HomeMy Public PortalAboutGeneral Information
THE METROPOLITAN ST. LOUIS
SEWER DISTRICT
GENERAL INFORMATION ABOUT THE
PLAN REVIEW, APPROVAL, AND
CONSTRUCTION PERMITTING OF
PRIVATE DEVELOPMENT PROJECTS
APRIL 2019
GENERAL INFORMATION ABOUT THE PLAN
REVIEW, APPROVAL AND CONSTRUCTION
PERMITTING OF PRIVATE DEVELOPMENT
PROJECTS
FOR
THE METROPOLITAN ST. LOUIS SEWER
DISTRICT
The following information will assist District customers when obtaining
permits and construction approval for new projects as
required by The Metropolitan St. Louis Sewer District.
Previous editions were:
July 1995
December 1997
January 1998
November 2001
July 2004
September 2007
March 2014
June 2018
March 2019
DISTRICT BOUNDARIES
The boundaries of the District include all of the City of St. Louis and the majority of St. Louis
County. The District is bounded on the north by the Missouri River, the east by the Mississippi
River, the south by the Meramec River, and the west generally by State Highway 109.
DISTRICT OFFICE
The main office of the District is located at 2350 Market Street in the City of St. Louis. This
facility is located at Jefferson & Market. All inquiries related to the design or construction of
private or public facilities should be directed to the:
Engineering Department
Metropolitan St. Louis Sewer District
2350 Market Street
St. Louis, MO 63103
Tel: 314-768-6272
Fax: 314-768-6302
The Plan Review and Permit Office is open Monday through Friday from 8:00 a.m. until 4:30
p.m.
PROJECTS REQUIRING REVIEW BY THE DISTRICT
All public or private sewerage and drainage works proposed to be constructed, altered or
reconstructed by any person or corporation, public or private within the District boundaries will
require review and approval by the District. This includes any altering of any storm drainage
channel, site drainage or flood plain within the District’s boundaries.
DESIGN AND CONSTRUCTION CRITERIA
All projects must be designed and construction in accordance with the latest version of the
following:
1. The Metropolitan St. Louis Sewer District’s “Rules and Regulations and Engineering
Design Requirements for Sanitary Sewage and Stormwater Drainage Facilities.”
2. Standard Construction Specifications for Sewers and Drainage Facilities.
3. These documents are on the MSD website under “Plan Review Documents.”
PLAN REVIEW SUBMITTAL REQUIREMENTS
All of the following items must be submitted before the District will begin review of a project:
1. A submittal fee of $450.00.
2. Plan submittals are to be made online in electronic format on the District’s Accela
website at https://aca3.accela.com/STLMSD
OTHER PLAN REVIEW FEE REQUIREMENTS
1. Review Fee – In addition to the submittal fee, a review fee will be required. This fee
will be determined by the District and will be based on one of the following criteria:
$375.00 per acre
or
$1.40 per lineal foot of sewer extension
2. Connection Fee – A connection fee will be required for sanitary connections to the
public system. The amount of this fee is based on the domestic water tap size of the
proposed facility and are as follows:
¾” $ 1,126.00
1” $ 1,693.00
1.5” $ 3,111.00
2” $ 4,812.00
2.5” $ 6,485.00
3” $ 8,782.00
4” $ 14,453.00
6” $ 28,631.00
8” $ 45,644.00
10” $ 65,493.00
12” and larger Determined on a case by case basis
3. Impact Fees – Surcharge, recoupment or subdistrict fees have been imposed by the
District in some areas within the District boundaries. If there are any questions as to
whether or not the project is within an impact area, please contact:
Bob Miller 314-335-2053
Mark Kuelker 314-335-2064
4. Construction and As-Built Deposits – After plan approval and before issuance of
construction permits, the project owner will be required to submit cash deposits with
the District in the amount of 10% of the estimated construction cost for all public
sewer construction (100% for public pump stations) and for items that are private but
are to be constructed under MSD inspection (such as detention). The cash deposit for
stormwater BMP’s will be in the amount of 50% of the estimated construction cost
for all stormwater BMP’s. In addition to the construction deposits, an as-built deposit
will also be required. This deposit is computed based on the following criteria:
$1,000.00 plus $100.00 per structure.
CONSTRUCTION PERMIT REQUIREMENTS
All applications for permits for construction of sewer and drainage facilities, for
connection to such facilities and for repair of connection to such facilities shall be made
by a master drainlayer having a certificate of qualification or other applicable license to
perform work as a master drainlayer issued in his name by the Board of Examiners of
Plumbers and Drainlayers of the City of St. Louis or St. Louis County, or other applicable
licensing authority.
No construction or connection permit shall be issued unless the applicant shall first have
filed with the District a cash or corporate bond in an amount not less than ten thousand
dollars ($10,000.00) and a general liability certificate. All questions regarding
Performance Bonds should be directed to:
Terri Stewart 314-768-6288
CONSTRUCTION PERMIT FEES
The following construction permit and inspection fees must be paid at the time of
issuance of the permit:
House Connection Permit $75.00
Storm, Sanitary or Combined Construction Permit (with footage) $195.00
Construction Permits with no footage $75.00
Sanitary or Combined Fee $5.80/ft
Storm Inspection Fee $4.20/ft
Sampling Tee No Charge
Lift Station $4,000.00
Questions regarding issuance of construction permits should be directed to:
Dixie Bryant 314-768-6286
The permitted drainlayer is required to schedule the required inspection 24 hours in
advance by calling:
Erica Newton 314-768-6379
CONSTRUCTION APPROVAL
Construction approval by the District is required prior to the release on any occupancy
permits by the local authority. Questions regarding the status of the construction
approval of a project should be directed to:
Brian Dunn 314-335-2072
DEDICATION OF PUBLIC SEWER AND RELEASE OF DEPOSITS
Following construction approval, the public sewers will be dedicated to the District. A
dedication inspection of a single lot development will be done upon request immediately
after construction approval. Dedication inspections for multi-lot commercial and
residential developments will be done when 50% of the lots have been built and when
100% of the lots have been completed. One-half of the construction deposit will be
released after each inspection and all discrepancies are corrected. To request a dedication
inspection, contact:
Mike Shelton 314-768-6387
CUSTOMER SERVICE DIVISION AND MAINTENANCE DEPARTMENT
The Customer Service Division and Maintenance Department are available for
emergency situations regarding problems with all public sewers. In the event of an
emergency, calls should be directed to:
Customer Service/Dispatcher 314-768-6260
GENERAL STEPS FOR PLAN SUBMITTAL, REVIEW
AND ISSUANCE OF PERMITS
1. A preliminary conference to obtain informal guidance for the proposed project is
suggested and encouraged, especially if there are unusual site concerns or issues.
2. Plans are submitted for review, either hard copy or electronic plan, along with plan
submittal requirements. Electronic submittals should be made on the Accela Citizen
Access site at https://aca3/accela.com/STLMSD
3. Generally within 24 hours of the submittal of plans that have not been rejected due to
lack of required information, the project is assigned an MSD reference number and
assigned to a plan reviewer.
4. The owner and engineer are sent a notice that the plans were accepted for review.
5. Plans are reviewed by MSD personnel.
6. Review comments will be posted to the ACA website
(https://aca3.accela.com/STLMSD). The engineer and owner are also notified of the
District’s requirements with regard to detention Maintenance Agreement, easements,
encroachment requirements, Agreement to Dedicate, review fee, connection fee, etc.
7. Revised plans are resubmitted for MSD review as necessary until all MSD comments
have been addressed. In addition, easements are submitted for MSD review prior to
execution along with Maintenance Agreements, Agreement to Dedicate, etc.
8. When the plans have reached a point that the District believes that only minor
changes (or no changes) are required, the engineer will be notified that the final plans
for approval may be submitted. The owner and the engineer will also be notified of
all other outstanding requirements. In addition, the construction and as-built deposit
amounts are computed and the Cash Deposit Agreement is sent to the owner. These
deposits and the agreement do not need to be submitted prior to plan approval, but are
required prior to permitting.
9. Upon receipt of the final plans and the submittal of all other requirements, the plans
are approved by MSD and uploaded to the District’s Plan Review and Permitting
website. An approval letter is emailed to the Engineer, Developer and to the
appropriate MSD departments and government agencies.
10. Permits will only be issued to a licensed and bonded drainlayer after the receipt of the
construction and as-built deposits and the executed Cash Deposit Agreement. The
drainlayer will be required to pay the permit and construction inspection fees.
11. When problems are encountered in the field due to unforeseen conditions, the District
will consider allowing a “field change” process in lieu of the formal submittal of a
plan revision. In either case, the contractor should first notify the owner’s engineer as
to what the problem is; the engineer should then contact the MSD Plan Review
division. Field changes will generally be allowed, in lieu of a formal plan revision,
when no new easements or detailed hydraulic analysis are required. The contractor
should not proceed with the change until formal approval for either the revision or
field change has been granted.
FREQUENTLY ASKED QUESTIONS ABOUT THE DEVELOPMENT REVIEW
PROCESS
Q. What projects need to be submitted to MSD for review?
A. The District requires that all public or private sewerage and drainage works
proposed to be constructed, altered or reconstructed by any person or corporation,
public or private, within the District’s Boundaries, be submitted to the District for
review and approval. This includes any altering of any storm drainage channel,
site drainage or flood plain with those boundaries.
Q. Who at MSD should be contacted and when?
A. The applicant should contact the District’s Engineering Department/Plan Review
Section (314-768-6272) with any general questions regarding the submittal of a
project. If the applicant has questions about specific issues, it is recommended
(and encouraged) that either the Manager or one of the Team Leaderss of the
Section be contacted and a meeting arranged, if necessary.
John Grimm, P.E. Program Manager
(314) 768-2743
Bob Miller, P.E. Principal Engineer/Team Leader
Missouri, Meramec & Coldwater
Watersheds (314) 335-2053
Mark Kuelker, P.E. Principal Engineer/Teamleader
Bissell & Lemay watersheds (314) 335-2064
Q. What are the District’s design and plan submittal requirements?
A. The District’s design requirements are detailed in the “Rules and Regulations and
Engineer Design Requirements for Sanitary Sewage and Stormwater Drainage
Facilities” which was adopted by a resolution of the MSD Board of Trustees in
February 2018. It can be found on www.stlmsd.com
Q. What does the applicant need to submit to MSD for review?
A. To initiate the project review, MSD requires an online submittal of a set of plans
(prepared and sealed by an engineer registered in the State of Missouri) and a
submittal fee of $450.00. The Engineering Department should be contacted if
there is any question about the required submittal fee.
Q. What other fees are required to be paid by the applicant?
A. In addition to the submittal fee, the applicant must pay a review fee for the
project. This fee is based on the acreage of the site for site development, or the
footage of sewer, for projects only involving a sewer extension. The District’s
current fees are $375.00/acre or $0.1.40/lineal footage of a sewer extension.
The applicant will also be required to pay a connection fee , a subdistrict or
surcharge fee (Caulks Creek and Williams Creek) if the project involves a
connection to the public sanitary sewer system. The connection fee is based on
the domestic water tap size for the building. The need for and amount of the
payment of any subdistrict or surcharge fees will depend on the project’s location
and property size. If the applicant has any questions regarding these fees, please
contact John Grimm (314-768-2743) of the Engineering Department/Plan Review
Section.
In addition, the applicant will be required to pay a refundable construction deposit
(10% of cost) and as-built plan deposit ($1,000.00 plus $100.00 for each
structure) if the project involves the construction of sewers, which are to be
dedicated to the District. Stormwater BMP Deposit (50% of the cost) will be
required for projects that include Stormwater BMP’s. Payments must be in the
form of a cashier’s check or cash for the construction deposit, and cash or
personal check for the as-built deposit. These payments may be made after plan
approval, but must be paid prior to the issuance of construction permits.
Lastly, the applicant will be responsible for paying all document-recording fees
such as Maintenance Agreements and Easements.
Q. How does the review process generally work?
Please see the District’s online Plan Review and Permitting website at
https://aca3.accela.com/STLMSD
Once the plans have been corrected to address all of the District’s requirements,
and all other documents and fees have been paid, the District will process the plan
approval and notify the developer, the project engineer and the appropriate
municipal agencies of the approval. The developer will also be notified as to
whether or not permits, construction deposit and an-built deposit are required.
After the construction and as-built deposits have been paid, the developer’s
licensed drainlayer must take out permits from the District for the work, prior to
beginning construction. In addition, the MSD Construction Division (314-768-
6379) must be notified a minimum of 24 hours before start of construction.
Failure to take out the permits and notify the Construction Division may result in
the District withholding construction approval of the project, and the denial of the
District to issue any future permits to either the owner or the drainlayer. In other
words, construction approval is different than plan approval.
Q. What will happen if the work is done without submitting plans to MSD or getting
construction approval of the work?
A. Failure to get the proper approvals from the District could result in the
withholding and release of occupancy permits, as well as legal action by the
District.
COMMON ISSUES OR ERRORS WHICH DELAY THE PERMITTING PROCESS
A. MSD does not receive the needed information to thoroughly review the project.
1. Site design does not include detention when required.
2. Detention calculations not submitted.
3. Stormwater hydraulics not submitted.
4. Pump station design information not submitted.
5. Failure to submit a geotechnical report or adhere to MSD policy regarding
sinkholes.
6. The MSD “Rules and Regulations and Engineering Design Drainage
Facilities” are not adhered to.
B. Site design issues, which could delay the approval process.
1. Pump Stations – Pump stations will only be allowed if MSD determines that
there is feasible means of servicing a development by gravity.
a. Prior to formal submittal of improvement plans, sufficient
information should be provided to MSD in order for the District to
give “conceptual” approval of the pump station.
b. Pump stations should be designed to MSD Pump Station Division
standards. Review of the pump station design by the Engineering
and Maintenance Departments could take up to 4 to 6 weeks.
2. Building or structure encroachment over easement/sewer.
a. Prior to formal submittal of improvement plans, sufficient
information should be provided to MSD in order for the District to
determine if the proposed encroachment will be allowed. The sewer
in question will need to be inspected to determine its condition. This
inspection may take the MSD Maintenance Department from 4 to 6
weeks to schedule and complete.
b. Should the District allow the encroachment, a pier and grade beam
foundation design, approved by MSD, as well as the execution of an
encroachment agreement will be required.
3. Downstream storm or sanitary system is inadequate to handle the additional
flow from the proposed development. MSD may require the system to be
upgraded, at the developers cost, as a condition of the plan approval. The
District may also require offsite ponding or discharge easements if adjacent
property is impacted by the construction of the storm sewers.
4. Easement Vacations – While the request to vacate an easement will not delay
the MSD plan approval process, the developer should be aware that St. Louis
County, the City of St. Louis and most municipalities will not issue a building
permit until MSD’s (and other utilities) rights to any easements within the
building footprint have been vacated.
a. Easement Vacations are executed by the Director of Engineering
based upon recommendations by Engineering Department staff.
b. MSD staff will not recommend that a vacation be granted if there is
an existing sewer within the easement. If the existing sewer is to be
relocated, the easement will not be vacated until construction
approval for the relocated sewer has been given.
c. Depending on when the request for vacation is submitted to MSD, a
minimum of 4 to 6 weeks may be required for review of the
submitted documentation, preparation of the Easement Vacation and
submittal to the Director of Engineering for approval.
d. All MSD billing accounts held by the Petitioner must be current.
e. Recording Fees will be determined and requested by MSD from the
Petitioner once the easement vacation has been approved.
C. Items required before plan approval.
1. Review Fees
2. Connection Fees
3. Special Fees
4. Recoupment Fees
5. Executed Easement
6. Pump Station approval
7. Detention requirements
8. Forms completed as required for project (Agreement to Dedicate,
detention Maintenance Agreement, Indemnification Agreement,
Encroachment Agreement, etc.