommendations and others to create
a functional, inviting corridor for all users. Specific
recommendations of the Vision Downtown Parkville
plan include enhanced sidewalk and streetscape
connections along East Street, new sidewalks along
Route 9 to the north connecting Parkville Commons
and 45 highway, sidewalk connections on 6th street
and 12th Street, and potential improvements along
White Alloe Creek.
ROUTE 9 CORRIDOR STUDY
12
PROCESS
When analyzing the Route 9 corridor, the Project Team recognized characteristics that
varied through different sections of the 4-mile study area. In an effort to ensure the greatest
opportunity for acceptance of proposed improvements, the Project Team utilized a tailored
process which included numerous one-on-one meetings with property owners at the
beginning of work so that their ideas for the corridor could be included in the first concepts
developed. Also included in the project approach was the analysis of future development
along Route 9, its economic benefits and growth impacts for the area. Lastly, within the
project process was the creation of potential funding scenarios that might be utilized by the
City to pay for corridor improvements.
PROJECT SCHEDULE
PHASE MAY 2015 JUN 2015 JUL 2015 AUG 2015 SEP 2015 OCT 2015 NOV 2015 DEC 2015 JAN 2016
Data Collection
Stakeholder Meetings
Concept Development
Public Meeting #1
Preliminary Design
Public Meeting #2
Final Report
13
ENGAGEMENT
Project engagement began with the On-site Kick-off Meeting, Wednesday, April 22, 2015 from 1:30 – 2:30 p.m. at the Parkville City Hall. With two
public meetings, five steering committee meetings, and 17 one-on-one meetings, the consultant team was able to establish the needs for the project
and to efficiently work within project constraints. Included in the appendix are meeting minutes, results from public meetings, and notes taken from
one-on-one meetings.
PUBLIC MEETINGS
At the first public meeting, Wednesday, August 5, 2015 from 6:00 – 7:30 p.m. at the Parkville Presbyterian Church, several concept designs were
displayed on poster sized boards.The 65 registered attendees were given green dot stickers to indicate a preferred option and red dot stickers to
indicate an unwanted option. The attendees placed their stickers on the display board and the results were incorporated into the design.
At the second public meeting, Thursday, October 29, 2015 from 6:00 – 7:30 p.m at the Parkville Presbyterian Church, one preliminary design was
presented along with costs per the twelve project segments (see Section 4). The 37 registered attendees were given twelve marbles with each
marble representing a vote for a preferred option. The attendees dropped their marbles in any amount into twelve jars representing the project
segments. The preferences were then recorded and used as part of the segment rank prioritizing process.
Public meeting display boards were available on the City’s website for those who could not attend the public meetings and feedback from the
electronically submitted comments were incorporated into the design. Display boards, attendance lists, feedback voting graphs, and comments are
included in Appendix 6 - Meetings.
STEERING COMMITTEE
Steering committee meetings took place in the Parkville City Hall Board Room on five dif-
ferent dates: May 4, 2015; July 16, 2015; August 26, 2015; October 9, 2015; and December 16,
2015. The committee had five voting members which represented either MoDOT, Parkville,
Riverside, Park University, or Platte County Planning & Development, seven advisory
members, and two staff. The city was tasked with approving the guiding principles for the
project, identifying key property owners, identifying traffic and multi-modal needs, selecting
Complete Street options, selecting design alternatives or change in alignment, and approv-
ing project segmentation.
14
FACE-T0-FACE STAKEHOLDER MEETINGS
Key property owners were identified and scheduled for a face to face meeting. By present-
ing the property owners with preliminary design drawings, the constraints of the project
and the impact of the project to the adjacent property was discussed. By understanding
the current utility of the property and the owner’s future intent, design alternatives could be
narrowed down to the best choice for the property owner and the design of the roadway. In
total, the consultant met with 17 property owners.
BOARD OF ALDERMAN MEETINGS
Two meetings were held with the Parkville Board of Alderman during the Route 9 Corridor Study development. These meetings were held on
August 4, 2015 and October 20, 2015.
In the first meeting, the project team presented the initial findings within the review of corridor conditions, the concerns that exist to improving the
infrastructures, and some initial concepts that were going to be presented to the public.
The second meeting was necessary in order to share the potential improvements to Route 9 and the conceptual construction estimates. This meet-
ing was also utilized to gain leadership feedback as we prepareed for the second public meeting.
ROUTE 9 CORRIDOR STUDY
15
16
SECTION 2Analysis
There have been a number of studies done within the Route 9 corridor for the City of Parkville in the last ten years. These studies
were an excellent foundation for the Missouri Route 9 Corridor Study. The foundation for the study was based on the existing
traffic studies, land use analysis, conceptual development scenarios and site specific plans. A LiDAR survey, traffic analysis
at critical intersections, and local meetings with property owners supplemented the existing number of studies with a more
complete concept. From this information, the team developed the most accurate preliminary design of “Complete Street”
solutions.
ROUTE 9 CORRIDOR STUDY
17
EXISTING CONDITIONS
The design characteristics and functional role of Route 9 changed dramatically throughout the study area. The number of lanes, width of right-of-way, and proxim-
ity of adjacent development are all important factors informing recommendations for improvements.
1: NEAR CLARK AVENUE 2: WALNUT GROVE CEMETERY 3: OLD PARKVILLE CEMETERY
65’56’40’
1 2 3
4
N
18
4: NEAR 7TH STREET 5: NEAR 4TH STREET 6: NEAR 3RD STREET
42’42’39’
More than Two Lanes
Lanes Width of Right of Way
Enough (56’+)
Nearly (around 56’)
Lacking (56’-)
Two Lanes
Legend564
N
ROUTE 9 CORRIDOR STUDY
19
SITE CHALLENGES
1. DRAINAGE ISSUES
Today, most of Route 9 lacks curbs, which results in
stormwater runoff that flows from the road directly
onto adjacent properties. In some cases, this runoff
creates drainage issues for property owners and can
present a hazardous condition during winters.
2. TRAFFIC SIGNAL LOCATION
With commercial businesses, public facilities,
residential neighborhoods, and expanding
development all generating vehicle trips on
northern sections of Route 9, traffic volumes create
challenges at multiple intersections today in the
area of Parkville Commons. For example, it can
be difficult to make turns from side streets at peak
traffic times. As growth continues, these challenges,
delays, and conflicts will worsen.
3. UNCONTROLLED ACCESS
Several portions of Route 9 have open access
along the entire frontage, meaning that cars could
drive onto or off of Route 9 from any point along
the adjacent property. In one section of Route 9
between Clark Avenue and NW Lakeview Drive,
there is over 700 feet of uncontrolled access. This
condition impacts pedestrian safety and comfort,
and also increases the potential for traffic accidents
and conflicts.
In addition to the overall design and function of the roadway, there are a number of unique, site-specific design challenges that must be addressed in recommenda-
tions for the future design of Route 9. The project team identified the following site challenges through several sources including on-site survey and inspection,
other recent studies, and most importantly from the conversations with corridor stakeholders, property owners, and users of the corridor.
1
2 3
4
5
6
N
20
4. WALNUT GROVE CEMETERY
NEAR ROAD
Walnut Grove Cemetery is located close to the
existing Route 9 roadway, providing limited space
for additional infrastructure along the roadway.
5. MAIN STREET VISIBILITY &
TURNING
Today, Main Street intersects Route 9 at a shallow
angle, which makes it difficult to turn and difficult
to see approaching vehicles. Steep topography
and adjacent homes limit options for realigning the
roadway to intersect at a better angle.
More than Two Lanes
Lanes Width of Right of Way
Enough (56’+)
Nearly (around 56’)
Lacking (56’-)
Two Lanes
Legend
6
6. 12TH STREET VISIBILITY
The existing retaining wall on the northwest corner
of the intersection of Route 9 and 12th Street
creates visibility challenges for drivers on 12th Street
crossing or turning onto Route 9.
9
8
7
N
ROUTE 9 CORRIDOR STUDY
21
9. ACCESS TO ENGLISH LANDING PARK/TRAIL
The railroad and other barriers prevent a clear connection to English
Landing Park and the Missouri Riverfront Trail, which provides impor-
tant regional connectivity for pedestrians and cyclists.
SITE CHALLENGES
8. TRAFFIC BACKS UP AT 1ST STREET
The unusual configuration of the 1st Street intersection functions today,
but does result in traffic backups in multiple directions when traffic is
heavy. Downtown Parkville is a critical center of activity along Route
9, but the current configuration of the 1st Street intersection is not ideal
for drivers or pedestrians.
More than Two Lanes
Lanes Width of Right of Way
Enough (56’+)
Nearly (around 56’)
Lacking (56’-)
Two Lanes
Legend
6 9
8
7
7. NARROW ROADWAY WIDTH IN DOWNTOWN
Downtown Parkville is the location where pedestrian and bicycle activ-
ity is greatest, and where the existing roadway conditions are most
narrow. Within the constrained limits of Route 9 in the Downtown area,
improvements that support future development goals could be disrup-
tive to existing property owners.
N
22
TRAFFIC MODEL SUMMARY
Rush hour traffic conditions along Route 9 suggest a considerable amount of time is wasted due to congestion. To minimize the delays felt by mainline traffic
and traffic waiting to enter mainline traffic, traffic signals were evaluated at intersections with high volumes of vehicles. Intersections that met the signal warrants
established by the Manual of Uniform Traffic Control Devices (MUTCD) were then analyzed with Synchro software. Synchro provided results showing which alterna-
tive produced the fewest delay times. Based on eight different options to improve downtown traffic, the best result occurred when a signal with vehicle detection
was located at East Street & 1st Street. Locating a signal at East Street & 2nd Street or locating a roundabout east of East Street & 1st Street was not preferred when
presented at the first public meeting. When comparing Synchro results between the intersections of Route 9 & Lewis Street, Route 9 & 63rd Street, Route 9 & 62nd
Street, and Route 9 & Clark Avenue, a signal at Route 9 & Clark Avenue was the most beneficial.
• E 6th Street – Two-lane residential local road
Speed limit of 25 mph
• E 7th Street – Two-lane residential local road
Speed limit of 25 mph Road -Two-lane non-residential local road
Speed limit of 30 mph
• E 12th Street – Two-lane residential local road
Speed limit of 25 mph
• E 13th Street – One-lane residential local road
Speed limit of 25 mph
• Main Street – Two-lane residential local road
Speed limit of 25 mph
• NW Lakeview Drive – Two-lane non-residential local road
Speed limit of 25 mph
• Clark Avenue – Two-lane non-residential local road
Speed limit of 25 mph
• NW 62nd Street – Two-lane residential local road
Speed limit of 25 mph
• NW 63rd Street – Two-lane non-residential local road
Speed limit of 25 mph
• Lewis Street – Two-lane non-residential local road
Speed limit of 25 mph
• Route 45/Tom Watson Parkway
Speed limit of 45 mph (east of Route 9) and 35 mph
(west of Route 9)
The design for the Route 9 corridor did not include altering the existing
speed limit segments.
Area Street and Highway Network
The existing roadways around the proposed development include:
• Missouri Route 9/NW River Park Drive/East Street – Four-lane, divided major
freeway (west of Intercon Drive) and two-lane, undivided major arterial (east
of Intercon Drive
Speed limit of 55 mph (Mattox Road to Park University), 25 mph
(Park University Entrance Drive to 7th Street), 35 mph elsewhere
• Horizons Parkway – Four-lane, divided minor freeway
Speed limit of 45 mph
• Mattox Road – Two-lane non-residential local road
Speed limit of 30 mph
• Intercon Drive/Farm Road – Two-lane non-residential local road
Speed limit of 30 mph
• Riverchase Lane – Two-lane residential local road
Speed limit of 25 mph
• Coffey Road – Two-lane non-residential local road
Speed limit of 25 mph
• Park University Entrance Drive – Two-lane non-residential local road
Speed limit of 25 mph
• S East Street – Two-lane non-residential local road
Speed limit of 25 mph
• E 1st Street – Two-lane non-residential local road
Speed limit of 25 mph
• E 2nd Street – Two-lane non-residential local road
Speed limit of 25 mph
• E 3rd Street – Two-lane residential local road
Speed limit of 25 mph
• E 4th Street – Two-lane residential local road
Speed limit of 25 mph
• E 5th Street – Two-lane residential local road
Speed limit of 25 mph
ROUTE 9 CORRIDOR STUDY
23
Existing Traffic Volumes
Existing traffic volume counts were not recorded as part of this Route 9 Corridor Study. Existing traffic counts were provided from past traffic studies performed
in the area, Downtown Traffic Study in June 2010, the Parkville Commons Traffic Impact Study in January 2012, and the Parkville Apartments Traffic Impact Study
in March 2015. Using the provided turning movement volumes, Synchro was used to perform an analysis of the intersections of Route 9 & Mattox Road, 1st Street &
East Street, Route 9 & Clark Avenue, Route 9 & 62nd Street, Route 9 & 63rd Street, and Route 9 & Lewis Street.
Determining Future Growth Rate
The Average Annual Daily Traffic (AADT) along the portion of Route 9 was provided by Kansas City District Traffic Volume and Commercial Vehicle Count Map
published by MoDOT on an annual basis. A summary of the AADT for each year is provided in the following table:
MoDOT Average Annual Daily Traffic Volumes on Route 9
Year AADT
(vehicles/day near
Horizons Parkway)
AADT
(vehicles/day near Route 45)
2005 16,461 11,094 (including 660 Trucks)
2006 16,675 11,239 (including 783 Trucks)
2007 16,675 (same as 2006)11,239 (including 787 Trucks)
2008 16,752 11,244 (including 1,352 Trucks)
2009 16,211 10,881 (including 992 Trucks)
2010 16,373 10,990 (including 1,013 Trucks)
2011 13,821 10,550 (including 908 Trucks)
2012 14,644 10,717 (including 1,088 Trucks)
2013 14,025 10,696 (including 846) Trucks)
24
According to the traffic volume maps, the growth rate near Horizons Parkway between 2005 and 2013 was -15.0% or -2.0% per year. The growth rate near Route 45
between 2005 and 2013 was -3.6% or -0.5% per year.
The population in the City of Riverside was 3,077 according to the 2000 Census and was 2,937 according to the 2010 Census. This is a decrease of 4.5%. However,
the annually updated Population Estimates Program managed by U.S. Census Bureau showed that the City of Riverside population in 2013 was 3,046, an increase
of 3.7% from 2010 or 1.2% per year.
The population in the City of Parkville was 5,223 according to the 2000 Census and was 5,554 according to the 2010 Census which indicated an increase of 6.3% or
0.6% per year. However, the annually updated Population Estimates Program managed by U.S. Census Bureau showed that the City of Parkville population in 2013
was 5,928, an increase of 6.7% from 2010 or 2.2% per year.
The traffic growth rates were examined from the Downtown Traffic Study in June 2010, the Parkville Commons Traffic Impact Study in January 2012, and the
Parkville Apartments Traffic Impact Study in March 2015. In the “Future Traffic Volumes” of the Downtown Traffic Study, it states that “traffic should be expected to
grow by about 50% over the next 20 years.” In both the Parkville Commons and the Parkville Apartments studies, a 1% annual growth rate was applied.
Considering the traffic growth for 2040, the population growth, the previously used growth rates, and the available developable land, a 1.0% growth rate for 25
years was applied to the Synchro models for detailed analysis. The growth factor constant based on the 1.0% growth rate was determined as follows:
Growth Factor used in Synchro = (1 + Constant % Growth) ^ Projected Years
= (1 + 0.01) ^ 25
= 1.28, for 25 years growth at 1.0%
Explanation of Performance Measures
Two performance measures commonly used for Traffic Impact Studies are vehicle delay and level-of-service (LOS). Vehicle delay is the average delay, in seconds,
experienced by one vehicle passing through the intersection. The quality of traffic operation at an intersection is defined through level-of-service (LOS) which con-
sists of assignments of ‘A’ for free-flowing conditions through ‘F’ for congested conditions. The procedures and methodology for determining the LOS are outlined
in the Highway Capacity Manual (HCM 2010), produced by the Transportation Research Board. LOS ‘A’ through ‘C’ is considered acceptable.
ROUTE 9 CORRIDOR STUDY
25
ALTERNATIVE TRANSPORTATION MODE CHOICES
Pedestrian: There are several existing concrete sidewalk segments along Route 9 and the surrounding streets. From White Alloe Creek Trail to 6th Street, there is
sidewalk on both sides of Route 9. From 6th St to past Parkville Presbyterian Church, there is a sidewalk on the western side of Route 9. Some businesses to the
north on Route 9 have sidewalks adjacent to Route 9 including the YMCA, a Law Firm, Mosaic Life Care, Kwik Kar Wash & Detail, Sonic, Gomer’s, and Bank Liberty.
The proposed Route 9 design is planned to connect the Southern Platte Pass trail along Route 45 to English Landing Park by having a 5 ft sidewalk on the west side
and a 10 ft trail along the east side. The 10 ft trail design includes reopening the White Alloe Creek Trail through Park University campus, a new connection from Park
University to the White Alloe Creek Trail, an extension of the trail system within English Landing Park to the Missouri Riverfront Trail, a connection from the Missouri
Riverfront Trailhead parking facility to the sidewalks along Horizons Parkway, and a trail along the bluff on the northern side of Route 9 from Park University campus
to Horizons Parkway. Existing sidewalks that have adequate width, are ADA compliant, and do not interfere with the corridor design will remain in use; otherwise,
existing sidewalks will be removed and replaced. Several street crossings are planned at the following intersections:
• Route 9 & Horizons Parkway (with pedestrian signal) Crossing South and East sides
• 1st Street & East Street (with pedestrian signal) Crossing North, South, East, and West sides
• 1st Street & Main Street Crossing North, South, and East sides
• Route 9 & 6th Street (with pedestrian signal) Crossing North, South, East, and West sides
• Route 9 & 12th Street (with pedestrian signal) Crossing North, South, East, and West sides
• Route 9 & Lakeview Drive (with pedestrian signal) Crossing North, South, East, and West sides
• Route 9 & Clark Avenue (with pedestrian signal) Crossing North, South, East, and West sides
• Route 9 & Route 45 (with pedestrian signal) Crossing North, South, East, and West sides
Curb bulb outs are planned for the 1st Street & Main Street intersection to decrease the time it takes for pedestrian crossing to occur and to increase the visibility of
pedestrians. With a signal placed at 1st Street & East Street, the stop sign configuration was changed for 1st Street & Main Street. The stop sign for the westbound
traffic will be removed and replaced with a yield to pedestrian sign. Stop signs will be added to the northbound and southbound approaches to 1st Street & Main
Street which is a departure from the current configuration. Stopping the northbound and southbound will allow the heavy congested westbound movement priority
which means that traffic will not back up into the 1st Street & East Street intersection. The curb bulb outs will also allow the new stop signs to be placed closer to the
travel lane to improve visibility. The on-street parking spaces will be removed which do not meet the required spacing of 20 ft of clearance between a parking stall
and a crossing.
Bicycle: Currently there are no bike lanes or bike paths along Route 9. Due to size constraints and the preference of both the steering committee and the public
meeting attendees. Bike lanes were not included in the design of the corridor. It was important to separate casual bike traffic from the travel lanes due to the steep
topography of Route 9 and to maintain pedestrian walkability on both sides of Route 9, therefore a 10 ft shared-use path was included in the design. 10 ft is the
minimum width for a shared-use path. Commuter bikers will retain access to the 10 ft wide shoulder on either side of the east-west portion of Route 9.
On a supplemental note, for the portion of the trail connecting from the Missouri Riverfront Trailhead parking facility to the sidewalks along Horizons Parkway that
is along the top of the levee, the gravel size, consistency, and compaction needs to match the gravel of the English Landing Park trail system. “Sharrows”, which are
painted chevrons indicating shared-use of bicycle and motor vehicles within the roadway, were not included in the design’s pavement markings. Bike racks along the
north-south portion of Route 9 should be installed, and appropriate safeguards should be added to parked bicycles in order to increase ridership.
26
Transit Buses: Transit buses are not currently in service for Route 9. Adding transit service to Parkville and Riverside would be a benefit for Park University students,
Platte County Health Department patrons, the local population, and on festival days when a large influx of tourists make their way to Parkville. The locations for
future bus stops are determined by the population density, the employment density, activity centers like Downtown and Park University, and future land use. After
reviewing population data for the Parkville area, the key locations for potential bus stops are at Route 9 & 1st Street, Route 9 & 5th Street, Route 9 & 12th Street, and
a loop including Route 9, Clark Avenue, Lewis Street, and either 63rd Street or Route 45.
Bus stops could be designed to have turnouts which would keep travel lanes clear; however, bus turnouts may not be possible in locations with limited right-of-way,
topography constraints, or building constraints. Turnouts were not included in the design drawings.
Transit stops oriented near Route 9 & 1st Street and 6th Street would serve downtown
with the buffer/amenity zone designed to accommodate transit facilities such as benches,
shelters, signage, etc. The Route 9 & 6th Street stop would serve people attending
sports events at Park University. A downtown stop is constrained mostly by heavy AM
southbound traffic and the retaining wall. The only likely location for a southbound pull
out appears to be the parking area near 5th Street. Transit headed northbound could
make use of the on-street parking spaces as necessary. Another option for an additional or
alternative Downtown Stop is near the pedestrian entrance to Park University.
The transit stop at Route 9 & 12th Street would serve the Park University sporting events,
the Health Center, and the trailhead for the nature sanctuary. Of the several options for
a bus stop in this location, having a bus turnout south of the intersection would be ideal
while a turnout north of the intersection is constrained by the retaining wall to the west
and the proximity of the Health Center facility and steep topography to the east. The
existing parking layout and road conditions for making a bus route loop around 13th Street
and 12th Street would require significant infrastructure and site modifications and would
greatly increase the bus travel time. Although the Route 9 & 6th Street stop would be 1/4
mile away from the Route 9 & 12th Street stop, the clientele of the Health Center, a vast
portion consisting of mothers with toddlers, may not be able to easily walk this distance.
A loop including Route 9, Clark Avenue, Lewis Street, and either 63rd Street or Route 45
would put transit users closer to commercial destinations in this activity area. A bus stop
not directly on Route 9 would have ample room for cars to pass or for construction of a
bus turnout, and transit buses would not significantly impact Route 9 mainline travel time.
Bus Route Loop Including Route 9, Clark Avenue, Lewis Street
and either 63rd Street or Route 45
ROUTE 9 CORRIDOR STUDY
27
FLOODING INTERFERENCE WITH TRAFFIC
Due to the close proximity of Parkville and Riverside to the Missouri River, flooding occasionally occurs which make segments of the road impassible and can alter
traffic patterns as a result. The streams and creeks which connect to the Missouri River by passing under Route 9 include Burlington Creek and Burlington Creek
Tributary 2 which crosses under Route 9 at the NW Intercon Drive intersection and White Branch which crosses under Route 9 200 ft to the east of East Street &
1st Street. A small stream running parallel to Route 9 from about 400 ft to 1200 ft off of its western side runs from north of Clark Ave to the Missouri River but does
not interfere with Route 9.
A Flood Protection Study, December 2013, was performed for the City of Parkville which made recommendations for improving flood protection to downtown
and Route 9. For the downtown district, a 7-10 foot permanent concrete barrier wall was recommended in the location shown in Figure RS-1 Recommended
Flood Protection Technology Placement. For English Landing Park, setting aside funds to clean up after a flood event or construction of a 3-6 foot berm along the
Missouri River were recommended. These recommendations could be incorporated in tandem with other Route 9 improvements if desired.
Flooding limits were checked using three Federal Emergency Management Agency (FEMA) Flood Insurance Rate Maps each dated April 2, 2015. Light blue dots
denote the 100 year annual flood while black dots denote other flood areas like the 500 year annual flood or areas protected by a levee. The map, 29165C0383D,
showed Route 9 is in the 1% annual chance flood (essentially the water level increases to the height of a flood which would only occur every 100 years) from about
300 ft to the north of East Street & 1st Street and 450 ft to the east of East Street & 1st Street. The map, 29165C0391D, showed Route 9 is in the 1% annual chance
flood from about 2000 ft to the east of East St & 1st St and continues to the east. The map, 29165C0392D, showed Route 9 is in the 1% annual chance flood from
the western edge of the map to about 950 ft to the west of Route 9 & Intercon Drive and Route 9 is within the 500 year flood area from this point to the levee.
Although a significant portion of Route 9 near the river can be flooded, the Route 9 Corridor Study did not make any recommendations to eliminate the chance of
flooding along Route 9. The study is adding curb and gutter to improve the drainage along Route 9 but not for the road segment along the river because a simple
10 ft wide shoulder is needed for the 55 mph speed limit.
During a 100 year flood event, several business
would receive substantial flood damage and the
homes at Riverchase Lane would be temporarily
isolated. During this event, traffic could be detoured
to local roads like NW Crooked Road and connected
to highways like Route 45, Interstate 29, Interstate
635 to avoid the flooded segments. Since the
Average Annual Daily Traffic (AADT) on Route 9
along the river is 14,025 vehicles per day (From 2013
MoDOT Traffic Volume map), rerouting all of these
vehicles could cause higher demand on local streets;
however, since the AADT of I-29 is 75,789 vpd and
I-635 is 52,667 vpd, the excess demand on state
routes is comparatively small.
Figure RS-1 Recommended Flood Protection Technology Placement,
as shown in the Flood Protection Study, December 2013
28
Portion of FEMA FIRM 29165C0383D showing
Route 9 Flooding Area
Portion of FEMA FIRM 29165C0391D Showing Route 9 Flooding Area
Portion of FEMA FIRM 29165C0392D showing Route 9 Flooding Area
ROUTE 9 CORRIDOR STUDY
29
30
SECTION 3Design Recommendations
After review of all available existing reports, studies and data, meetings with individuals and organizations in Parkville, and extensive
on-site field analysis, the Project Team moved forward with development of multiple alternatives for complete streets typical
sections. These typical sections were also developed to deal with the unique challenges identified within the different sections of
the corridor. The Route 9 corridor has different characteristics throughout the 4-mile length. The section south of Missouri Route
45 functions more like an urban arterial, the downtown section has more of the feel of an urban “Main Street” and the eastern
section operates like an expressway. The design recommendations integrated these functions into the analysis thus creating twelve
individual sections, or projects that the community can begin to focus on as the begin the transform the Route 9 corridor to meet
the goals and objectives of this study.
ROUTE 9 CORRIDOR STUDY
31
GENERAL DESIGN
RECOMMENDATIONS
The goals of the Route 9 Corridor Study include
addressing capacity and traffic flow issues. At the
same time, improvements are intended to enhance
aesthetics and accommodations for pedestrians and
cyclsits. All of these needs must be met within a
constrained road right-of-way.
Based on an analysis of the various benefits and
tradeoffs provided, as well as the preferences
identified at the first public meeting, the project
team recommends a roadway configuration that
includes a sidewalk on the west side of the street
and a ten foot wide multi-use path on the east. In
some locations three lanes are recommended, while
two lanes are proposed for locations with fewer turn
movements.
57’
3 LANES, SHARED MULTI-USE PATH & SIDEWALK
2 LANES, SHARED MULTI-USE PATH & SIDEWALK
47’
32
LOOKING NORTH NEAR CLARK AVENUE - EXISTING CONDITIONS
LOOKING NORTH NEAR CLARK AVENUE - POTENTIAL IMPROVEMENTS
ROUTE 9 CORRIDOR STUDY
33
SITE SPECIFIC DESIGN
RECOMMENDATIONS
The following recommendations respond to the
unique, site-specific issues identified along the Route
9 corridor. In some cases, these recommenda-
tions represent adaptations of the overall roadway
design. In other cases, these recommendations are
additional considerations or project elements that
are essential for the project to achieve its goals of
enhanced connectivity and livability. Throughout
the Route 9 Corridor Study process, the project
team met with property owners along the length of
the corridor to identify and resolve various design
challenges. The recommendations in the following
section represent the outcomes of those conversa-
tions as well as community feedback during public
meetings.
CHALLENGE: DRAINAGE ISSUES
Today, most of Route 9 lacks curbs, which results in
stormwater runoff that flows from the road directly
onto adjacent properties. In some cases, this runoff
creates drainage issues for property owners.
RECOMMENDATION: CAPTURE
RUNOFF
The proposed design of Route 9 will include curbs,
drains, bioswales, and other stormwater infrastruc-
ture along its entire length, ensuring that stormwater
is captured, treated, and conveyed without negative
impacts to adjacent properties. These improve-
ments should virtually eliminate drainage issues
related to runoff from Route 9.
Existing Condition:
Curbless Roadway
Proposed Design:
Curbed Roadway
Swaled Edge
Sloped Hillside
Traditional
Storm Sewer
To Creek
or River
Green Solution
Bioretention Prefilter
Prior to Storm Sewer
34
CHALLENGE: TRAFFIC SIGNAL
LOCATION
With commercial businesses, public facilities, resi-
dential neighborhoods, and expanding development
all generating vehicle trips on northern sections of
Route 9, traffic volumes create challenges at multiple
intersections today in the area of Parkville Commons.
For example, it can be difficult to make turns from
side streets at peak traffic times. As growth con-
tinues, these challenges, delays, and conflicts will
worsen.
RECOMMENDATION: PROVIDE NEW
SIGNAL AT CLARK AVENUE
The project team analyzed traffic volume data and
crash data for four intersections to explore the
viability of a new traffic signal. A new signal at Clark
Avenue is warranted based on future traffic volumes
and also the preferred location based on feedback
at the first public meeting. The recommended
design includes a street stub for future connection
to the east to serve future potential development or
if a connection to 62nd street becomes desirable.
Traffic calming measures along 63rd street can help
to guide traffic through Parkville Commons to the
new signal and reduce traffic speeds within the retail
area.
Lewis Street
• Future traffic warrants signal
• Spacing too close to Route 45
SIGNAL OPTIONS
63rd Street
• Future traffic warrants signal
• Connects to many businesses and
houses
62rd Street
• Not warranted for signal
• Only connection for 69 houses
Clark Avenue
• Future traffic warrants signal
• Connects to many businesses and
houses
ROUTE 9 CORRIDOR STUDY
35
SITE SPECIFIC DESIGN
RECOMMENDATIONS
CHALLENGE: UNCONTROLLED
ACCESS
Several portions of Route 9 have open access
along the entire frontage, meaning that cars could
drive onto or off of Route 9 from any point along
the adjacent property. In one section of Route 9
between Clark Avenue and NW Lakeview Drive,
there is over 700 feet of uncontrolled access. This
condition impacts pedestrian safety and comfort,
and also increases the potential for traffic accidents
and conflicts.
RECOMMENDATION: FOCUS
ACCESS ON EXISTING DRIVEWAYS
The recommended design for Route 9 focuses
access on existing driveways. This configuration is
simpler for pedestrians and clearer for motorists.
The recommended design preserves all existing
driveways and most existing parking. The project
team has worked with adjacent property owners to
identify design solutions that improve Route 9 while
maintaining the function of adjacent properties. The
recommended design reflects the outcomes of those
conversations.
CHALLENGE: WALNUT GROVE
CEMETERY IS CLOSE TO THE ROAD
Walnut Grove Cemetery is located close to the
existing Route 9 roadway, providing limited space
for additional infrastructure along the roadway.
RECOMMENDATION: NO IMPACT
ON WALNUT GROVE CEMETERY
The recommended design for Route 9 fits within
the existing right-of-way adjacent to Walnut Grove
Cemetery. All proposed improvements will be
located outside of the line of the existing retaining
wall, and there will be no impacts on the adjacent
cemetery.
CHALLENGE: MAIN STREET
INTERSECTION VISIBILITY AND
TURN MOVEMENTS
Today, Main Street intersects Route 9 at a shallow
angle, which makes it difficult to turn and difficult
to see approaching vehicles. Steep topography
and adjacent homes limit options for realigning the
roadway to intersect at a better angle.
RECOMMENDATION: MODIFY
EXISTING MAIN STREET
INTERSECTION
The recommended design for Route 9 modifies the
Main Street intersection through paint, curbs, and a
slightly straightened approach to improve visibility
and make it simpler to navigate the intersection.
These improvements are located within existing
right-of-way. In the future, a reconfiguration of Main
Street is possible that would align Main Street paral-
lel to Route 9 until intersecting with new develop-
ment further north. In this future configuration, Main
Street could route south of Parkville Cemetery and
connect to a new intersection at Lakeview Drive.
This long term solution would require additional
grading work and some property acquisition.
36
CHALLENGE: 12TH STREET
INTERSECTION VISIBILITY
The existing retaining wall on the northwest corner
of the intersection of Route 9 and 12th Street creates
visibility challenges for drivers on 12th Street cross-
ing or turning onto Route 9.
CHALLENGE: 12TH STREET
INTERSECTION VISIBILITY
Rebuilding the existing retaining wall to improve
visibility around the corner addresses the safety
challenges at this intersection without requiring a
realignment of the roadway.
CHALLENGE: NARROW ROADWAY
WIDTH IN DOWNTOWN
Downtown Parkville is the location where pedestrian
and bicycle activity is greatest, and where the exist-
ing roadway conditions are most narrow. Within
the constrained limits of Route 9 in the Downtown
area, improvements that support future develop-
ment goals could be disruptive to existing property
owners.
RECOMMENDATION: NEW
FEATURES WITHIN EXISTING
CONSTRAINTS
The project team recommends a design for Route
9 in the Downtown area that achieves long term
project goals to improve traffic flow, pedestrian and
bicycle amenities, and future development potential
while minimizing impacts on existing properties. The
recommended design incorporates a new signal at
1st Street, and turn lanes at 2nd, 5th, and 6th Streets
to significantly improve the flow of traffic through
the area. By maintaining two lanes between 2nd and
5th Street, the design is able to incorporate a new
sidewalk and multi-use pathway with minimal impact
to adjacent properties. The proposed design also
includes improvements to White Aloe Creek Trail.
ROUTE 9 CORRIDOR STUDY
37
SITE SPECIFIC DESIGN
RECOMMENDATIONS
LOOKING NORTH AT 2ND STREET - POTENTIAL IMPROVEMENTS
LOOKING NORTH AT 2ND STREET - EXISTING CONDITIONS
38
LOOKING SOUTH AT 5TH STREET - EXISTING CONDITIONS
LOOKING SOUTH AT 5TH STREET - POTENTIAL IMPROVEMENTS
ROUTE 9 CORRIDOR STUDY
39
SITE SPECIFIC DESIGN
RECOMMENDATIONS
CHALLENGE: TRAFFIC BACKS UP
AT 1ST STREET AT PEAK TIMES
The unusual configuration of the 1st Street inter-
section functions today, but does result in traffic
backups in multiple directions when traffic is heavy.
Downtown Parkville is a critical center of activity
along Route 9, but the current configuration of
the 1st Street intersection is not ideal for drivers or
pedestrians.
RECOMMENDATION: NEW SIGNAL
AT 1ST STREET
The project team conducted travel time analysis
of several intersection options for Route 9 in
Downtown Parkville based on 2010 and forecast
2035 conditions. A new signal at 1st street is recom-
mended based on the anticipated travel time savings
in both the AM and PM peak travel times today and
in the future. A signal at East Street and 1st Street is
also the preferred configuration based on feedback
at the first public meeting.
3
1
2
A new signal at 1st Street would function best
in coordination with other improvements.
The proposed design would include separate
lanes for westbound and northbound traffic
as far east as Coffey Road. Northbound traffic
approaching from the east would continue to
move freely through the intersection without
having to stop. Two left turn lanes would
be provided for southbound traffic. At the
intersection of 1st and Main Streets, stop signs
would be modified to give traffic on 1st Street
priority movement.
Time Savings
A.M. (2010)- 1.2 min
A.M. (2035)- 5.2 min
P.M. (2010)- 0.5 min
P.M. (2035)- 2.3 min
TRAVEL SAVINGS WITH 1ST
STREET TRAFFIC SIGNAL
40
CHALLENGE: ACCESS TO ENGLISH
LANDING PARK & EXISTING TRAIL
The railroad and other barriers prevent a clear
connection to English Landing Park and the Missouri
Riverfront Trail, which provides important regional
connectivity for pedestrians and cyclists.
RECOMMENDATION: CONNECTION
THROUGH NEW 1ST STREET
INTERSECTION
The project team explored several options for at-
grade crossings and pedestrian bridges to connect
pedestrian and bicycle facilities along Route 9 to
the Missouri Riverfront Trail. Because it is a lower-
cost option, and because it directs activity through
Downtown Parkville, the project team recommends
at-grade connections through a new intersection
at 1st Street. This recommendation also reflects
feedback provided at the first public meeting.
Rout
e
9
Ro
u
t
e
9
1 st Street
Ea
s
t
S
t
r
e
e
t
McAfee
S
t
r
e
e
t
Missour
i
R
i
v
e
r
f
r
o
n
t
T
r
a
i
l
Ma
i
n
S
t
r
e
e
t
Pe
d
e
s
t
r
i
a
n
B
r
i
d
g
e
Pe
d
e
s
t
r
i
a
n
B
r
i
d
g
e
1
2
3
4
Existing Trail
Option 1 (At Grade)
Option 2 (At Grade)
Option 3 (Elevated)
Option 4 (Elevated)
LEGEND
ROUTE 9 CORRIDOR STUDY
41
SITE SPECIFIC DESIGN
RECOMMENDATIONS
TRAIL CONNECTIONS TO RIVERSIDE AND BEYOND
Regional connectivity is critical to the success of trail infrastructure. Connecting these two segments
of the Missouri Riverfront Trail will help implement the regional MetroGreen plan, which will ultimately
connect the Parkville and Riverside trails to Downtown Kansas City and other Northland trails, such
as the Line Creek Trail or the planned Vivion Road Trail. Negotiations to obtain trail easements are
currently underway, which will help advance this trail connection.
42
CHALLENGE: CONGESTION RELIEF AT COFFEY ROAD
The main challenge at Route 9 & Coffey Road was to relieve delays caused by mainline traffic turning onto Coffey Road or the nearby businesses parking area.
RECOMMENDATION: COFFEY ROAD TURN LANES
Turning lanes are planned for Route 9 at Coffey Road and for Route 9 at the parking access point to the east of Coffey Road. At Coffey Road, the eastbound traffic
will have at minimum a 190 ft left-turn bay and a 90 ft taper. While the minimum taper length for 55 mph is 180 ft, the 90 ft taper would not interfere with the access
drive to the west for the Missouri River Boating Association. Westbound traffic will have a 215 ft right-turn bay which will continue past the parking access point for
208 ft and include a 180 ft taper. A center turn lane is planned for Route 9 from Coffey Road to past Riverchase Lane. Riverchase Lane is not planned to have a right-
turn lane installed due to right-of-way restrictions but the planned 180 ft taper for westbound Route 9 right-turning traffic will help relieve the congestion at this site.
CHALLENGE: VEHICLE DELAY AT MATTOX ROAD
The main challenge at Route 9 & Mattox Road was to relieve delays and increase safety for traffic
entering mainline traffic.
RECOMMENDATION: NEW SIGNAL AT MATTOX ROAD
A detailed survey and study was performed by Trekk Design Group, LLC for the intersection of
Route 9 & Mattox Road. See Appendix for “Route 9 at Mattox Intersection Study.” Based on the
Manual on Uniform Traffic Control Devices (MUTCD), a signal is warranted to be installed as well
as a new eastbound right-turn bay with a length of 188 ft plus a taper of 180 ft. The distance from
the proposed signal meets the required spacing between intersections with signalization since
Horizons Parkway is 2,125 ft away and the minimum distance required is 1,320 ft.
ROUTE 9 CORRIDOR STUDY
43
A: ROADWAY ALTERNATIVES & RECOMMENDATIONS
LANE WIDTH
• Should be 11 ft wide on either side with a 10 ft wide two-way left-turn lane (TWLTL)
• Exceptions:
• Travel lanes should match existing from Route 45 to Sta. 1485+33 with left turn lanes 11 ft wide at Route 9 & Route 45
• Travel lanes should be 10 ft wide from 1548+00 to 1555+50
• Southbound left turn lane at East Street & 1st Street should be 11 ft wide
• Eastbound left turn lane at Route 9 & Park University Entrance Drive should be 11 ft wide
• All lanes should be 12 ft wide from 1569+00 to past Mattox Road
• Side street lane width should be 11 ft wide or match existing
SPEED
• Route 45 to 6th Street (SB) and Route 45 to 7th Street (NB)
• 300 ft difference between 25 mph and 35 mph signs
• Relocate SB 25 mph sign to line up with 35 mph sign at 7th or
• Relocate NB 35 mph sign to line up with 25 mph sign at 6th
• 6th Street to 250 ft west of Park University Entrance Drive (SB) and 7th Street to 250 ft west of Park University Entrance Drive (NB)
• 250 ft west of Park University Entrance Drive to 500 ft east of Park University Entrance Drive//35 mph
• 500 ft east of Park University Entrance Drive to Mattox Road//55 mph
BIKE LANES
• Not recommended
SHOULDER
• Should be 10 feet wide
SIDEWALKS
• Should be 5 ft wide on the western side and 10 ft wide on the eastern side
• Exceptions:
• Aesthetic sidewalk with variable from 1503+00 to 1506+20
• Transistion from 5 ft wide to 6 ft wide from 1512+96.98 to 1513+72.50
• Variable segment at cemetery retaining wall > 4.44 ft wide from 1514+07.69 to 1514+29.72 = 22.03 ft
• Transistion from 6 ft wide t o 5 ft wide from 1514+43.21 to 1515+03.6
• 6 ft wide from 1543+86.95 to start of the shoulder 1560+26.85
RETAINING WALL is spaced 1 ft away from the outside edge of sidewalk
• Exceptions:
• Use integral wall and sidewalk on west side from 1412+32.23 to 1513+46.68
• Use integral wall and sidewalk on west side from 1537+05.95 to 1537+38.95
CURB
• Should be 2 feet wide and include storm sewer
44
CURB RETURNS
• Should have a radius of 30 feet and 10 feet for driveway
• Exceptions:
• At Route 9 & 62nd Street use a 25 ft radius
• At the southern School of Rock entrance & Route 9 use a 18 ft radius
• At Route 9 & 13th Street use a 10 ft radius
• At Route 9 & 12th Street use a 10 ft radius for the eastbound approach
• At Route 9 & 7th Street use a 10 ft radius
• At Route 9 & 6th Street use a 10 ft radius for the eastbound approach
• At Route 9 & 5th Street use a 10 ft radius
• At Route 9 & 4th Street use a 10 ft radius
• At Route 9 & 3rd Street use a 10 ft radius
• At Route 9 & 2nd Street use a 10 ft radius
• At East Street & 1st Street use a 8 ft radius for the northwest corner, 3 ft radius for the northeast corner, 5 ft radius for the southeast corner, and use
a 90 ft radius for the westbound right-turn lane
• At Route 9 & Park University Drive use 40 ft radius
• At Route 9 & Mattox Road use a 65 ft radius for the southwest corner
CROSSWALK LOCATIONS
• Route 9 & Mattox Road
• East Street & 1st Street
• Route 9 & 6th Street
• Route 9 & 12th Street
• Routh 9 & Lakeview Drive
• Route 9 & Clark Avenue
• Route 9 & Route 45
SIDEWALK SEPARATION
• Grassy area between the back of the curb and the sidewalks is 3 ft wide
• Exceptions:
• West side from 1512+96.98 to 1515+03.64, width varies from 3 ft to 0 ft to avoid cemetery retaining wall
• West side from 1543+86.95 to start of the shoulder at 1560+26.85, width of 0 ft to avoid returning wall reconstruction
• East side from 1541+34.72 to 1544+80.24, width varies from 3 ft to 0 ft to avoid stadium seating
• East side from 1548+24.82 to 1549+38.47, width of 0 ft due to on-street parking
• East side from 1549+99.65 to 1550+89.30, width of 0 ft due to on-street parking
• East side from 1555+87.40 to start of the shoulder, width varies from 2 ft to 0 ft to avoid Post Office building corner and to account for 10 ft NB left
turning lane at 2nd Street
HANDRAILS on retaining walls
• Match metal railing on White Alloe Creek Bridge:
• Height at least 42 inch (FHWA Designing Sidewalks and Trails for Access, Part II of II: Best Practices
Design Guide 14.7), 54 inch on bridges
• Gripping surface from 1.25 inch - 1.5 inch wide (ADA Accessibility Guidelines for Buildings and Facilities 4.26)
ROUTE 9 CORRIDOR STUDY
45
LIGHTING
• Within grassy area between the back of curb and sidewalk
POTENTIAL DUCT BANK UNDER 10 FT TRAIL
• At least 4 ft wide
• Inculde 3 ft wide vaults within grassy area between curb and sidewalk
ADDITIONAL RIGHT-OF-WAY TO ACQUIRE
• 3486.53 sq ft (0.08 ac) from 1482+61.34 to 1485+34.64
• 2266.77 sq ft (0.05 ac) from 1493+12.79 to 1494+10.18
• 2981.48 sq ft (0.07 ac) from 1500+67.07 to 1506+59.94
• 8792.95 sq ft (0.20 ac) from 1511+40.73 to 1512+53.61
EXISTING RIGHT-OF-WAY
• Cross Section of 57 ft in 60 ft Right-of-Way
B: SITE SPECIFIC DESIGN RECOMMENDATIONS
CHANGES TO INTERSECTIONS
• Route 9 & Route 45:
• Adjust Route 9 northbound lanes approaching intersection since 1 thru lanes turns into 2 thru lanes after the intersection
• Route 9 & Lewis Street
• Restripe and add eastbound left-turn bay
• Route 9 & 63rd Street
• Remove channelization island and restripe to add EB left-turn bay
• Route 9 & Clark Avenue
• Add signal
• Route 9 & Lakeview Drive
• Match geometry and island for new construction
• Route 9 & Main Street
• Issue: Approach angle is 15 degrees and unsafe
• Constraints: Right-of-way, topography, elevation changes, bordered by Missouri Conservation land and houses, cemetary retaining walls on either
side of the road
• Of the options examined, the recommended approach is to adjust the approach angle of Main Street to Route 9 to 75 degrees (Option 1). This is the
minimal cost option and would not interfere with possible future configurations of Route 9 and Main Street. Option 5 is the ultimate build to meet the
needs of the City; however, there are currently no plans to construct Option 5.
Option 1 - Adust approach angle of Main Street to Route 9 to 75 degrees
Advantage Disadvantage
Better visibilty for Main Street Increase in grade
Lowest Cost No change in access
46
Option 2 - Adjust approach angle of Main Street to Route 9 to 90 degrees
Advantage Disadvantage
Better visibility for Main Street Cost of removing 3 houses
Full Access Tight Curves
Option 3 - Connect Main Street to 57th Street, add access to Route 9, add access to Lakeview Drive
Advantage Disadvantage
Better visibilty for Main Street Cost of removing 3 homes
Full access Short distance for Main Street/Route 9 connection
Access to Signal
Access for 57th Street and West Street
Option 4 - Keep Main Street connection, reroute Route 9 to intersect with 57th Street, add access to Lakview Drive
Advantage Disadvantage
Better visibility for Main Street Cost of removing 1 house
Full Access Route 9 must curve into conservation (510 ft min radius)
Access to signal Traffic issue for southbound lefts
Access for 57th Street and West Street Grade across intersection is issue
Option 5 - Connect Main Street to Lakeview Drive, connect 57th Street to Route 9
Advantage Disadvantage
Better visibility for Main Street Cost of removing 3 houses
Full Access
Access to signal
Access for 57th Street and West Street
Greater distance for Main Street/Route 9 connection
• Route 9 and 12th Street
• Add left-turn bay for northbound and southbound approaches
• Route 9 & 6th Street
• Add left-turn bay for northbound, southbound, and westbound approaches
• East Street & 1st Street
• Reconstruct intersection to remove stop signs and add signal
• Main Street & 1st Street
• Reconstruct intersection to add curb turnouts, replace westbound stop sign with yield to ped sign, add northbound and southbound stop signs
SHOULDER REMOVAL
• Remove southbound shoulder to replace with curb and gutter and sidewalk from 1479+00 to 1483+00
TRAIL
• Reconstruct White Alloe Creek Trail and add pavement along existing path from 6th Street to Route 9
• Construct sidewalk connection from Route 9 to Nature Sanctuary along south side of 12th Street
ROUTE 9 CORRIDOR STUDY
47
MAILBOXES
• 9 mailboxes total
• Location 1: One grouped pick-up / drop-off location at 1345 MO Route 9
• Southbound side, 500 ft north of Lakeview Drive
• Spacing from intersection = OK
• Location 2: One mailbox near 1345 MO Route 9
• Southbound side, 170 ft north of Lakeview Drive
• Spacing from intersection = NOT OK, 170 ft < 200 ft min
• Location 3: One mailbox at 1345 MO Route 9
• Southbound side, 90 ft north of Lakeview Drive
• Spacing from Intersection = NOT OK, 90 ft < 200 ft min
• Location 4: One mailbox at 1356 Mo Route 9
• Southbound side, 150 ft south of Lakeview Dr
• Spacing from intersection = OK
• Location 5: One mailbox near 1301 East Street
• Northbound side, 310 ft north of 13th St
• Spacing from Intersection = OK
• Causes unsafe Pedestrian Crossing
• Location 6 - One mailbox near 1301 East Street
• Northbound side, 65 ft north of 13th St
• Spacing from Intersection = NOT OK, 65 ft < 100 ft min
• Causes unsafe Pedestrian Crossing
• Location 7: One mailbox near Quarry on MO Route 9
• Westbound side, 860 ft west of Coffey Rd
• Spacing from Intersection = OK
• Spacing requirements based on AASHTO Roadside Design Guide, Figure 11-4
• Assumed AADT of 15000 vpd for Route 9
• Assumed AADT of 500 vpd for cross streets
NECESSARY ADDITIONAL RIGHT-OF-WAY
• Project Segment 1 - Route 45 to 62nd Street
• Farley State Bank 3.437.3460 sq ft (0.0789 acre)
• Burn, Alan J & Tracey S 49.1844 sq ft (0.0011 acre)
• Project Segment 2 - 62nd Street to Parkville Athletic Complex
• SKG LLC 2,266.76668 sq ft (0.0520 acre)
• Project Segment 3 - Parkville Athletic Complex to Lakeview Dr.
• Don Julian Builder Inc 2,981.4827 sq ft (0.0684 acre)
• Tuf Flight Industries 8,792,.9483 sq ft (0.2019 acre)
48
UTILITY CONFLICTS
Several utility poles will need to be relocated along Route 9. There are two recommended
concepts; Relocate poles to within the grassy area between the back of curb and side-
walks or construct a 4 ft wide duct bank underneath the 10 foot trail and periodically
place 3 foot wide access vaults with the grassy area. For the relocation of the poles, the
utility companies will be required to cover the costs of reinstallation. For the duct bank,
the utilities will be more weather resistant and the streetscape will be more aesthetically
pleasing; however, construction costs will be excessive and would most likely exceed the
30% contingency applied to each project. Depending on the unit cost of the duct bank,
the construction cost could nearly double for each project segment if a duct bank was
added to the scope.
• Project Segment 1 - Route 45 to 62nd Street
Poles to be relocated - 6
• Project Segment 2 - 62nd Street to Parkville Athletic Complex
Poles to be relocated - 8
• Project Segment 3 - Parkville Athletic Complex to Lakeview Dr.
Poles to be relocated - 16
• Project Segment 4 - Lakeview Drive to 13th Street
Poles to be relocated - 10
• Project Segment 5 - 13th Street to 12th Street
Poles to be relocated - 7
• Project Segment 6 - 12th Street to 7th Street
Poles to be relocated - 6
• Project Segment 7 - 7th Street to 5th Street
Poles to be relocated - 5
• Project Segment 8 - 5th Street to 2nd Street
Poles to be relocated - 5
• Project Segment 9 - 2nd Street to White Alloe Creek
Poles to be relocated - 5
• Project Segment 10 - White Alloe Creek to Park University Entrance Drive
Poles to be relocated - 1
• Project Segment 11 - Park Univeristy Entrance Drive to Coffey Rd.
Poles to be relocated - 0
• Project Segment 12 - Coffey Road to Mattox Road
Poles to be relocated - 0
ROUTE 9 CORRIDOR STUDY
49
50
SECTION 4Project Segments
One of the primary outcomes to be accomplished within the Route 9 Corridor Study was to deliver preliminary plans for
improvements through the 4-mile corridor. Additionally, these preliminary plans were broken into logical project segments so the
City could ultimately create a plan to design and construct improvements over time, or if new development was occurring, the
City would be able to work closely with the development partner to incorporate the proposed Route 9 design. This section of the
report illustrates the twelve project segments, the proposed ideas for each and construction estimates (2015 dollars).
ROUTE 9 CORRIDOR STUDY
51
SEGMENT 1: ROUTE 45 TO 62ND STREET
ESTIMATED COST:$750,353.85SEGMENT 1 DETAILS: FIXING DRAINAGE ISSUES
• Pavement, 78 Tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 2,472 feet
• Storm Sewer, 2,000 feet
• Sidewalk, 1,667 square yards
• Retaining Wall, 1836 square feet
52
ESTIMATED COST:$550,076.57
SEGMENT 2: 62ND STREET TO PARKVILLE ATHLETIC COMPLEX
SEGMENT 2 DETAILS: ADDING TRAFFIC SIGNAL AT CLARK AVE.
• Pavement, 126 Tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 1,973 feet
• Storm Sewer, 2,000 feet
• Sidewalk, 1,272 square yards
• Retaining Wall, 0 square feet
• Traffic Signal Installation
ROUTE 9 CORRIDOR STUDY
53
SEGMENT 3: PARKVILLE ATHLETIC COMPLEX TO LAKEVIEW DRIVE
ESTIMATED COST:$1,518,450.81SEGMENT 3 DETAILS: IMPROVING PARKING ACCESS
• Pavement, 2,611 tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 5,258 feet
• Storm Sewer, 2,750 feet
• Sidewalk, 2,292 square yards
• Retaining Wall, 3,699 square feet
54
SEGMENT 4: LAKEVIEW DRIVE TO 13TH STREET
ESTIMATED COST:$2,031,710.41
SEGMENT 4 DETAILS: IMPROVE VISION AT MAIN STREET
• Pavement, 282 tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 3,590 feet
• Storm Sewer, 4,000 feet
• Sidewalk, 3,143 square yards
• Retaining Wall, 10,341 square feet
ROUTE 9 CORRIDOR STUDY
55
SEGMENT 5: 13TH STREET TO 12TH STREET
ESTIMATED COST:$908,953.32SEGMENT 5 DETAILS: REPLACING RETAINING WALL
• Pavement, 192 tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 993 feet
• Storm Sewer, 1,200 feet
• Sidewalk, 1,255 square yards
• Retaining Wall, 4,725 square feet
56
SEGMENT 6: 12TH STREET TO 7TH STREET
ESTIMATED COST:$785,360.36
SEGMENT 6 DETAILS: TRAIL BEHIND PARK UNIVERSITY STANDS
• Pavement, 200 tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 1,231 feet
• Storm Sewer, 1,500 feet
• Sidewalk, 1,177 square yards
• Retaining Wall, 4,104 square feet
ROUTE 9 CORRIDOR STUDY
57
SEGMENT 7: 7TH STREET TO 5TH STREET
ESTIMATED COST:$603,511.79SEGMENT 7 DETAILS: 6TH STREET TURN LANES
• Pavement, 249 tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 1,616 feet
• Storm Sewer, 1,800 feet
• Sidewalk, 1,896 square yards
• Retaining Wall, 270 square feet
58
SEGMENT 8: 5TH STREET TO 2ND STREET
ESTIMATED COST:$198,542.52
SEGMENT 8 DETAILS: 2-LANE SECTION
• Pavement, 24 tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 538 feet
• Storm Sewer, 750 feet
• Sidewalk, 554 square yards
• Retaining Wall, 189 square feet
ROUTE 9 CORRIDOR STUDY
59
SEGMENT 9: 2ND STREET TO WHITE ALLOE CREEK
ESTIMATED COST:$537,728.65SEGMENT 9 DETAILS: ADDING TRAFFIC SIGNAL AT EAST ST. & 1ST ST.
• Pavement, 161 tons
• Shoulder, 0 square yards
• Concrete Curb and Gutter, 2,419 feet
• Storm Sewer, 1,200 feet
• Sidewalk, 1,020 square yards
• Retaining Wall, 59 square feet
• Traffic Signal Installation
60
SEGMENT 10: WHITE ALLOE CREEK TO PARK UNIVERSITY ENTRANCE DRIVE
ESTIMATED COST:$414,886.40
SEGMENT 10 DETAILS: ADDED EASTBOUND LANE
• Pavement, 479 tons
• Shoulder, 973 square yards
• Concrete Curb and Gutter, 885 feet
• Storm Sewer, 1,000 feet
• Sidewalk, 1,239 square yards
• Retaining Wall, 0 square feet
ROUTE 9 CORRIDOR STUDY
61
SEGMENT 11: PARK UNIVERSITY ENTRANCE DRIVE TO COFFEY ROAD
ESTIMATED COST:$1,560,160.95SEGMENT 11 DETAILS: ADDED WEST BOUND LANE
• Pavement, 1,881 tons
• Shoulder, 6,741 square yards
• Concrete Curb and Gutter, 0 feet
• Storm Sewer, 0 feet
• Sidewalk, 11,300 square yards
• Retaining Wall, 0 square feet
62
SEGMENT 12: COFFEY ROAD TO MATTOX ROAD
ESTIMATED COST:$1,554,555.40
SEGMENT 12 DETAILS: INTERSECTION & TURN LANE IMPROVEMENTS
• Pavement, 1,242 tons
• Shoulder, 3,682 square yards
• Concrete Curb and Gutter, 76 feet
• Storm Sewer, 0 feet
• Sidewalk, 15,090 square yards
• Retaining Wall, 0 square feet
• Traffic Signal Installation
SEGMENT 12A: MATTOX ROAD INTERSECTION ONLY
ESTIMATED COST:$400,000.00
ROUTE 9 CORRIDOR STUDY
63
PROJECT SUMMARY
The Missouri Route 9 project segments are listed below. The construction estimates are in 2015 dollars. As mentioned earlier, the project segments
have been identified based on corridor challenges, technical analysis and logical project limits for transportation management. The estimated cost
includes the optional street lighting costs, an added 30% contingency, and an added 15% for engineering design and inspection.
Route 9 Project Segments Estimated Cost
Route 45 to 62nd Street $890,995.92
62nd St. To Parkville Athletic Complex $657,569.01
PAC to Lakeview Drive $1,752,739.80
Lakeview Drive to 13th Street $2,343,711.96
13th Street to 12th Street $1,047,731.58
12th Street to 7th Street $913,307.14
7th Street to 5th Street $708,802.58
5th Street to 2nd Street $247,065.39
2nd Street to White Alloe Creek $630,408.73
White Alloe Creek to Park University Entrance Drive $506,779.98
Park University Entrance Drive to Coffey Rd $1,740,179.52
Coffey Road to Mattox Road $1,733,927.17
ROUTE 9 CORRIDOR STUDY
64
65
SECTION 5Project Outcomes
Improvements to Route 9 will not only enhance connectivity and address traffic challenges, but also hold the opportunity to cata-
lyze new private investment along the corridor. Parkville has long standing goals to make its downtown more inviting, comfort-
able, and attractive, and to focus on Route 9 as a strategic corridor for economic development. Investment in infrastructure and
amenities along Route 9 helps to make development sites more desirable and functional. Likewise, new development along the
corridor helps to position roadway improvements to realize their full potential.
66
DEVELOPMENT ANALYSIS
The project team has identified several specific development opportu-
nities along the corridor. While these are not the only locations where
new investment and development is possible, they are sites that have
some history of development planning, either through the City’s recent
planning efforts or the efforts of private partners. The project team
is using these sites to explore the potential economic development
benefits and opportunities associated with improvements to Route 9.
1
7
8
6
4
5
3
2
Convenience Retail
Parkville Commons Infill
Parkville Connections
SKG LLC Property
Riss Lake Frontage
East Street Redevelopment
Downtown Infill
American Water Site
1
7
8
6
4
5
3
2
ROUTE 9 CORRIDOR STUDY
67
1: CONVENIENCE RETAIL 2: PARKVILLE COMMONS INFILL 3: PARKVILLE CONNECTIONS
4. SKG LLC PROPERTY 5: RISS LAKE FRONTAGE 6: EAST STREET REDEVELOPMENT
7: DOWNTOWN INFILL 8. AMERICAN WATER SITE
68
DEVELOPMENT ANALYSIS
For each development opportunity along Route 9, the project team reviewed proposed development plans, site conditions, and market information to estimate
development capacity for the site. This development capacity analysis provided a breakdown of residential units and non-residential square footage for each identi-
fied opportunity. The breakdown of uses and development capacity then informed a high level cost estimate for development.
Three development scenarios were explored: modest development, moderate development, and major development. The Modest Development represents near
term opportunities that have potential to be immediately leveraged or coordinated with Route 9 improvements. The Major Development scenario represents the
full capacity of the identified development sites (but not necessarily the full development potential of the entire corridor). The Moderate Development Scenario falls
somewhere in between. The analysis also identified existing development in the opportunity areas to understand the net impacts of new development. The devel-
opment analysis has a variety of uses, including determining the potential fiscal benefits to the City of new development and for exploring different infrastructure
funding scenarios.
EXISTING
CONDITIONS
SINGLE
FAMILY
ATTACHED MULTI-
FAMILY
RETAIL OFFICE INDUSTRIAL PUBLIC/
CIVIC
EDUCA-
TIONAL
HIGH
LEVEL COST
ESTIMATESUNITSUNITSUNITSSQ. FEET SQ. FEET SQ. FEET SQ. FEET SQ. FEET
1. Convenience Retail
2. Parkville Commons Infill
3. Parkville Connections 1 4,200 1,350 25,270
4. SKG LLC Property
5. Riss Lake Frontage
6. East Street Redevelopment 2 13,350 12,500 11,250
7. Downtown Infill
8. American Water Site 11,200
Total 3 0 0 17,550 1,350 37,770 22,450 0
ROUTE 9 CORRIDOR STUDY
69
MODEST
DEVELOPMENT
SINGLE
FAMILY
ATTACHED MULTI-
FAMILY
RETAIL OFFICE INDUSTRIAL PUBLIC/
CIVIC
EDUCA-
TIONAL
HIGH
LEVEL COST
ESTIMATESUNITSUNITSUNITSSQ. FEET SQ. FEET SQ. FEET SQ. FEET SQ. FEET
1. Convenience Retail 5,858 $1,054,440
2. Parkville Commons Infill
3. Parkville Connections
4. SKG LLC Property
5. Riss Lake Frontage
6. East Street Redevelopment 2 55 11,950 11,250 28,800 $20,913,000
7. Downtown Infill
8. American Water Site 4,050 4,125 $1,226,250
Total 2 0 55 21,858 4,125 0 11,250 28,800 $23,193,690
Net -1 0 55 4,308 2,775 -37,770 -11,200 28,800
MODERATE
DEVELOPMENT
SINGLE
FAMILY
ATTACHED MULTI-
FAMILY
RETAIL OFFICE INDUSTRIAL PUBLIC/
CIVIC
EDUCA-
TIONAL
HIGH
LEVEL COST
ESTIMATESUNITSUNITSUNITSSQ. FEET SQ. FEET SQ. FEET SQ. FEET SQ. FEET
1. Convenience Retail 5,858 $1,054,440
2. Parkville Commons Infill 14,000 11,200 $4,200,000
3. Parkville Connections 170 86,000 10,000 $42,000,000
4. SKG LLC Property 28,000 $3,920,000
5. Riss Lake Frontage 6,000 $900,000
6. East Street Redevelopment 2 55 11,950 11,250 28,800 $20,913,000
7. Downtown Infill 2,000 $300,000
8. American Water Site 4,050 4,125 $1,226,250
Total 2 0 225 129,858 53,325 0 11,250 28,800 $74,513,690
Net -1 0 225 112,308 51,975 -37,770 -11,200 28,800
70
MAJOR
DEVELOPMENT
SINGLE
FAMILY
ATTACHED MULTI-
FAMILY
RETAIL OFFICE INDUSTRIAL PUBLIC/
CIVIC
EDUCA-
TIONAL
HIGH
LEVEL COST
ESTIMATESUNITSUNITSUNITSSQ. FEET SQ. FEET SQ. FEET SQ. FEET SQ. FEET
1. Convenience Retail 5,858 $1,054,440
2. Parkville Commons Infill 66 14,000 11,200 $13,704,000
3. Parkville Connections 46 65 170 96,000 20,000 $60,784,000
4. SKG LLC Property 56,000 $7,840,000
5. Riss Lake Frontage 6,000 12,000 $2,700,000
6. East Street Redevelopment 112 15,500 10,500 28,800 $32,456,000
7. Downtown Infill 2,000 2,000 $600,000
8. American Water Site 44 5,250 $8,127,000
Total 46 65 392 144,608 101,200 0 10,500 28,800 $127,265,440
Net 43 65 392 127,058 99,850 -37,770 -11,950 28,800
ROUTE 9 CORRIDOR STUDY
71
DOWNTOWN DEVELOPMENT
Both the 2009 Parkville Master Plan and the Vision
Downtown Parkville discuss the benefits of future
redevelopment on the east side of East Street.
Despite its ideal locations between Downtown
Parkville and Park University, this area is not utilized
to its highest potential today. Infill and redevelop-
ment opportunities can extend the experience of
the Downtown area, incorporate higher-intensity,
higher-value development, enhance the aesthetics
and walkability along Route 9, and better serve the
current and future needs of Park University. The
community’s vision for future development of this
area informs how Route 9 will look and function in
the future. Below are two scenarios that highlight
different development opportunities.
One approach to investment and development east
of East Street is to maintain the existing buildings
and building lines where possible, and strategically
develop in the available spaces in between. As
businesses move or evolve, new uses could reposi-
tion existing buildings to better support Downtown’s
vision. New development would be focused on
smaller parcels and occur incrementally.
Another approach to investment and develop-
ment east of East Street is to pursue a coordinated
development strategy for the entire site. While this
concept could still be developed in phases over time,
each component would support an overall concept
for integrated uses, access, parking, and amenities.
The above diagram illustrates just one possible scenario for how existing uses and new infill development could integrate with
improvements to Route 9 and other amenities, including a restored trail along White Aloe Creek.
ROUTE 9 CORRIDOR STUDY
72
73
SECTION 6Implementation Strategy
The Missouri Route 9 Corridor Study must be a study that goes beyond advancing the planning process; it must create
an implementation strategy and a financial strategy. City leadership and community supporters can then seek the funding
neccessary to complete the projects. The components include: 1) the identification of funding sources available for the projects
from local, state and federal sources, 2) project financing scenarios to assist community leaders in their decision-making process,
and 3) a project prioritization matrix that includes criteria that is specifically tailored for the projects within the Route 9 Study.
ROUTE 9 CORRIDOR STUDY
74
FUNDING OPTIONS
The Project Team has designed a comprehensive Plan of Finance. The Mayor, the Board of Aldermen and the public will be able to discuss the
recommended strategy for each of the project segments. While certain revenue sources are not as economically desirable or politically palatable as
others, all sources will be discussed to inform the decision-making process in the future. A Sources & Uses analysis was used to marry project costs
to secured or potential revenue sources as well as a timeline. The project will approximately cost $13.2 million. The construction time horizon is 25
years.
REVENUES AND FINANCING OPTIONS
COMMUNITY IMPROVEMENT DISTRICT
A Community Improvement District (CID) may be either a political subdivision or a not-for-profit corporation. CID’s are organized for the purpose of
financing a wide range of public-use facilities and establishing and managing policies and public services relative to the needs of the district.
SUPPORTING ORGANIZATIONS
A CID is a separate legal entity, and is distinct and apart from the municipality that creates the district. A CID is, however, created by ordinance of
the governing body of the municipality in which the CID is located and may have other direct organizational or operational ties to the local govern-
ment, depending upon the charter of the CID.
TYPICAL BUDGET ITEMS AND RESPONSIBILITIES
A CID may finance new facilities or improvements to existing facilities that are for the use of the public.
Such public-use facilities include:
• Convention centers, arenas, meeting facilities, pedestrian or shopping malls and plazas
• Paintings, murals, fountains or kiosks
• Parks, lawns, gardens, trees or other landscapes
• Streetscapes, lighting, benches, marquees, awnings, canopies, trash receptacles, walls
• Lakes, dams and waterways
• Sidewalks, streets, alleyways, bridges, ramps, tunnels, traffic signs and signals utilities, drainage works, water, storm and sewer systems and
other site improvements
• Parking lots, garages
• Childcare facilities and any other useful, necessary or desired improvement
A CID may also provide a variety of public services, some of which may be:
• Operating or contracting for the operation of parking facilities, shuttle bus services
• Leasing space for sidewalk café tables and chairs
• Providing trash collection and disposal services
• With consent of the municipality, prohibiting, or restricting vehicular and pedestrian traffic and vendors on streets
• Within a designated “blighted area”, contract with any private property owner to demolish, or rehabilitate any building or structure owned
by such property owner
• Providing or contracting for security personnel, equipment or facilities
75
FINANCIAL RESOURCES
Funding of CID projects and services must be set forth in the requesting petition that is presented to the local governing body of the municipality in.
which the CID is located. Funding may be accomplished by district-wide special assessment, rents, fees, and charges for the use of CID property or
services, grants, gifts or donations. If the CID is organized as a political subdivision, property and sales taxes may also be imposed within the bound-
aries of the CID.
ORGANIZING A CID
By request petition, signed by property owners owning at least 50% of the assessed value of the real property and more than 50% per capita of all
owners of real property within the proposed CID, presented for authorizing ordinance to the governing body of the local municipality in which the
proposed CID would be located. Language contained in the petition narrative must include a five year plan, describing the purposes of the pro-
posed district, the services it will provide, the improvements it will make and an estimate of the costs of those services and improvements and the
maximum rates of property taxes and special assessments that may be imposed within the proposed district. Other information must state how the
CID would be organized and governed and whether the governing board would be elected or appointed. There are specific rules that provide the
required elements of a CID petition, and the procedures for publication, public hearings, etc.
ADVANTAGES CHALLENGES:
Broader Use of Funds than TDD Tax Increase
Ease of creation, formed by the City Political exposure to City
Locally Driven Limited to public improvements unless blighted
Board could be appointed by City
TRANSPORTATION DEVELOPMENT DISTRICT
A Transportation Development District (TDD) may be created to act as the entity responsible for developing, improving, maintaining, or operating
one or more “projects” relative to the transportation needs of the area in which the District is located. A TDD may be created by request petition
filed in the circuit court of any county partially or totally within the proposed district.
The district has the authority to finance the project through special assessments; property tax, sales tax, or toll roads. In addition, they can liquidate
any and all of the above methods through debt financing. Special Assessments must either be approved by a majority vote of district voters, if any,
or by the district property owners, who will indicate their approval by signing a special assessment petition. There may be one or more assessments,
which must apply to project improvements that specially benefit district properties.
TYPICAL BUDGET ITEMS
A TDD serves to fund, promote, plan, design, construct, improve maintain or operate one or more “projects” or to assist in such activity. “Projects
may include:
• Streets, highways, roads, interchanges, intersections, bridges, traffic signal lights or signage:
• Bus stops, terminals, stations, wharves, docks, rest areas or shelters;
• Airports, river, or lake port, railroad, light rail or other mass transit improvements and any similar or related improvement or infrastructure.
FINANCIAL RESOURCES
Funding of TDD projects may be accomplished through the creation of District-wide special assessments or property or sales taxes with a required
majority voter or petition approval. Other funding sources requiring voter majority approval may include establishing tolls or fees for the use of the
project. The TDD may also issue bonds, notes, and other obligations in accordance with the authority granted to the entity for such issuance.
ROUTE 9 CORRIDOR STUDY
76
ORGANIZING A TDD
At least 50 registered voters from each county within the proposed district, or the governing body of any local transportation authority within any
county where the proposed project is to be located, all of the property owners within the proposed district, if no district residents are eligible to be
registered voters, or two or more local transportation authority’s adopting resolutions to form a district; with one, subsequently filing.
ADVANTAGES CHALLENGES:
Most allowable spending matches up Use of fund restricted to transportation only
Multiple ways to form (property owners, voters or City) Formed by Court
Multiple ways to approve sales tax (registered voters or property owners) Tax requires and election
Can be noncontiguous Political exposure to City
Tax increase
TAX INCREMENT FINANCING
Tax Increment Financing (TIF) allows for the capture of 100% of incremental local property tax and 50% of incremental local sales tax for 23 years to
be spent on the redevelopment of a Blighted Area as defined by Statute.
The focus of the funding opportunities for the Route 9 Project centers on the redevelopment of specific locations. The City of Parkville could
consider the use of TIF to accelerate that redevelopment and share a portion of the captured revenues with the specific location and use a portion
to advance the Route 9 Project
TYPICAL BUDGET ITEMS
TIF may be used to pay certain costs incurred with a redevelopment project. Such costs may include, but are not limited to:
• Professional services such as studies, surveys, plans, financial management, legal counsel;
• Land acquisition and demolition of structures;
• Rehabilitating, reparigin existing buildings on site;
• Building necessary new infrastructure in the project area such as streets, sewers, parking, lighting; and
• Relocation of resident and business occupants located in the project area.
APPROVAL OF TIF
TIF begins with the establishment of a TIF Commission by the City consisting of specific members to represent the impacting taxing jurisdiction. A
plan with specific statutory requirements is submitted for recommendation by the TIF Commission to the governing body of the City. Next the City
takes up the TIF Plan and approves it by Ordinance. A TIF plan is usually implemented by a Redevelopment Agreement.
ADVANTAGES CHALLENGES:
All allowable spending matches up Impacts other taxing districts
Local Control Political exposure to the City
Spurs Redevelopment
A plan can cover a large Redevelopment Area but active specific projects as they begin
77
MODOT COST SHARE
Current Missouri state budget forecasts for transportation infrastructure are significantly less then prior years. This has caused the Missouri
Department of Transportation (MODOT) to suspend applications for their Cost Share Program. However, long range budget forecasts are improving
and the Cost Share Program has proven enormously popular and efficient in enhancing the financial viability of MODOT and, therefore, the Project
Team believes it will eventually be restored and potentially enhanced. The financial needs of state transportation will eventually be addressed. The
Project Team believes that it is important to position Parkville to take full advantage of whatever solution presents itself. Positioning the Route
9 Project for MODOT funding includes identifying the items in the project budget that would qualify for the cost share program. It is imperative
that the Parkville project be staged and developed to a point that the full benefit of whatever available funds can be secured. Under the currently
suspended Cost Share Program, MODOT is allowed to match up to $20 million, consequently, the Project Team is evaluating sources for the local
match. If secured, this could fully fund the project.
MODOT TRANSFERS CONTROL OF ROUTE 9 TO THE CITY
An additional option for the City to consider is potentially taking over this section of Route 9 from MoDOT. This option should only be considered by
the City under the following circumstances: 1) the proposed improvements to Route 9 would be most effectively implemented under City leadership,
2) MoDOT agrees to provide funds (in addition to the Cost Share Program) to cover maintenance expenditures for a 20-year period. Once the scope
of coverage from MODOT is ascertained, the next likely source of funding would be a loan through the Missouri Transportation Finance Corporation
(MTFC). It is anticipated that the Project will liquidate an annual revenue stream through the Missouri Transportation Finance Corporation who offer
subsidized loans for transportation infrastructure. The Project Team is evaluating and sizing various annual revenue sources inclusive of special
taxing district revenues (Benefit District) and other sources.
CAPITAL IMPROVEMENT SALES TAX
The City of Parkville has the statutory authority to seek voter approval for a ½% Capital Improvement Sales Tax. The revenues created from this
sales tax can be used to fund capital improvements, operation and maintenance of capital improvements, as well as the retirement of bonds issued
to fund capital improvements.
TYPICAL BUDGET ITEMS
Capital Improvement Sales Tax can be used to fund a broad range of Capital Improvement Expenses:
• Pay-as-you-go expenses for capital improvements city-wide;
• Debt service on obligations issued to fund capital improvements;
• Operation and maintenance of capital improvements
APPROVAL OF A CAPITAL IMPROVEMENT SALES TAX
The City approves an ordinance to seek voter approval of a Capital Improvement Sales Tax. Voter approval requires a simple majority vote within
the City.
ADVANTAGES CHALLENGES:
All allowable spending matches up Tax increase
Local Control Political exposure to the City
Spurs Redevelopment
Can be used City Wide
ROUTE 9 CORRIDOR STUDY
78
Single
Family
Attached Multi-Family Retail Office Industrial Public/Civic Educational Hotel
Units Units Units Sq. Feet Sq. Feet Sq. Feet Sq. Feet Sq. Feet Rooms
Convenience Retail 5,858
Parkville Commons InFill
Parkville Connections 1 4,200 1,350 25,270
SKG LLC Property
Riss Lake Frontage
East Street Redevelopment 2 55 11,950 11,250 28,800
Downtown Infill
American Water Site 4,050 4,125
TOTAL 3 0 55 26,058 5,475 25,270 11,250 28,800 0
NET 0 0 55 8,508 4,125 -12,500 -11,200 28,800 0
MODEST DEVELOPMENT
LOCAL GROWTH
The following tables show local growth of businesses along Route 9. Modest growth, moderate growth and major growth are all compared and
used in the financial analysis.
79
Single
Family
Attached Multi-Family Retail Office Industrial Public/Civic Educational Hotel
Units Units Units Sq. Feet Sq. Feet Sq. Feet Sq. Feet Sq. Feet Rooms
Convenience Retail 5,858
Parkville Commons InFill 66 14,000 11,200
Parkville Connections 46 65 170 96,000 20,000
SKG LLC Property 56,000
Riss Lake Frontage 6,000 12,000
East Street Redevelopment 112 15,500 10,500 28,800
Downtown Infill 2,000 2,000
American Water Site 44 5,250
TOTAL 46 65 392 144,608 101,200 0 10,500 28,800 0
NET 43 65 392 127,058 99,980 -37,770 -11,950 28,800 0
MAJOR DEVELOPMENT
Single
Family
Attached Multi-Family Retail Office Industrial Public/Civic Educational Hotel
Units Units Units Sq. Feet Sq. Feet Sq. Feet Sq. Feet Sq. Feet Rooms
Convenience Retail 5,858
Parkville Commons InFill 14,000 11,200
Parkville Connections 170 86,000 10,000
SKG LLC Property 28,000
Riss Lake Frontage 6,000
East Street Redevelopment 2 55 11,950 11,250 28,800
Downtown Infill 2,000
American Water Site 4,050 4,125
TOTAL 2 0 225 129,858 53,325 0 11,250 28,800 0
NET -1 0 225 112,308 51,975 -37,770 -11,250 28,800 0
MODERATE DEVELOPMENT
ROUTE 9 CORRIDOR STUDY
80
Fair Market
Value (FMV)
Assessed FMV TIF Sales
Convenience Retail $1,054,440 $337,421 $1,054,440 $585,800
Parkville Commons InFill $4,200,000 $1,344,000 $4,536,000 $1,400,00
Parkville Connections $42,000,000 $10,180,800 $17,280,000 $8,600,000
SKG LLC Property $3,920,000 $1,612,800 $3,920,000 $0
Riss Lake Frontage $900,000 $900,000 $600,000
East Street Redevelopment $20,913,000 $2,193,120 $2,151,000 $1,195,000
Downtown Infill $300,000 $115,200 $300,000 $200,000
American Water Site $1,226,250 $470,880 $0 $405,000
TOTAL $74,513,690 $16,254,221 $30,141,440 $12,985,800
NET $57,759,212 $10,998,294 $13,386,962 $11,230,800
Moderate Level Economic Drivers
Fair Market
Value (FMV)
Assessed FMV TIF Sales
Convenience Retail $1,054,440 $337,421 $1,054,440 $585,800
Parkville Commons InFill $66,500 $21,280 $0 $0
Parkville Connections $518,321 $41,336 $999,000 $420,000
SKG LLC Property $312,000 $99,840 $0 $0
Riss Lake Frontage $60,750 $17,100 $60,750 $0
East Street Redevelopment $20,913,000 $5,490,960 $11,673,000 $1,195,000
Downtown Infill $381,000 1$21,920 $0 $0
American Water Site $1,226,250 $470,880 $1,226,250 $405,000
TOTAL $24,532,261 $6,669,737 $15,013,440 $2,605,800
NET $7,777,783 $1,443,810 -$402,467 $850,800
LOCAL ECONOMIC DRIVERS
An initial sizing of economic drivers (real estate value and retail sales base) are summarized in the table below. The value is based on projected construction cost
and the sales are based on $100 per square foot. While some of these users will create more sales then others this is a good base line point for analysis.
Modest Level Economic Drivers
81
Modest
Development
Moderate
Development
Major
Development
New City Revenue (NCR) Property 9,405 71,643 154,293
New City Revenue (NCR) Sales 12,762 168,462 190,587
TIF Revenue -473,521 747,255
City Revenue after TIF -84,231 95,294
Special District Revenue 8,508 112,308 127,058
City Wide Capital Improvement Tax 459,254 511,154 518,529
Annual Revenue Streams
Modest
Development
Moderate
Development
Major
Development
New City Revenue (NCR)131,959 1,996,858 2,868,227
TIF -3,126,806 4,592,062
NCR and TIF 131,959 5,123,664 7,460,288
NCR, TIF & Special District (SD)167,787 6,758,201 9,309,498
NCF, TIF, SD & CIT 3,969,757 11,009,267 13,621,899
Sample Missouri Transportation Finance Corporation (MTFC) Project Funds
ANNUAL REVENUE SCENARIOS
An initial sizing of possible revenue sources is summarized in the table below.
Fair Market
Value (FMV)
Assessed FMV TIF Sales
Convenience Retail $1,054,440 $337,421 $1,054,440 $585,800
Parkville Commons InFill $13,704,000 $4,35,280 $4,536,000 $1,400,000
Parkville Connections $60,784,000 $14,263,360 $20,880,000 $9,600,000
SKG LLC Property $7,840,000 $3,225,600 $7,840,000 $0
Riss Lake Frontage $2,700,000 $1,036,800 $2,700,000 $600,000
East Street Redevelopment $32,456,000 $3,957,120 $2,790,000 $1,550,000
Downtown Infill $600,000 $230,400 $600,000 $200,000
American Water Site $8,127,000 $1,506,240 $0 $525,000
TOTAL $127,265,440 $28,942,221 $40,400,440 $14,460,800
NET $110,510,962 $26,686,294 $23,645,962 $12,705,800
Major Level Economic Drivers
ROUTE 9 CORRIDOR STUDY
82
CONCLUSION OF FUNDING OPTIONS
From reviewing the table above the Mayor, the Board of Alderman and the public can understand the current financial situation. Revenue can
be generated from new businesses in the form of property or sales taxes, Tax Increment Finance Area (TIF), Special District (SD), and City Wide
Improvement Tax. Based on the current local taxes, the City could collect between $16,000 and $345,000 annually, depending on the amount
of new development. Another revenue producer could be the use of Tax Increment Financing (TIF). Projections suggest that an annual revenue
stream between $0 and $552,000 could be produced from a TIF. Current projections in revenue from new businesses along the corridor that could
be part of a special taxing district [either a Community Improvement District (CID) or a Transportation Development District (TDD)] suggest that
an annual revenue between $4,000 and $127,000 could be produced from a 1% Special District Sales Tax. The Project Corridor already includes a
number of Special Districts (Transportation Development District (TDD) or Community Improvement District (CID)). Given the current lay of the
land in Parkville it is not possible to simply overlay a corridor wide Special District to garner project funding since most of the area is already covered
by Special District. A City-wide sales tax is an additional funding mechanism that could be employed. Revenue projections suggest that annual
revenue of $457,154 could be produced from a ½% City-wide sales tax (either Economic Development or Capital Improvement). These funding
methods could be blended in any manner that the Mayor and Board of Alderman think would be advisable.
No discussion of a new sales tax is complete without reviewing the impact on the overall tax rate. The project corridor already includes a number of
special districts with a sales tax. The total sales rate ranges from 7.1% to 9.1% depending on location. Forming new special districts with a 1% sales
tax will put the corridor at 8.1% thus on a level playing field with the rest of the city. As for a city wide sales tax, the metropolitan area has sales tax
rates in areas with special districts that vary from 8.725% – 10.15% so an all in sales tax rate of 8.6% with a 1% special district and ½% City Wide Sales
tax would be marketable.
As the project progresses, it is possible that other MODOT programs could add additional funds for the project segments, and the City of Parkville
could take control of maintenance and operations of Route 9. In addition, there remains discussion of a new funding solution for MODOT and should
the voters decide to support it, it could provide a significant infusion of match or unmatched funds.
Using this report, the City of Parkville can move towards their “Grand Vision” for their community. This financial section explained the various fund-
ing options for Route 9 and, while some options may be more favorable than others, this report will arm the City with the knowledge to make firm
financial decisions.
83
MID-AMERICA REGIONAL COUNCIL (MARC) GRANT CRITERIA
As the metropolitan areas designated planning organization the Mid-America Regional Council (MARC) provides funding grants for transportation projects with
similar goals to the Route 9 Corridor improvements. These are three catagories the city may submit projects to for funding: 1.) the Surface Transportation Program
(STP), 2.) the Transportation Alternatives Program (TAP), and 3.) the Congestion Mitigation & Air Quality Program (CMAQ). Projects can be submitted into each
of these catagories, making it possible for any one project to receive funding from multiple categories. To be considered for funding, the City must submit their
selected project(s) to MARC during the “call for projects” period, which will take place from January 2016 to March 2016. Projects must be submitted using MARC’s
criteria for project types. As a part of the Route 9 Corridor Study, the project team scored each project segment using the MARC criteria. Each of the project
segments score very high in each of the 3 possible grant funds; Transportation Alternatives Program, Congestion Mitigation and Air Quality Improvement Program,
and Surface Transportation Program. If a MARC grant is awarded, each of the submitted projects will require a 20% match of funds. To be competitive in the pool
of projects asking for funds, a viable option is to submit two or more projects to MARC. The multiple projects to be submitted could each be a combination of two
adjacent project segments. Another option is to have multiple local authorities submit for a MARC grant. Grants are awarded based on a scoring system. The scoring
breakdown is detailed below and is based on the best possible scores per segment.
A. Transportation Alternatives Program (100 Points Maximum)
TAP Project Eligibility
1) Relate to surface transportation in terms of function, proximity, and impact.
2) Include at least one of the federally designated TAP activities that MARC has condensed into five categories:
Category I. Active Transportation Infrastructure Projects
Infrastructure projects — both on-road and off-road — related to bicycle, pedestrian and other non-motorized forms of transportation
TAP Project Deductions
(All Projects)
-5 points because the area is not in an EJ tract
Environmental Justice tracts are census tracts with minority populations above average and > 20% of the population is in poverty.
See Environmental Justice document for details
(Category I)
-4 points if project serves any activity center higher development intensity and walkability
(-0 points if highest development intensity)
The intersection at Route 9 and Hwy 45 is a higher-intensity and more-walkable center
OR
-6 points if project serves any activity centers
Downtown Parkville near Park University is a basic activity center
OR
-10 points if project serves no activity centers
-5 points because project excludes elements that use renewable energy sources, recycled materials, or other green technologies
-6 points because Parkville’s population is 5,928 (2013), and the population residents & employees w/in 1-mi radius ranges from 5,000 to 9,999
ROUTE 9 CORRIDOR STUDY
84
B. Congestion Mitigation and Air Quality Improvement Program (100 Points Maximum)
CMAQ Project Eligibility
1) All federal eligibility, based on the most recent guidance of the CMAQ Program, must be met.
Available at: http://www.fhwa.dot.gov/environment/air_quality/cmaq/
2) Must be a transportation project that meets the federally designated CMAQ activity that MARC has categorized as:
Bicycle Pedestrian Projects. Construction of bicycle/pedestrian facilities (paths, bike racks, support facilities, etc.) that are not exclusively
recreational and provide a reduction in single-occupant vehicle travel.
3) Must generate an emissions reduction.
4) Must be located in or benefit a nonattainment or maintenance area within the Kansas City region.
CMAQ Project Deductions
0 points deducted without details on each segment’s emissions
C. Surface Transportation Program
STP Project Eligibility
In general, the location of STP projects is not limited. However, STP projects may not be undertaken on roads functionally classified as local or rural minor
collectors unless the roads were on a Federal-aid highway system on January 1, 1991, except—
1) for Bridges Not on Federal-aid Highways,
2) for projects described in paragraphs (2), (4), (6), (7), (11), (20), (25), and (26), of 23 U.S.C. 133(b) (described below under “Eligible Activities”),
3) as approved by the Secretary, and
4) for areas of 5,000 or less population (described below under “Special Rule for Areas of 5,000 or less population (23 U.S.C. 133(h))”).
STP Project Deductions
(All Projects)
-5 points because the area is not in an EJ tract
Environmental Justice tracts are census tracts with minority populations above average and > 20% of the population is in poverty.
See Environmental Justice document for details.
(Bridge Restoration, Rehabilitation, & Replacement)
N/A
(Bicycle/Pedestrian, Livable Communities Pilot Projects & Other Eligible Projects)
-6 points if project serves any activity center higher development intensity and walkability
(-0 points if highest development intensity)
The intersection at Route 9 and Hwy 45 is a higher-intensity and more-walkable center
OR
-9 points if project serves any activity centers
Downtown Parkville near Park University is a basic activity center
OR
85
-15 points if project serves no activity centers
-14 points because Parkville’s population is 5,928 (2013), and the population residents & employees w/in 1-mi radius ranges from 5,000 to 9,999
(Public Transportation)
N/A
(Roadway Capacity)
-4 points if project serves any activity center higher development intensity and walkability
(-0 points if highest development intensity)
The intersection at Route 9 and Hwy 45 is a higher-intensity and more-walkable center
OR
-6 points if project serves any activity centers
Downtown Parkville near Park University is a basic activity center
OR
-10 points if project serves no activity centers
-3 points because project is not on the Central Monitoring System (CMS)
-2 points because the current AADT/Lane on Route 9 is between 5,001 ‐ 10,000
Route 9 traffic near Horizons Pkwy is 14,025 vpd. Route 9 traffic near R45 is 10,696 vpd.
(Transportation Operations and Management)
-4 points if project serves any activity center higher development intensity and walkability
(-0 points if highest development intensity)
The intersection at Route 9 and Hwy 45 is a higher-intensity and more-walkable center
OR
-6 points if project serves any activity centers
Downtown Parkville near Park University is a basic activity center
OR
-10 points if project serves no activity centers
-4 points because project is not on the Central Monitoring System (CMS)
-5 points because project does not include a bridge replacement
-2 points because the current AADT/Lane on Route 9 is between 5,001 ‐ 10,000
Route 9 traffic near Horizons Pkwy is 14,025 vpd. Route 9 traffic near R45 is 10,696 vpd.
-2 points because the future AADT/Lane on Route 9 is between 5,001 ‐ 10,000
Route 9 traffic near Horizons Pkwy is 14,025 vpd. Route 9 traffic near R45 is 10,696 vpd.
ROUTE 9 CORRIDOR STUDY
86
(Transportation Safety)
-4 points if project serves any activity center higher development intensity and walkability
(-0 points if highest development intensity)
The intersection at Route 9 and Hwy 45 is a higher-intensity and more-walkable center
OR
-6 points if project serves any activity centers
Downtown Parkville near Park University is a basic activity center
OR
-10 points if project serves no activity centers
-4 points because the current AADT/Lane on Route 9 is between 5,001 ‐ 10,000
Route 9 traffic near Horizons Pkwy is 14,025 vpd. Route 9 traffic near R45 is 10,696 vpd.
-4 points because the future AADT/Lane on Route 9 is between 5,001 ‐ 10,000
Route 9 traffic near Horizons Pkwy is 14,025 vpd. Route 9 traffic near R45 is 10,696 vpd.
Segment TAPAll Projects + Category I(30 Max + 70 Max)
CMAQ(100 Max)STPAll Projects(30 Max)
STPBicycle / Pedestrian Livable Communites Pilot Projects & Other Eligible Projects (100 Max)
STPRoadway Capacity(100 Max)
STPTransportation Operations & Management (100 Max)
STPTransportation Safety(90 Max)
Route 45 to 62nd Street 80 100 25 80 89 83 78
62nd Street to Parkville Athletic
Complex (PAC)
80 100 25 80 89 83 78
PAC to Lakview Drive 80 100 25 80 89 83 78
Lakeview Dr. to 13th St.74 100 25 71 83 77 72
13th St. to 12 St.74 100 25 71 83 77 72
12 St. to 7th St.74 100 25 71 83 77 72
7th St. to 5th St.78 100 25 77 87 81 76
5th St. to 2nd St.78 100 25 77 87 81 76
2nd to White Alloe Creek 78 100 25 77 87 81 76
White Alloe Creek to Park
University Entrance Dr.
78 100 25 77 87 81 76
Park University Entrance Dr. To
Coffee Rd.
74 100 25 71 83 77 72
Coffey Rd to Mattox Rd.74 100 25 71 83 77 72
87
PROJECT PRIORITIZATION
Throughout the process of completing the Route 9 Corridor Study, it was critical that one of the most important outcomes needed to be a project
prioritization matrix that would provide specific direction for community decision makers as to what order projects should move forward towards
construction. Several categories of criteria were included within this matrix, which were developed over the multiple months of work with the
Steering Committee and City leaders. Criteria included within the matrix includes: traffic benefit, multimodal benefit, economic benefit, public meet-
ing priority, construction costs, ease of constructability, MARC scoring, low controversy, and requiring other segments to be built first. The scoring
system applies a value of 0, 0.5, or 1 to each of the resultant categories which is multiplied by the weighted factor. Also of importance to have in
the matrix is the scoring of every project segment using the Mid-America Regional Council Surface Transportation Program (STP) project scoring
criteria. This MARC scoring is a significant category particularly if the City decides to submit Route 9 projects for federal funding. As one can see in
the Prioritization Matrix, all of the Route 9 projects score very well within the MARC system, therefore the projects should receive strong consider-
ation if submitted for funding.
Project Segment Traffic
Benefit
Multimodal
Benefit
Economic
Benefit
Public
Meeting
Priority
Score
(/50)
Rank
Route 45 to 62nd Street Good Best Med 1 27.5 5
62nd St. to PAC Better Best Med 2 33.75 2
PAC to Lakeview Best Best High 4 50 1
Lakeview Dr to 13th St Better Best Low 5 21.25 8
13th Street to 12th St Better Best Low 8 21.25 8
12th St to 7th St.Good Better Low 9 6.25 12
7th St 5th St Better Good High 11 26.25 6
5th St to 2nd St Good Good High 6 22.5 7
2nd St to White Alloe Creek Best Good High 9 32.5 4
White Alloe Creek to Park
University Entrance Drive
Better Better Low 11 12.5 11
Park University Entrance Dr to
Coffey Road
Best Better Low 6 21.25 8
Coffey Rd to Mattox Rd Best Better Med 3 33.75 2
Benefits in Addition to Safety
ROUTE 9 CORRIDOR STUDY
88
Project Segment Cost Ease of
Constructability
MARC
Scoring
Low
Controversy
Require
Other
Segment
Score
(/50)
Route 45 to 62nd Street $750,354 Easy Best Y N 40.0
62nd St. to PAC $550,077 Easy Best N N 45.0
PAC to Lakeview $1,518,451 Hard Best Y N 20.0
Lakeview Dr to 13th St $2,031,710 Easy Good Y Y 15.0
13th Street to 12th St $908,953 Hard Good Y N 20.0
12th St to 7th St.$785,360 Easy Good Y Y 25.0
7th St 5th St $603,512 Easy Better Y N 35.0
5th St to 2nd St $198,543 Easy Better N N 40.0
2nd St to White Alloe Creek $537,729 Hard Better N Y 25.0
White Alloe Creek to Park
University Entrance Drive
$414,886 Hard Better Y Y 30.0
Park University Entrance Dr to
Coffey Road
$1,560,161 Hard Good Y N 20.0
Coffey Rd to Mattox Rd $1,554,555 Hard Good Y N 20.0
Feasibility
Benefits Ranking
1 PAC to Lakeview Dr 62nd to PAC
2 62nd St to PAC PAC to Lakeview Dr
3 Coffey Rd to Mattox Rd Route 45 to 62nd
4 2nd St to White Alloe Creek 5th St to 2nd St
5 Route 45 to 62nd St 7th St to 5th St
6 7th St to 5th St 2nd St to White Alloe Creek
7 5th St to 2nd St Coffey Rd to Mattox Rd
8 13th St to 12th St White Alloe Creeek to Park University Entrance Drive
8 12th St to 7th St Park University Entrance Dr to Coffey Rd
8 Park University Entrance Dr to Coffey Rd 13th St to 12 St
11 White Alloe Creek to Park University Entrance Dr Lakeview Dr to 13th St
12 12th St to 7th St 12th St to 7th St
89
Feasibility Ranking
1 62nd St to PAC
2 Route 45 to 62nd St
3 5th St to 2nd St
4 7th St to 5th St
5 White Alloe Creek to Park University Entrance Dr
6 2nd St to White Alloe Crek
7 12th St to 7th St
8 PAC to Lakeview Dr
8 13th St to 12th St
8 Park University Entrance Dr to Coffey Rd
8 Coffey Rd to Mattox Rd
12 Lakeview Dr to 13th St
Overall Ranking
1 62nd St to PAC
2 PAC to Lakeview Dr
3 Route 45 to 62nd St
4 5th St to 2nd St
5 7th St to 5th St
6 2nd St to White Alloe Creek
7 Coffey Rd to Mattox Rd
8 White Alloe Creek to Park University Entrance Dr
9 Park University Entrance Dr to Coffey Rd
10 13th St to 12th St
11 Lakeview Dr to 13th St
12 12th St to 7th St
ROUTE 9 CORRIDOR STUDY
90
91
SECTION 7Appendices
DETAILED TRANSPORTATION ANAYSIS
Appendix 1 - Executive Summary of New Signals
Appendix 2 - Roundabout Capacity Check
Appendix 3 - Route 9 at Mattox Intersection Study
ENVIRONMNETAL SCORING
Appendix 4 - MARC Scoring Criteria
Appendix 5 - Environmental Justice
MEETING MINUTES
Appendix 6 - Meeting Minutes
DETAILED DESIGN DOCUMENTS
Appendix 7 - Design Plan and Profile Sheets
ROUTE 9 CORRIDOR STUDY
92