HomeMy Public PortalAbout15899 Lower Meramec WWTF Expansion Phase II (12255)ORDINANCE NO. 15899
AN ORDINANCE, making an appropriation of Fifty-Seven Million Seven
Hundred Thousand Dollars ($57,700,000.00) from the Sanitary Replacement Fund to be used for
wastewater treatment plant construction in Lower Meramec WWTF Expansion Phase II (12255)
in Unincorporated St. Louis County, Missouri; and authorizing the Executive Director and
Secretary-Treasurer on behalf of The Metropolitan St. Louis Sewer District to enter into Contract
No. 22150 with Plocher Construction Company, Inc. for said wastewater treatment plant
construction.
WHEREAS, the bid for said wastewater treatment plant construction is One
Hundred Fourteen Million Four Hundred Forty-Three Thousand Dollars ($114,443,000.00) and
the allowance for construction change orders and other project expenses is Two Million Five
Hundred Fifty-Seven Thousand Dollars ($2,557,000.00);
WHEREAS, a supplemental appropriation request is planned for Fiscal Year 2023
(FY23) and Fiscal Year 2024 (FY24) for a total appropriation amount of One Hundred Seventeen
Million Dollars ($117,000,000.00); and
WHEREAS, the Director of Finance has certified that there is an unencumbered
balance in the above-named fund sufficient to pay the obligation authorized herein.
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES OF
THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Fifty-Seven Million Seven Hundred Thousand Dollars
($57,700,000.00) is hereby appropriated from the Sanitary Replacement Fund to be used for
wastewater treatment plant construction in Lower Meramec WWTF Expansion Phase II (12255)
in Unincorporated St. Louis County, Missouri; said contract being comprised of such terms and
conditions as have been approved by the Office of the General Counsel of the District.
Section Two. The Executive Director and Secretary-Treasurer are hereby
authorized on behalf of The Metropolitan St. Louis Sewer District to enter into Contract No. 22150
with Plocher Construction Company, Inc. for said wastewater treatment plant construction in
Lower Meramec WWTF Expansion Phase II (12255) in Unincorporated St. Louis County,
Missouri, pursuant to bids received on the 24th day of March 2022.
The foregoing Ordinance was adopted on June 9, 2022