HomeMy Public PortalAbout140_DPW Qtr 2 Report 2011DPW Quarter 2, FY 2011
Projects
1) 13th Street Crossover
Man Hrs Equipment Materials Labor Total
100.1 $0.00 $14,082.94 $12,512.50 $26,595.44
2) 2nd Avenue Crossover
Man Hrs Equipment Materials Labor Total
68.9 $0.00 $9,847.47 $8,612.50 $18,459.97
3) Installed water line at DPW Shop
Man Hrs Equipment Materials Labor Total
8 $0.00 $0.00 $1,000.00 $1,000.00
4) Cut back roads and graded
Man Hrs Equipment Materials Labor Total
96 $7,200.00 $0.00 $12,000.00 $9,677.50
5) Tybrisa Street Drainage Project
Man Hrs Equipment Materials Labor Total
12 $900.00 $696.00 $1,500.00 $3,096.00
Maintenance
Clean, Restock, and Maintaining Facilities, Restrooms, and Parks
Man Hrs Equipment Materials Labor Total
662 $254.76 $10,030.87 $16,550.00 $26,835.63
Cutting grass, Ditches, Trimming and Landscaping
Man Hrs Equipment Materials Labor Total
1603 $20,992.38 $220.88 $40,075.00 $61,288.26
Cleaning up Street Trash and Barrels (including street sweeper)
Man Hrs Equipment Materials Labor Total
407 $12,419.64 $0.00 $10,175.00 $22,594.64
Cleaning up Beaches and Trash
Man Hrs Equipment Materials Labor Total
108 $0.00 $0.00 $2,700.00 $2,700.00
Fixing, Replacing, and Installing New Signs
Man Hrs Materials Materials Labor Total
12 $87.56 $0.00 $300.00 $387.56
Island-wide Road Repair & Maintenance
Man Hrs Equipment Materials Labor Total
57.5 $0.00 $1,806.88 $7,187.59 $8,994.38
Maintaining Beaches (Swings, Mobi-Mats, and Crossovers)
Man Hrs Equipment Materials Labor Total
11.5 $0.00 $0.00 $287.50 $287.50
Building Maintenance
- Campground Restroom Renovation
Man Hrs Materials Labor Total
960 $0.00 $24,000.00 $24,000.00
- 16th Street Parking Lot (Run power to Info Booth)
Man Hrs Materials Labor Total
12 $245.63 $300.00 $545.63
- Painting City Hall
Man Hrs Materials Labor Total
96 $116.91 $2,400.00 $2,516.91
Changes to Parking Layout
Man Hrs Equipment Materials Labor Total
25 $0.00 $0.00 $626.00 $626.00
Holidays & Festivals
Holiday Lighting
Man Hrs Equipment Materials Labor Total
536.5 $11,131.00 $907.53 $13,412.50 $25,451.03
Halloween
Man Hrs Equipment Materials Labor Total
4.5 $40.00 $0.00 $112.50 $152.50
Pirate’s Fest
Man Hrs Equipment Materials Labor Total
38 $1,635.00 $101.97 $950.00 $2,686.97
Work Orders
DPW, Building Maintenance and Parks & Rec. have completed 58 Work Orders for the following departments this quarter:
YMCA - 9
Campground - 8
Police Dept. - 4
M.S.C. - 5
Fire Department - 2
DPW - 7
Facilities, Parks, and Restrooms - 10
City Hall & Resident Requests and Observations - 12
TEMA - 1
Fleet Department
The Fleet Department has completed 100 Service and Repair Orders for the following departments this quarter:
Campground - 1 Parts: $0.00 Labor: $50.00
DPW - 42 Parts: $6,699.81 Labor: $4,129.16
Fire Department - 8 Parts: $441.46 Labor: $350.00
Parking - 4 Parts: $561.88 Labor: $625.25
Police Dept. - 29 Parts: $570.37 Labor: $3,425.00
Water/ Sewer - 16 Parts: $1,999.42 Labor: $819.25
Totals: Parts: $10,272.94 Labor: $9,398.66 Total: $19,671.60
Total time spent on research, ordering parts, inventory, paperwork and filing, and cleaning the shop: 488 man hours Cost in labor: $12,200.00
Purchasing
199 Purchase Orders have been made this quarter amounting to $105,049.02
Major Purchases
-14th Street Drainage Project Carroll & Carroll $52,892
-1 Month Grader Rental Low Country $4,338.00
-Repair 10 Ton A/C at Gym Weather Doctors $5,564.00
- Pull Tarps for Trucks LoAlbo $1,904.00
Completed Training:
One Employee is currently enrolled in Schools or Colleges outside of work –
Jackie Cary
GADOT Setting up work zone – Entire department
OSHA Safety in Woodbine – Sandy Herring, Chris Shook, Matt Moses