HomeMy Public PortalAbout2020-02-25 Item 6 PresentationMillbrae Recreation Center
02/25/2020 City Council Meeting
Monthly Update
Update
•02/07/2020 –Issued the Request for Qualification
•02/13/2020 –Held Pre-Qualification Conference
•12 attendees from 5 general contracting firms and 7 design firms
•02/14/2020 –Held Subcommittee Meeting to Discuss Cost Savings
Opportunities
•02/20/2020 –Issued Addendum #2 –extend submittal date 03/05/2020
•Concurrent Efforts
•Request for Proposals –Contract/Criteria Document
•Project Labor Agreement
•Updating City Website
•Planning fundraising Efforts
Schedule & Questions
Next Steps:
Questions?
DESIGN-BUILD PRE-QUALIFICATION (RFQ)FEB to MAR 2020
DESIGN-BUILD PROPOSALS (INCLUDING PLA)APRIL –JUNE 2020
AWARD OF DESIGN-BUILD CONTRACT JULY 2020
CONSTRUCTION DOCUMENTS & CONSTRUCTION JULY 2020 -
DECEMBER 2021
MOVE -IN & OCCUPANCY/SUBSTANTIAL COMPLETION/SOFT OPENING MARCH 2022