HomeMy Public PortalAboutAGCSITE APR 2022 PresentationFY 2023 Capital
Improvement
Program -
Proposed
Construction
Services
Rich Unverferth, P.E.
Director of Engineering
April 20, 2022
Technology Overview
•Participants are in listen-and-view mode
•There are several ways to engage
•Type your question using Q/A icon at the bottom of your screen
at any time (even before the Q/A portion has begun)
•Everyone can read all questions posed and you can “Upvote”
questions you want answered
•Ground Rules: General questions only during live Q&A
•Specific project questions should be directed to Allen Muehlher,
AFMUEH@stlmsd.com
Today’s Agenda
•Introductions and About MSD
•Proposed Program –Summary
•Proposed Program –Ongoing Construction
•Proposed Program –Procurements Needed
•Proposed Program –Work Order Repairs
•Proposed Program –Contingency Projects
•Proposed Program –Looking Ahead
•Prequalification Process
•Small Contractor Program
•Bid Schedule and Plan Room
•Prevailing Wage Program
•Construction Management Division Staffing
•Diversity
•Executive Director’s Update
•Questions and Answers
MSD Overview & Details
•Government Utility
•State Constitution
•Voter Approved Charter
•6 Member Board of Trustees
(3 City & 3 County)
•Two utilities: Wastewater & Stormwater
•520 square mile service area
•All of St. Louis City
•87% of St. Louis County
•~1,300,000 customers
•88 municipalities served
•7 Treatment Plants
•350+ million gallons per day of wastewater treated
•4,500+ miles of sanitary sewers
•1,400+ miles of combined sewers
•3,000+ miles of stormwatersewers
•4th largest sewer system in the United States (as measured by miles of sewers handling wastewater)
Proposed Program –FY2023
•Summary
Proposed Program –FY2023
•Summary
Proposed Program –FY2023
•Ongoing Construction, Supplemental Funding
Project Name Additional
Appropriation:
BADEN CITYSHED MITIGATION BASINS (CALVARY, FREDERICK, PARTRIDGE AND TILLIE) -
SEPARATION SEWERS
2,400,000
CAULKS CREEK A PUMP STATION (P-750) IMPROVEMENTS 3,200,000
CAULKS CREEK FORCEMAIN (RIVER VALLEY RD TO L-52)2,500,000
HARLEM -BADEN RELIEF PHASE IV (HEBERT) (GOODFELLOW TO HAMILTON)1,279,000
LOWER MERAMEC RIVER SYSTEM IMPROVEMENTS -BAUMGARTNER TO FENTON WWTF
TUNNEL
48,000,000
LOWER MERAMEC WWTF EXPANSION PHASE II 30,000,000
MC-02 WATSON TO EDGAR RD SANITARY RELIEF (SKME-580A)5,954,000
PRICE TO PIONEER SANITARY RELIEF 2,507,000
95,840,000
Proposed Program –FY2023
•Ongoing Construction
Proposed Program –FY2023
•Ongoing Construction
Proposed Program –FY2023
•Ongoing Construction
Proposed Program –FY2023
•Ongoing Construction
Proposed Program –FY2023
•Ongoing Construction
Proposed Program –FY2023
•Ongoing Construction
Proposed Program –FY2023
•Ongoing Construction
Proposed Program –FY2023
•Ongoing Construction
Proposed Program –FY2023
•Procurements Needed
Construction
Category
# Bid
Opportunities
FY23
Construction
Budget
CIPP 9 29,518,000
Facilities 6 132,900,000
Pump Stations 6 8,670,000
Sewers 26 49,586,000
PIR 2 1,402,000
Tunnels 0 0
Bank Stabilization 0 0
Total 49 222,076,000
Proposed Program –FY2023
•Procurements Needed (CIPP)
Project Name Description Budget
NORTH FEE FEE CREEK PUBLIC I/I REDUCTION REHABILITATE 90,000 FEET OF THE PUBLIC SEWER SYSTEM
USING THE CURED IN PLACE PIPE METHOD.6,000,000
BISSELL -COLDWATER -MISSOURI -MERAMEC PUBLIC I/I
REDUCTION (2023) CONTRACT E
REHABILITATE 47,900 FEET OF THE PUBLIC SEWER SYSTEM
USING THE CURED IN PLACE PIPE METHOD.4,251,000
BISSELL -COLDWATER -MISSOURI -MERAMEC PUBLIC I/I
REDUCTION (2023) CONTRACT D
REHABILITATE 54,900 FEET OF THE PUBLIC SEWER SYSTEM
USING THE CURED IN PLACE PIPE METHOD.3,594,000
STORMWATER INFRASTRUCTURE REPAIRS (REHABILITATION)
(2023)
CONSTRUCT CURED-IN-PLACE PIPE INSTALLATION FOR
STORMWATER SYSTEM REHABILITATION AND REPAIR, AS
NEEDS ARE IDENTIFIED BY SEWER CLEANING AND INSPECTION
EFFORTS.
3,000,000
BISSELL -COLDWATER -MISSOURI -MERAMEC PUBLIC I/I
REDUCTION (2023) CONTRACT C
REHABILITATE 41,900 FEET OF THE PUBLIC SEWER SYSTEM
USING THE CURED IN PLACE PIPE METHOD.2,663,000
FF-15 AND FF-16 SANITARY RELIEF PHASE II REHABILITATION REHABILITATE 4,500 FEET OF 18-INCH TO 30-INCH DIAMETER
SEWER. REHABILITATE 10 MANHOLES.2,650,000
INFRASTRUCTURE REPAIRS (REHABILITATION) (2023)
CONTRACT A
CONSTRUCT CURED-IN-PLACE PIPE INSTALLATION FOR SYSTEM
REHABILITATION AND REPAIR, AS NEEDS ARE IDENTIFIED BY
SEWER CLEANING AND INSPECTION EFFORTS.
2,500,000
INFRASTRUCTURE REPAIRS (REHABILITATION) (2023)
CONTRACT B
CONSTRUCT CURED-IN-PLACE PIPE INSTALLATION FOR SYSTEM
REHABILITATION AND REPAIR, AS NEEDS ARE IDENTIFIED BY
SEWER CLEANING AND INSPECTION EFFORTS.
2,500,000
BISSELL -COLDWATER -MISSOURI -MERAMEC PUBLIC I/I
REDUCTION (2023) CONTRACT F
REHABILITATION OF THE PUBLIC SEWER SYSTEM USING THE
CURED IN PLACE PIPE METHOD, TO REDUCE PUBLIC I/I.2,360,000
Proposed Program –FY2023
•Procurements Needed (Facilities)
Project Name Description Budget
BISSELL & LEMAY WWTF FLUIDIZED BED INCINERATORS CONSTRUCT FLUIDIZED BED INCINERATORS AT THE BISSELL
AND LEMAY WASTEWATER TREATMENT FACILITIES, TO
INCLUDE REDUNDANT SLUDGE ACCEPTANCE SYSTEMS AND
SOLIDS HANDLING SYSTEM IMPROVEMENTS.
101,000,000
BISSELL POINT WWTF FINE SCREEN, CONCRETE AND GATE
IMPROVEMENTS
INSTALL FINE SCREENS TO REPLACE FAILING COMMINUTORS,
REPAIR SLUICE GATES AND COMPONENTS, AND CONCRETE.
18,000,000
COLDWATER CREEK WWTF REPAIRS AND IMPROVEMENTS
(2023)
AERATION CONTROL BUILDING IMPROVEMENTS, INCLUDING
REPLACEMENT OF AERATION CONTROL PIPING AND
INSTRUMENTATION, AND INSTALLATION OF A PARALLEL
BOSKER SWITCH TRACK SYSTEM AND NEW BOSKER UNITS.
5,000,000
HARLEM CITYSHED MITIGATION BASINS (ASHLAND AND
ESSEX)
CONSTRUCT 2 STORMWATER DETENTION BASINS, AND 2 RAIN
GARDENS.4,000,000
LEMAY WWTF REPAIRS AND IMPROVEMENTS (2023) (GRIT
TANKS AND SECONDARY CLARIFIER DUCT BANK)
CONSTRUCT CONCRETE REPAIRS, REPLACE SECONDARY
CLARIFIER DUCT BANK, AND RENEW 4 GRIT TANKS.4,000,000
LEMAY WWTF AERATION BLOWER AND POWER DISTRIBUTION
IMPROVEMENTS
REPLACE AERATION BLOWER MOTORS, DRIVES, AND
CONTROLS, AND MAKE IMPROVEMENTS TO LEMAY
SUBSTATION RELAYS AND POWER DISTRIBUTION SYSTEM.
900,000
Proposed Program –FY2023
•Procurements Needed (Pump Stations)
Project Name Description Budget
PUMP STATION MANLIFT REPLACEMENT REPLACE MANLIFTS IN VARIOUS PUMP STATIONS.
4,000,000
EARTH CITY UPS PUMP STATION (P-702) REPLACEMENT
PHASE II
CONSTRUCT REPLACEMENT OF PUMP STATION P-702, 266
FEET OF 8-INCH FORCE MAIN, AND 128 FEET OF 8-INCH TO
72-INCH SANITARY SEWER.
1,800,000
LEMAY 1 PUMP STATION (P-301) COOLING TOWER
REPLACEMENT
REMOVE AND REPLACE EXISTING COOLING TOWERS, PIPING,
AND VALVES 1,130,000
ROBYN HILLS NUMBER 1 PUMP STATION (P-417)
REPLACEMENT
REPLACE PUMP STATION P-417.
780,000
PUMP STATION FALL PROTECTION UPGRADES -PHASE I CONSTRUCT INTEGRATED FALL PROTECTION GRATING AND
HATCH MODIFICATIONS WHERE NECESSARY OVER EXISTING
WET WELLS, AND INSTALL SAFETY POST ANCHOR PLATES.
500,000
FABICK PUMP STATION (P-444) IMPROVEMENTS (SKME-404E)CONSTRUCT MODIFICATIONS TO THE FABICK PUMP STATION
TO MEET CURRENT STANDARDS.460,000
Proposed Program –FY2023
•Procurements Needed (Sewers)
Project Name Description Budget
BLACK CREEK -HADDINGTON COURT RELIEF SEWERS CONSTRUCT 7,955 FEET OF 8-INCH TO 42-INCH SANITARY
SEWER, AND ELIMINATE CONSTRUCTED SSO OUTFALLS BP-
013, BP-017, AND BP-151.
13,000,000
HARLEM BADEN RELIEF PHASE IV (HEBERT) -HAMILTON TO
DARVER TRUNK SEWER
CONSTRUCT 3,660 FEET OF 12-INCH TO 108-INCH STORM
AND COMBINED SEWERS, AND 900 FEET OF PIPE IN TUNNEL.6,000,000
FLORISSANT/DUNN SANITARY RELIEF (ST. ANTHONY LN TO I-
270)
CONSTRUCT 6,170 FEET OF 8-INCH TO 24-INCH SANITARY
SEWER.4,910,000
JEFFERSON BARRACKS TUNNEL CONSOLIDATION SEWERS CONSTRUCT 5,700 FEET OF 8-INCH TO 36-INCH SANITARY
SEWER, AND REHABILITATE 2,800 FEET OF 30-INCH TO 36-
INCH SANITARY SEWER, TO CONVEY FLOW TO THE NEW
JEFFERSON BARRACKS TUNNEL.
3,400,000
INFRASTRUCTURE REPAIRS (REHABILITATION) (2023)
CONTRACT C
CONSTRUCT GEOPOLYMER LINING REHABILITATION AT 6
MISSISSIPPI RIVER OUTFALLS.3,310,000
SAYLESVILLE SANITARY RELIEF (SAYLESVILLE DR TO S
GREENTRAILS DR)
CONSTRUCT 3,920 FEET OF 18-INCH SANITARY SEWER, AND
280 LINEAR FEET OF 8 TO 12 FEET HIGH HEAVY STONE
REVETMENT BANK STABILIZATION.
2,850,000
LARIMORE STORM SEWER CONSTRUCT 4,880 FEET OF 12-INCH TO 54-INCH STORM
SEWER.2,600,000
Proposed Program –FY2023
•Procurements Needed (Sewers)
Project Name Description Budget
AMBLEWOOD SANITARY RELIEF (WATERFORD DR TO
BIRCHBARK DR)
CONSTRUCT 2,400 FEET OF 10-INCH TO 24-INCH SANITARY
SEWER.
2,453,000
LAMBERT AIRPORT RESTRICTED ACCESS ASSETS INSPECTION
AND REPAIR
PERFORM CCTV INSPECTION, REPAIR AND CIPP
REHABILITATION OF 48,000 FEET OF SANITARY SEWER AND
26,000 FEET OF STORM SEWER.
2,000,000
WHITE PLAINS SANITARY RELIEF (SALTBOX DR TO CEDAR CREEK
RD)
CONSTRUCT 2,785 FEET OF 8-INCH TO 15-INCH SANITARY
SEWER.
1,800,000
WEBSTER GROVES TRUNK E SANITARY REHABILITATION AND I/I
REDUCTION PHASE IV
CONSTRUCT 3,200 FEET OF 12-INCH TO 21-INCH STORM
SEWER, AND PERFORM PRIVATE I/I REDUCTION AT 40
PROPERTIES.
1,300,000
GLENFIELD SANITARY RELIEF (WATSON WOODS CT TO S
LINDBERGH BLVD)
CONSTRUCT 2,400 FEET OF 8-INCH TO 12-INCH SANITARY
SEWER.
1,130,000
NEWPORT LANDING PUMP STATION (P-480) ELIMINATION CONSTRUCT 1,555 FEET OF 8-INCH SANITARY SEWER.
DECOMMISSION AND ABANDON EXISTING PUMP STATION P-
480 AND ASSOCIATED FORCEMAIN.
626,000
BALLMAN DRIVE 300 BLOCK STORM SEWER CONSTRUCT 670 FEET OF 18-INCH TO 24-INCH STORM SEWER.
600,000
NORTH NEW FLORISSANT -FOX RUN STORM SEWER CONSTRUCT 1,230 FEET OF 12-INCH TO 36-INCH STORM
SEWER.600,000
Proposed Program –FY2023
•Procurements Needed (Sewers)
Project Name Description Budget
LAMBERT AIRPORT RESTRICTED ACCESS ASSETS INSPECTION
AND REPAIR
PERFORM CCTV INSPECTION, REPAIR AND CIPP
REHABILITATION OF 48,000 FEET OF SANITARY SEWER AND
26,000 FEET OF STORM SEWER.
500,000
CROSS TIMBERS #705 SANITARY REPLACEMENT CONSTRUCT 410 FEET OF 8-INCH DIAMETER SANITARY
SEWERS, 515 FEET OF 2-INCH DIAMETER FORCE MAIN, AND
FOUR (4) GRINDER PUMP SYSTEMS.
425,000
GREENBRIAR #2 PUMP STATION (P-448) ELIMINATION CONSTRUCT 1,080 FEET OF 8-INCH SANITARY SEWER.
DECOMMISSION AND ABANDON EXISTING PUMP STATION P-
448 AND ASSOCIATED FORCEMAIN.
425,000
ROXBURGH DR SANITARY RELIEF CONSTRUCT 530 FEET OF 21-24 INCH SANITARY SEWER, AND
ELIMINATE CONSTRUCTED SSO BP-018.400,000
BEAUCAIRE DRIVE -MARK DRIVE -MONACO DRIVE STORM
SEWER
CONSTRUCT 305 FEET OF 12-INCH STORM SEWER.
325,000
DEARBORN DR STORM SEWER CONSTRUCT 355 FEET OF 15-INCH TO 24-INCH STORM
SEWER.320,000
BANFF SANITARY RELIEF (CAITHNESS RD TO LANARK RD)CONSTRUCT 342 FEET OF 12-INCH SANITARY SEWER.
167,000
SAYLESVILLE SANITARY RELIEF (SAYLESVILLE DR TO S
GREENTRAILS DR)
CONSTRUCT 3,920 FEET OF 18-INCH SANITARY SEWER, AND
280 LINEAR FEET OF 8 TO 12 FEET HIGH HEAVY STONE
REVETMENT BANK STABILIZATION.
150,000
LITZSINGER #10412 STORM SEWER IMPROVEMENTS CONSTRUCT 250 FEET OF 12-INCH TO 18-INCH STORM
SEWER.115,000
LONGFORD DRIVE 1851 STORM SEWER CONSTRUCT 134 FEET OF 12-INCH TO 24-INCH STORM
SEWER.95,000
MEADOW CREEK LN 508 STORM SEWER CONSTRUCT 200 FEET OF 12-INCH STORM SEWER.
85,000
Proposed Program –FY2023
•Procurements Needed (PIR)
Project Name Description Budget
HATHAWAY DRIVE SANITARY RELIEF CONSTRUCT 1,042 FEET OF 10-INCH SANITARY SEWER AND
PERFORM PRIVATE I/I REDUCTION AT 6 PROPERTIES.902,000
LINDSAY -ST. ALBERT PRIVATE I/I REDUCTION
CONSTRUCT 870 FEET OF 8-INCH TO 12-INCH SANITARY
SEWER AND PERFORM PRIVATE I/I REDUCTION AT 27
PROPERTIES.
500,000
Proposed Program –FY2023
•Work Order Repairs
Project Name Description Budget
INFRASTRUCTURE REPAIRS (WASTEWATER) (2023)CONSTRUCT REPAIR OR REPLACEMENT OF WASTEWATER
INFRASTRUCTURE DISTRICTWIDE.9,000,000
STORMWATER INFRASTRUCTURE REPAIRS (2023)CONSTRUCT REPAIR OR REPLACEMENT OF STORMWATER
INFRASTRUCTURE THROUGHOUT THE DISTRICT.4,000,000
INFRASTRUCTURE REPAIRS (FACILITIES) (2023)
CONSTRUCT REPAIR, REPLACEMENT, OR IMPROVEMENT
PROJECTS TO ADDRESS NEEDS AT FACILITIES SUCH AS
TREATMENT PLANTS AND PUMP STATIONS.
3,000,000
Proposed Program –FY2023
•Contingency Projects
Project Name Description Budget
HALL STREET STORM SEWERS CONSTRUCT 5,500 FEET OF 12-INCH TO 66-INCH STORM SEWER, 523 FEET OF 72-
INCH TUNNEL, AND 16,800 FEET OF DRAINAGE DITCH ALONG HALL STREET.
7,000,000
CAULKS CREEK PUMP STATION B (P-751)
RELOCATION
RECONSTRUCT PUMP STATION AT NEW LOCATION.5,000,000
WW-2 AND WW-3 WARSON WOODS SANITARY
RELIEF
CONSTRUCT 10,600 FEET OF 8-INCH TO 24-INCH SANITARY SEWER. ELIMINATE
CONSTRUCTED SSO OUTFALLS BP-156, BP-158, AND BP-501.
5,000,000
SCADA SYSTEM UPGRADE CONSTRUCT SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA)
IMPROVEMENTS TO ALLOW FOR ACTIVE CONTROLS TO MANAGE WET WEATHER
FLOWS.
5,000,000
HARLEM CITYSHED MITIGATION BASINS
(ASHLAND AND ESSEX) -SEPARATION SEWERS
CONSTRUCT 16,320 OF STORM SEWER FOR SOFT SEPARATION.4,800,000
HALLSTEAD STORM CHANNEL PHASE IV (MCBJ-
230)
CONSTRUCT 1,220 FEET OF 45-FOOT WIDE BY 12-FOOT HIGH VERTICAL WALL
CHANNEL, FROM VORHOFF DRIVE SOUTH TO HUDSON DRIVE.
4,200,000
NEW ENGLAND TOWN CLIFF CAVE PUMP
STATION (P-323) IMPROVEMENTS
CONSTRUCT 3,500 FEET OF 8-INCH TO 12-INCH SANITARY SEWER, 1,600 FEET OF 6-
INCH FORCEMAIN, AND REPLACE SANITARY PUMP STATION P-323.
4,000,000
VALLEY SANITARY RELIEF PHASE III CONSTRUCT 6,960 FEET OF 8-INCH TO 15-INCH SANITARY SEWER.4,000,000
GC-06 GRAVOIS CREEK TO BRIARSTONE AND
GATES SANITARY RELIEF PHASE II
CONSTRUCT 4,700 FEET OF 8-INCH TO 18-INCH SANITARY SEWER, AND ELIMINATE
CONSTRUCTED SSO OUTFALL BP-382.
3,758,000
UPPER BADEN SANITARY RELIEF (JENNINGS
STATION RD TO OAKRIDGE BLVD)
CONSTRUCT 4,100 FEET OF 15-INCH TO 27-INCH SANITARY SEWER, AND ELIMINATE
CONSTRUCTED SSO OUTFALL BP-001.
2,974,000
FILLMORE PUMP STATION (P-308)
REHABILITATION
REHABILITATE THE MECHANICAL AND ELECTRICAL SYSTEMS, AND THE BUILDING
ENVELOPE.
1,800,000
FRIEDENS (PARTIAL) I/I REDUCTION (CHAIN OF
ROCKS DR AND FONTAINE PL)
CONSTRUCT 3,000 FEET OF 8-INCH TO 12-INCH STORM SEWER.1,750,000
Proposed Program –FY2023
•Contingency Projects
Project Name Description Budget
SUTHERLAND LANSDOWNE COMBINED SEWER
REPLACEMENT
REPLACE 470 FEET OF 10-INCH AND 310 FEET OF 15-INCH COMBINED SEWERS.1,215,000
MISSISSIPPI FLOODWALL ORS PUMP STATIONS -
LADDER REPLACEMENTS
REPLACE FIXED STEEL LADDERS INSIDE AND OUTSIDE OF PUMP STATIONS.1,200,000
SPIRIT OF ST. LOUIS 1 PUMP STATION (P-735)
REPLACEMENT
REPLACE PUMP STATION P-735.1,085,000
VALLEY VIEW PUMP STATION (P-734)
REPLACEMENT
REPLACE PUMP STATION P-734, AND 430 FEET OF FORCE MAIN.600,000
HIGHGATE -ENFIELD STORM SEWER CONSTRUCT 945 FEET OF 12-INCH TO 24-INCH STORM SEWER 520,000
FAIRWAY CT 3901 BANK STABILIZATION CONSTRUCT 320 FEET OF 11 TO 15 FOOT HIGH HEAVY STONE REVETMENT BANK
STABILIZATION.
487,000
OUTER LADUE AND CHIPPER STORM SEWER CONSTRUCT 1,125 FEET OF 12-INCH TO 30-INCH STORM SEWER, AND 5 RAIN
GARDENS.
434,000
GLENMARY TO WHITE ROSE STORM
IMPROVEMENTS
CONSTRUCT 755 FEET OF 24-INCH TO 36-INCH STORM SEWER 380,000
DENNIS AND KAPPEL STORM SEWER CONSTRUCT 970 FEET OF 15-INCH TO 27-INCH STORM SEWER.334,000
BALLAS RD. -BALWYCK LN. BANK STABILIZATION CONSTRUCT 520 FEET OF COMPOSITE BANK REVETMENT AND ONE GRADE
CONTROL STRUCTURE.
322,000
WHITEHALL CT -PINE AVE STORM SEWER CONSTRUCT 510 FEET OF 12-INCH TO 18-INCH STORM SEWER 270,000
SHERWOOD DR. #2790 STORM SEWER CONSTRUCT 480 FEET OF 12-INCH TO 15-INCH STORM SEWER.176,000
Proposed Program –FY2023-27
•Looking Ahead
Fiscal Year
Anticipated
Construction
Budget
Estimated
# of bid
opportunities
FY23 335,916,000 49
FY24 480,635,000 67
FY25 425,669,000 31
FY26 286,012,000 29
FY27 205,580,000 34
Total 1,733,812,000 210
Proposed Program –FY2024
•Procurements Needed
Construction
Category
Estimated # of
Bid Opportunities
FY24 Budget
CIPP 4 14,110,000
Facilities 3 13,000,000
Pump Stations 9 41,620,000
Sewers 43 101,336,000
PIR 2 2,086,000
Tunnels 0 0
Bank Stabilization 6 7,243,000
Total 67 179,395,000
Proposed Program –FY2025
•Procurements Needed
Construction
Category
# Projects Construction
Budget
CIPP 3 14,000,000
Facilities 4 60,500,000
Pump Stations 1 5,000,000
Sewers 21 82,222,000
PIR 0 0
Tunnels 0 0
Bank Stabilization 2 7,200,000
Total 31 168,922,000
Proposed Program –FY2026
•Procurements Needed
Construction
Category
# Projects Construction
Budget
CIPP 4 17,340,000
Facilities 2 10,400,000
Pump Stations 4 6,400,000
Sewers 19 28,312,000
PIR 0 0
Tunnels 0 0
Bank Stabilization 0 0
Total 29 62,452,000
Proposed Program –FY2027
•Procurements Needed
Construction
Category
# Projects Construction
Budget
CIPP 4 22,000,000
Facilities 6 18,385,000
Pump Stations 7 9,685,000
Sewers 15 28,810,000
PIR 1 2,000,000
Tunnels 1 72,000,000
Bank Stabilization 0 0
Total 34 152,880,000
Proposed Program –FY2023-27
•Looking Ahead –Design Build Projects
Fiscal Year Project
23 BISSELL & LEMAY WWTF FLUIDIZED BED
INCINERATORS
24 ELTORA WET WEATHER STORAGE FACILITY
25 MISSISSIPPI FLOODWALL ORS PUMP STATIONS
REHABILITATION PHASE IV
Prequalification Process
•Contractors must be prequalified to bid
•Prequalification applications are accepted at any time
•https://msdprojectclear.org/doing-business/capital-improvement-replacement-program/capital-construction/prequalification-process/
•Contractors are prequalified for Specific Work Categories
•Annual Renewal of Prequalification is required
Small Contractor Program (SCP)
•Program Purpose
•SCP Project Size
•SCP Typical Work Types
•https://msdprojectclear.org/doing-
business/capital-improvement-replacement-
program/small-contractor-program/
Michael Buechter, P.E.
Program Manager, Design
Engineering Division
Phone: (314) 768-2772
Fax: (314) 768-6341
E-mail: mtbuec@stlmsd.com
Bid Schedule
•https://msdprojectclear.org/doing-
business/capital-improvement-replacement-
program/
Plan Room
•https://www.stlmsdplanroom.com/
Prevailing Wage Program
•https://msdprojectclear.org/doing-
business/prevailing-wage/
Construction Management Division Staffing
https://msdprojectclear.org/about/our-
organization/departments/engineering/
pr()iect
wastewater + stormwater
CONSTRUCTION ANA EMENT DIVISION
Capital Construction
Program Manager
Kottliofi (C11)
Civil Engineer
([Open} (C 7)
Principal
E 1eer
Niece, 6{C 14,
Civil
Engineer Sr
1—
PiOnSell IC 'j
DIvielon
Irspetor
B,ricren )C 6 )
>pivifion
Inspector
Schemer IC 6)
Eng Corist
Supervisor
Wee)nirik (C $)
Resident
R epeeior
Nichols, WIC 3,)
Resident
Ir131poi rr
( j {C 3)
Cons'. h
Inspector Sr.
Duncan (A 11)
Const
Inspector Sr.
(Open' IA 11)
Const
inspector Sr.
(OpenI IA 11)
Capital Constriction
program Manager
Bergmann (C 11)
Resident
Intsgx. I.i}r
(Open) (G. 3)
Eng Cons!
Supervisor
[Day (C 6)
Civil Engineer
Senior
:„m1111, J. (C sj
Civil Engineer
)v"r'arren (C 7]
RelAdani
Inspector
Olomenkarrp
(LC 31
Genet.
Inspector S . Barry (A i
Eng Consi
S+llpervlsfsr
McFarland (C 3i
F esident
Inspector
pro (C 3)
Conat.
Inspector Sr.
Biondi:. rA 111
Wit.
Impede( Sr_
JackAson, D.
Const.
Inspector $r.
Roth, J. (A 11j
C#»I-
Inspector Sr_
Riser (A 11)
to-nst.
Inspector Sr.
Virginia (A 11)
Canal.
Inspector Sr.
Schell (A 11 )
Covet.
Inspector Sr.
po.en) (A • 1
Capital Construction
Program Manager
White. K. (C 11)
Senior
Civil Engineer
Martin (C. 9) I
Eng Const
Supervisor
❑ietiker (C 1 L
Re n1
InSetliOr
licks 3)
Resident
In
Stroud (C 3
Crpivil, �E,,,ngineer
(01; 11)I.C7)
Asst. Frc irxs-
Ware; :2 s
Eng Cons)
Si II.II.I41 i-Di
F(.oleas 1i2 a.)
Cpnst.
Inspector Sr.
Men, G. (A 11)1
Canal.
Inspector Sr_
Lowe (A 11)
Resident
Inspector
Jarvis, D. (C, 3)
�rt3t.
Inspect(
Beizhir to 1 lj
Const.
Inspector Sr.
McCarty (AA 11)
Inspector Sr_
Johnson. } S
Consa.
IllSgeder $r
M te'y IA 11)
Const,
Inspector Sr_
(Open) (A 11)
Const.
Irispec#a` Sr,
(Olpen)(A11)
pr()iect
wastewater + stormwater
CONSTRUCTION MANAGEMENT DIVISION
GIS&CA➢)
Technician
Kin:ir,Poi. ( L11)
Development Inspection
Engineering
Construction Supervisor
Shelton (C 8)
Rosidml
Irffipr?or
Treat (C 3)
Cow Ir qi n
H.
Dee,rrreg (A 10)
Con41. lrecpaCtor
Episa {A 10)
Coral. Inspe for
Jag (A 10)
Conan Inspector
Pilucha to 10)
C0nsl Inspector
R0IN, V (A 10)
Cr1naL Inspeclar
Steible {A 10)
r sidont
Inspector
Bormenn (C 31
Corosl Inspector
Bell (A 10)
CcrnSL. Ins(*elor
Davls (A 10)
Garrst. Inaceelor
Peterson LA 10)
Conet. Inspector
Potft , R (A io)I
col. Inr.Gxyc10r
{Ogler] l IA 10)
Division
Inspector
)unn (c 6
GIVCAD
Teettiklen
'craves (A 111
-ICcinst Inspector
'wept*? (A 10)
HOonst. Inspector
(Open) (A TO:,
Ad inistrative
Support
Administrative Support
Manager
Silberschlag (C 5
S tlans
As
sociate
Rulo {A 9)
Oboe
Associate
Brower (A 8i
Office
Carpunky (AB)
came*
Associate
Potter `A 8)
Noc)a
Aesoclate
Stage. (A 8}
Office
Associate
ConaL Irrspeclar
(Open) {A 10)
Metropolitan
St. Louis
Sewer District
Disparity Study
and Workforce
Study Update
April 20,
2022
2
Race and Gender-Conscious Prime Contract Remedies
•Apply prime incentive credits for engineering professional
services and non-engineering professional services
contracts.
•Implement a Sheltered Market Program to increase
MWSBE utilization.
•Implement a Mentor-Protégé Program to increase MWSBE
capacity.
Summary
of
Disparity
Study
Recommen
dations
Race and Gender-Conscious Subcontract Remedies
•Set subcontract MWBE goals for the ethnic and gender
groups with a statistically significant disparity.
•Building Construction –21% MBE and 10% WBE
Subcontracting Goals
•Non-Building Construction –10% MBE and 10% WBE
Subcontracting Goals
•Engineering Professional Services –18% MBE and
13% WBE Subcontracting Goals
•Revise MWBE participation requirements for truckers.
3
Race and Gender-Neutral Recommendations
•Modify the electronic subcontract tracking system to
report both MWBE and non-MWBEs subcontractors.
•Require reporting on all MWBE’s and non-MWBE
subcontractors on all bid and proposal contracts.
Workforce Recommendations
•Construction –37% Minority and 11% Women
•Construction Apprentice -46% Minorities and
Women
•Engineering Professional Services –31%
Minorities and 37% Women
•Disparity Study presentation and documents
available on MSD’s website:
http://www.msdprojectclear.org/disparity
•MSD will collect public input and comments through
April 30, 2022
•Board Introduction (June, 2022)
•Board Adoption (July, 2022)
•Implementation plans to begin upon Board approval.
•Program changes beginning of FY2024 (July 1,
2023).
Shonnah
Paredes,
Manager of
Diversity
Programs,
Metropolitan
St. Louis
Sewer District
(314) 768-
6395
sparedes@stlmsd.com
MSD Next Steps
4
Executive Director’s Update
•Plans for Stormwater Program
•Status of Board of Trustees
Further Details will be provided during Quarterly
AGC/SITE Update Meetings
www.MSDProjectClear.org
Questions
and Answers
Thanks to: