HomeMy Public PortalAboutExhibit MSD 73F - Storm CIRP w priorityDetailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
12754 ALLEMANIA ST 4709 STORM
IMPROVEMENTS
CONSTRUCT 1,500 FEET OF 12-
INCH TO 36-INCH STORM SEWERS
YARD AND STRUCTURE FLOODING. 597,000 FY25 Design Services 5140 7.38
12754 ALLEMANIA ST 4709 STORM
IMPROVEMENTS
CONSTRUCT 1,500 FEET OF 12-
INCH TO 36-INCH STORM SEWERS
YARD AND STRUCTURE FLOODING. 1,704,000 FY27 Construction 5140 7.38
12782 ARGYLE AVE. 9000 BLOCK STORM
SEWER
CONSTRUCT 600 FEET OF 60-INCH
STORM SEWER.
YARD FLOODING AND CREEK
EROSION THREATENING
STRUCTURES.
1,020,000 FY26 Construction 5564 0.61
13804 BAJA CT 16416 TO 16432 BANK
STABILIZATION
CONSTRUCT 240 FEET OF
MODULAR BLOCK WALL.
CREEK EROSION. 134,000 FY26 Design Services 5140 1.74
13804 BAJA CT 16416 TO 16432 BANK
STABILIZATION
CONSTRUCT 240 FEET OF
MODULAR BLOCK WALL.
CREEK EROSION. 358,000 FY28 Construction 5140 1.74
12827 BERWICK DRIVE STORM
IMPROVEMENTS
CONSTRUCT 420 FEET OF 12-INCH
STORM SEWER, AREA INLET, AND
CURB INLET.
OVERLAND FLOW INTO
RESIDENTIAL BASEMENT.
222,000 FY25 Design Services 5140 2.79
12827 BERWICK DRIVE STORM
IMPROVEMENTS
CONSTRUCT 420 FEET OF 12-INCH
STORM SEWER, AREA INLET, AND
CURB INLET.
OVERLAND FLOW INTO
RESIDENTIAL BASEMENT.
633,000 FY27 Construction 5140 2.79
12655 BIG BEND 10014 STORM
IMPROVEMENTS
CONSTRUCT 1000 FEET OF 12-
INCH TO 30-INCH STORM SEWER.
UNDERSIZED STORM SYSTEM
LEADING TO OVERLAND
FLOODING.
930,000 FY25 Construction 5571 1.19
11337 BLACKTHORN - HEATHER CREEK
BANK STABILIZATION (GCMB-140)
CONSTRUCT 730 FEET OF 6 TO 12
FOOT HIGH ROCK BLOCK WALL,
615 FEET OF COMPOSITE
REVETMENT, 80 CUBIC YARDS OF
HEAVY STONE REVETMENT, AND
FIVE GRADE CONTROL
STRUCTURES.
CREEK EROSION THREATENING SIX
PROPERTIES ON HEATHER AND
BLACKTHORN DRIVES.
236,000 FY28 Design Services 5140 1
11168 BRIARBROOK TRAIL STORM
SEWER
CONSTRUCT 485 FEET OF 15-INCH
TO 24-INCH STORM SEWER AND
APPURTENANCES.
STORM SEWER SYSTEM ALONG
BRIARBROOK TRAIL DISCHARGES
ONTO PROPERTY CAUSING
FLOODING OF DRIVEWAY AND
FRONT YARD.
459,000 FY26 Construction 5566 0.57
13366 BRIARWYCK STORM
IMPROVEMENTS
CONSTRUCT 225 FEET OF 12-INCH
STORM SEWER, MANHOLE AND
INLET.
STRUCTURE FLOODING. 61,000 FY25 Design Services 5140 9.01
13366 BRIARWYCK STORM
IMPROVEMENTS
CONSTRUCT 225 FEET OF 12-INCH
STORM SEWER, MANHOLE AND
INLET.
STRUCTURE FLOODING. 141,000 FY27 Construction 5140 9.01
13802 BRIDGETON VALLEY CIRCLE 3609
STORM SEWER
CONSTRUCT 140 FEET OF 12-INCH
STORM SEWER.
BASEMENT AND OVERLAND
FLOODING.
48,000 FY26 Design Services 5140 1.92
13802 BRIDGETON VALLEY CIRCLE 3609
STORM SEWER
CONSTRUCT 140 FEET OF 12-INCH
STORM SEWER.
BASEMENT AND OVERLAND
FLOODING.
136,000 FY28 Construction 5140 1.92
11252 CALVERTON RD. #421 STORM
SEWER
CONSTRUCT 482 FEET OF 12-INCH
TO 15-INCH RCP STORM SEWER.
YARD FLOODING AND EROSION. 187,000 FY26 Construction 5564 0.61
10374 CEDAR BRIDGE COURT #189 BANK
STABILIZATION
CONSTRUCT 75 FEET OF BANK
STABILIZATION, CONSISTING OF
ROCK BLOCK TOE, HIGH HEAVY
STONE REVETMENT, COMPOSITE
REVETMENT, AND
BIOSTABILIZATION.
CREEK EROSION. 108,000 FY26 Design Services 5140 2
10374 CEDAR BRIDGE COURT #189 BANK
STABILIZATION
CONSTRUCT 75 FEET OF BANK
STABILIZATION, CONSISTING OF
ROCK BLOCK TOE, HIGH HEAVY
STONE REVETMENT, COMPOSITE
REVETMENT, AND
BIOSTABILIZATION.
CREEK EROSION. 290,000 FY28 Construction 5140 2
13403 CEDAR FOREST COURT 2145
STORM IMPROVEMENTS
CONSTRUCT 150 FEET OF 12-INCH
STORM SEWER, AND INLET.
YARD FLOODING AND OVERLAND
FLOODING OF POOL.
48,000 FY27 Design Services 5140 1.25
11259 CEDARHURST DRIVE CREEK BANK
STABILIZATION
CONSTRUCT 1,300 FEET OF BANK
STABILIZATION AND ROCK TOE
PROTECTION.
CHANNEL EROSION. 2,530,000 FY25 Construction 5120 0.63
Page 1
Exhibit MSD 73F
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
13374 CHAMBERLIN DR 470 STORM
IMPROVEMENTS
CONSTRUCT 140 FEET OF 12-INCH
STORM SEWER, AND NEW INLET.
YARD EROSION AT 2 PROPERTIES. 32,000 FY28 Design Services 5140 0.95
11254 CHAMPLIN DR. #1629 STORM
SEWER
CONSTRUCT 430 FEET OF 15-INCH
TO 18-INCH STORM SEWER .
REAR YARD FLOODING. 60,000 FY27 Design Services 5140 0.67
13368 CLAYMONT 613 STORM
IMPROVEMENTS
CONSTRUCT 300 FEET OF 15-INCH
STORM SEWER, AND TWO INLETS.
FLOODING. 67,000 FY25 Design Services 5140 4.83
13368 CLAYMONT 613 STORM
IMPROVEMENTS
CONSTRUCT 300 FEET OF 15-INCH
STORM SEWER, AND TWO INLETS.
FLOODING. 191,000 FY27 Construction 5140 4.83
12940 CLERBROOK LANE STORM SEWER
(LADUE 1608.03)
CONSTRUCT 270 FEET OF 18-INCH
STORM SEWER.
STREET AND YARD FLOODING. 122,000 FY26 Construction 5566 0.38
12940 CLERBROOK LANE STORM SEWER
(LADUE 1608.03)
CONSTRUCT 270 FEET OF 18-INCH
STORM SEWER.
STREET AND YARD FLOODING. 245,000 FY26 Construction 5566 0.38
13488 COLDWATER CREEK OMCI
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES WITHIN THE
COLDWATER CREEK OMCI.
STORMWATER ISSUES IN THE
COLDWATER CREEK OMCI TAXING
SUBDISTRICT.
1,071,681 FY25 Construction, Phase
II
5564 #N/A
12919 CRANBERRY LANE #4044
STORMWATER IMPROVEMENTS
CONSTRUCT 200 FEET OF BERM
AND REGRADE EXISTING GRADE.
BACKYARD AND BASEMENT
OVERLAND FLOODING.
57,000 FY27 Design Services 5140 0.67
11510 CRESTWICK DR. #9901-9915
STORM SEWER
REMOVE 165 FEET OF EXISTING
STORM SEWER AND CONSTRUCT
540 FEET OF 12-INCH TO 30-INCH
RCP STORM SEWER.
YARD, GARAGE AND BASEMENT
FLOODING AND YARD EROSION.
85,000 FY26 Design Services 5140 1.78
11510 CRESTWICK DR. #9901-9915
STORM SEWER
REMOVE 165 FEET OF EXISTING
STORM SEWER AND CONSTRUCT
540 FEET OF 12-INCH TO 30-INCH
RCP STORM SEWER.
YARD, GARAGE AND BASEMENT
FLOODING AND YARD EROSION.
242,000 FY28 Construction 5140 1.78
11332 CULLODEN ROAD 819 - 827
STORM SEWER
CONSTRUCT 485 FEET OF 12-INCH
STORM SEWER.
YARD FLOODING. 136,000 FY25 Construction 5583 0.82
11425 DANVERS DR. #1249 AND 1257
STORM SEWER
CONSTRUCT 365 FEET OF 12-INCH
TO 21-INCH STORM SEWER .
YARD FLOODING AND EROSION. 57,000 FY28 Design Services 5140 0.93
13487 DEER CREEK OMCI
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES WITHIN THE
DEER CREEK OMCI.
STORMWATER ISSUES IN THE
DEER CREEK OMCI TAXING
SUBDISTRICT.
2,054,226 FY25 Construction, Phase
II
5566 #N/A
13625 DEGENHARDT AVENUE 300
STORM SEWER
CONSTRUCT 320 FEET OF 12-INCH
TO 18-INCH STORM SEWER.
OVERLAND FLOODING AT 300
DEGENHARDT AVENUE
86,000 FY26 Design Services 5140 2.13
13625 DEGENHARDT AVENUE 300
STORM SEWER
CONSTRUCT 320 FEET OF 12-INCH
TO 18-INCH STORM SEWER.
OVERLAND FLOODING AT 300
DEGENHARDT AVENUE
243,000 FY28 Construction 5140 2.13
11255 DELLWOOD CREEK BANK
STABILIZATION - WEST
FLORISSANT TO HUDSON RD.
CONSTRUCT 140 FEET OF 25 FOOT
HIGH BIOSTABILIZATION, 360 FEET
OF 8 FOOT HIGH
BIOSTABILIZATION, AND 140 FEET
OF 4 FOOT HIGH ROCK LINING.
CHANNEL EROSION THREATENING
A PARKING LOT AND HOUSE.
1,035,000 FY26 Construction 5120 1.05
11060 DELLWOOD CREEK STREAMBANK
STABILIZATION (MCDW-15)
CONSTRUCT 1110 FEET OF 10-
FOOT TO 20-FOOT HIGH
RETAINING WALL AND 210 FEET
OF BANK STABILIZATION.
10 structures threatened by
channel erosion in Dellwood
Creek.
1,444,000 FY26 Construction 5120 1.46
11281 DENNIS DRIVE #9733 STORM
SEWER
CONSTRUCT 645 FEET OF 18-INCH
RCP STORM SEWER .
YARD FLOODING AT 9733 DENNIS
DRIVE.
57,000 FY27 Design Services 5140 0.6
13885 DES PERES AVENUE 1104 CREEK
BANK STABILIZATION
CONSTRUCT 100 FEET OF 10 FOOT
HIGH HEAVY STONE REVETMENT.
EROSION. 57,000 FY26 Design Services 5140 2.2
13885 DES PERES AVENUE 1104 CREEK
BANK STABILIZATION
CONSTRUCT 100 FEET OF 10 FOOT
HIGH HEAVY STONE REVETMENT.
EROSION. 153,000 FY28 Construction 5140 2.2
Page 2
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
12898 DICKSON #615 STORM SEWER CONSTRUCT 155 FEET OF 12-INCH
STORM SEWER, NEW INLET AND
MANHOLE.
YARD FLOODING. 184,000 FY27 Construction 5571 2
10580 DONNYCAVE LANE STORM SEWER CONSTRUCT 295 FEET OF 12-INCH
STORM SEWER.
RUNOFF FROM THE NEW
PARKWAOOD SUBDIVISION
AFFECTS PROPERTIES ON THE
WEST SIDE OF DONNYCAVE LANE.
67,000 FY26 Design Services 5140 1.54
10580 DONNYCAVE LANE STORM SEWER CONSTRUCT 295 FEET OF 12-INCH
STORM SEWER.
RUNOFF FROM THE NEW
PARKWAOOD SUBDIVISION
AFFECTS PROPERTIES ON THE
WEST SIDE OF DONNYCAVE LANE.
190,000 FY28 Construction 5140 1.54
13203 DOVERCLIFF CT #1918 STORM
IMPROVEMENTS
CONSTRUCT 200 FEET OF 12-INCH
STORM SEWER AND AREA INLET.
YARD EROSION. 40,000 FY28 Design Services 5140 0.94
13171 EASEMENT ACQUISITION FOR
STORMWATER PROJECTS (2025)
PROVIDE EASEMENT ACQUISITION
FUNDING FOR CAPITAL
IMPROVEMENT AND
REPLACEMENT PROGRAM
STORMWATER PROJECTS.
IMPLEMENTATION OF THE
STORMWATER CAPITAL PROGRAM
REQUIRES PROPERTY RIGHTS
ACQUISITION FOR EASEMENTS
AND PURCHASES.
250,000 FY25 Property Rights
Acquisition
5140 #N/A
13172 EASEMENT ACQUISITION FOR
STORMWATER PROJECTS (2026)
PROVIDE EASEMENT ACQUISITION
FUNDING FOR CAPITAL
IMPROVEMENT AND
REPLACEMENT PROGRAM
STORMWATER PROJECTS.
IMPLEMENTATION OF THE
STORMWATER CAPITAL PROGRAM
REQUIRES PROPERTY RIGHTS
ACQUISITION FOR EASEMENTS
AND PURCHASES.
500,000 FY26 Property Rights
Acquisition
5140 #N/A
13173 EASEMENT ACQUISITION FOR
STORMWATER PROJECTS (2027)
PROVIDE EASEMENT ACQUISITION
FUNDING FOR CAPITAL
IMPROVEMENT AND
REPLACEMENT PROGRAM
STORMWATER PROJECTS.
IMPLEMENTATION OF THE
STORMWATER CAPITAL PROGRAM
REQUIRES PROPERTY RIGHTS
ACQUISITION FOR EASEMENTS
AND PURCHASES.
500,000 FY27 Property Rights
Acquisition
5140 #N/A
13174 EASEMENT ACQUISITION FOR
STORMWATER PROJECTS (2028)
PROVIDE EASEMENT ACQUISITION
FUNDING FOR CAPITAL
IMPROVEMENT AND
REPLACEMENT PROGRAM
STORMWATER PROJECTS.
IMPLEMENTATION OF THE
STORMWATER CAPITAL PROGRAM
REQUIRES PROPERTY RIGHTS
ACQUISITION FOR EASEMENTS
AND PURCHASES.
500,000 FY28 Property Rights
Acquisition
5140 #N/A
10590 EDNA AND GROVE STORM SEWER
EXTENSION
CONSTRUCT 195 FEET OF 18-INCH
RCP.
SYSTEM OF THREE STREET INLETS
WITH NO DOWNSTREAM
CONNECTION OR OUTFALL
RESULTING IN FLOODING STREETS.
75,000 FY26 Design Services 5140 1.18
10590 EDNA AND GROVE STORM SEWER
EXTENSION
CONSTRUCT 195 FEET OF 18-INCH
RCP.
SYSTEM OF THREE STREET INLETS
WITH NO DOWNSTREAM
CONNECTION OR OUTFALL
RESULTING IN FLOODING STREETS.
214,000 FY28 Construction 5140 1.18
13805 EVERGREEN FOREST AND BIRCH
FOREST BANK STABILIZATION
CONSTRUCT 300 FEET OF 10 FOOT
HIGH MODULAR BLOCK WALL.
EROSION. 141,000 FY28 Design Services 5140 1.09
13803 EVERGREEN FORESTCT 2424 AND
2428 BANK STABILIZATION
CONSTRUCT 200 FEET OF 12 FOOT
HIGH MODULAR BLOCK WALL.
CHANNEL EROSION IMPACTING
RESIDENTIAL HOMES.
116,000 FY26 Design Services 5140 2.16
13803 EVERGREEN FORESTCT 2424 AND
2428 BANK STABILIZATION
CONSTRUCT 200 FEET OF 12 FOOT
HIGH MODULAR BLOCK WALL.
CHANNEL EROSION IMPACTING
RESIDENTIAL HOMES.
311,000 FY28 Construction 5140 2.16
12811 FAWNDALE DRIVE 10102 STORM
SEWER
CONSTRUCT 90 FEET OF 12-INCH
STORM SEWER AND NEW INLET.
OVERLAND STRUCTURE FLOODING
AND YARD PONDING.
202,000 FY27 Construction 5571 4.79
Page 3
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
11041 FEE FEE CREEK BANK
STABILIZATION EAST TRIB TO
PAGE (FEE 09)
CONSTRUCT 720 FEET OF
CHANNEL STABILIZATION
CONSISTING OF ROCK BLOCK
WALLS AND HEAVY STONE
REVETMENT.
Erosion at 5 commercial buildings
along Fee Fee Creek between the
east trib and Page Ave.
471,000 FY28 Design Services 5140 0.92
11291 FERGUSON BRANCH STREAMBANK
STABILIZATION - CHURCH TO
DARST
CONSTRUCT 740 FEET OF 12-FOOT
TALL MODULAR BLOCK RETAINING
WALL AND APPURTENANCES
CREEK EROSION THREATENING
STRUCTURES.
1,902,000 FY26 Construction 5120 1.29
13180 GENERAL SERVICES AGREEMENT -
STORMWATER PLANNING (2025)
RETAIN FIRM FOR AS NEEDED
STORMWATER CAPITAL PROGRAM
PLANNING SERVICES. SERVICES
MAY BE RENEWED THROUGH
FY2027 BASED ON
PERFORMANCE.
PLANNING NEEDS TO SUPPORT
THE STORMWATER CAPITAL
PROGRAM THROUGHOUT THE
DISTRICT EXCEED THE CAPACITY
OF INTERNAL STAFF.
1,000,000 FY25 GSA - (Planning)
CIRP Funds
5140 #N/A
13180 GENERAL SERVICES AGREEMENT -
STORMWATER PLANNING (2025)
RETAIN FIRM FOR AS NEEDED
STORMWATER CAPITAL PROGRAM
PLANNING SERVICES. SERVICES
MAY BE RENEWED THROUGH
FY2027 BASED ON
PERFORMANCE.
PLANNING NEEDS TO SUPPORT
THE STORMWATER CAPITAL
PROGRAM THROUGHOUT THE
DISTRICT EXCEED THE CAPACITY
OF INTERNAL STAFF.
1,000,000 FY26 GSA - (Planning)
CIRP Funds
5140 #N/A
13180 GENERAL SERVICES AGREEMENT -
STORMWATER PLANNING (2025)
RETAIN FIRM FOR AS NEEDED
STORMWATER CAPITAL PROGRAM
PLANNING SERVICES. SERVICES
MAY BE RENEWED THROUGH
FY2027 BASED ON
PERFORMANCE.
PLANNING NEEDS TO SUPPORT
THE STORMWATER CAPITAL
PROGRAM THROUGHOUT THE
DISTRICT EXCEED THE CAPACITY
OF INTERNAL STAFF.
1,000,000 FY27 GSA - (Planning)
CIRP Funds
5140 #N/A
13179 GENERAL SERVICES AGREEMENT -
STORMWATER PLANNING (2028)
RETAIN ENGINEERING FIRM FOR
AS NEEDED STORMWATER
CAPITAL PROGRAM PLANNING
SERVICES. SERVICES MAY BE
RENEWED THROUGH FY2030
BASED ON PERFORMANCE.
THE STORMWATER CAPITAL
PROGRAM PLANNING NEEDS
THROUGHOUT THE DISTRICT
EXCEED THE CAPACITY OF
INTERNAL STAFF.
500,000 FY28 GSA - (Planning)
CIRP Funds
5140 #N/A
13299 GENERAL SERVICES AGREEMENT -
WATER QUALITY SUPPORT
SERVICES (2024)
RETAIN ENGINEERING FIRM FOR
AS NEEDED WATER QUALITY
SUPPORT SERVICES. SERVICES
MAY BE RENEWED THROUGH
FY2026 BASED ON
PERFORMANCE.
WATER QUALITY EXPERTISE IS
NEEDED TO SUPPORT THE
DISTRICT'S REGULATORY AND
LEGAL EFFORTS.
150,000 FY25 GSA - Planning
(Supplemental
Appropriation)
5110 #N/A
13299 GENERAL SERVICES AGREEMENT -
WATER QUALITY SUPPORT
SERVICES (2024)
RETAIN ENGINEERING FIRM FOR
AS NEEDED WATER QUALITY
SUPPORT SERVICES. SERVICES
MAY BE RENEWED THROUGH
FY2026 BASED ON
PERFORMANCE.
WATER QUALITY EXPERTISE IS
NEEDED TO SUPPORT THE
DISTRICT'S REGULATORY AND
LEGAL EFFORTS.
150,000 FY26 GSA - Planning
(Supplemental
Appropriation)
5110 #N/A
13744 GENERAL SERVICES AGREEMENT -
WATER QUALITY SUPPORT
SERVICES (2027)
RETAIN ENGINEERING FIRM FOR
AS NEEDED WATER QUALITY
SUPPORT SERVICES. SERVICES
MAY BE RENEWED THROUGH
FY2029 BASED ON
PERFORMANCE.
WATER QUALITY EXPERTISE IS
NEEDED TO SUPPORT THE
DISTRICT'S REGULATORY AND
LEGAL EFFORTS.
150,000 FY27 GSA - (Planning)
Operating Fund
5110 #N/A
13744 GENERAL SERVICES AGREEMENT -
WATER QUALITY SUPPORT
SERVICES (2027)
RETAIN ENGINEERING FIRM FOR
AS NEEDED WATER QUALITY
SUPPORT SERVICES. SERVICES
MAY BE RENEWED THROUGH
FY2029 BASED ON
PERFORMANCE.
WATER QUALITY EXPERTISE IS
NEEDED TO SUPPORT THE
DISTRICT'S REGULATORY AND
LEGAL EFFORTS.
150,000 FY28 GSA - Planning
(Supplemental
Appropriation)
5110 #N/A
13607 GENESTA STREET 8002 STORM
SEWER
CONSTRUCT 260 FEET OF 15-INCH
STORM SEWER.
DETACHED GARAGE FLOODING AT
8002 GENESTA STREET.
53,000 FY28 Design Services 5140 1.07
11579 GEREMMA AND WHITE TREE
CHANNEL IMPROVEMENTS
CONSTRUCT 1,125 FEET OF
CHANNEL IMPROVEMENTS.
FLOODING FROM THE 10 YEAR
STORM EVENT AT 278 GEREMMA
DRIVE.
352,000 FY28 Design Services 5140 1.12
12712 GLEN ECHO DR STORM SEWER
(NORDIC DR TO CLEARVIEW DR)
CONSTRUCT 400 FEET OF 15-INCH,
AND 200 FEET OF 12-INCH,
STORM SEWER.
OVERLAND FLOW FLOODING
PROPERTIES.
60,000 FY27 Design Services 5140 0.63
Page 4
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
11599 GOLDEN OAK CT. #10 AND 12
STORM SEWER
CONSTRUCT 190 FEET OF 12-INCH
RCP STORM SEWER .
YARD FLOODING. 33,000 FY28 Design Services 5140 0.98
13395 GOLFVIEW DR 680 STORM
IMPROVEMENTS
CONSTRUCT 150 FEET OF 12-INCH
STORM SEWER, AND INLET.
HOME AND YARD FLOODING. 45,000 FY25 Design Services 5140 4.5
13395 GOLFVIEW DR 680 STORM
IMPROVEMENTS
CONSTRUCT 150 FEET OF 12-INCH
STORM SEWER, AND INLET.
HOME AND YARD FLOODING. 128,000 FY27 Construction 5140 4.5
10172 GRAND & HARRISON STORM
IMPROVEMENTS
CONSTRUCT 40 FEET OF TRIPLE 6
X 3 BOX CULVERT, 90 FEET OF 96-
INCH RCP STORM SEWER, AND
145 FEET OF 10 FOOT WIDE ROCK
LINED TRAPEZOIDAL CHANNEL.
FLOODING OF RESIDENTIAL AND
COMMERCIAL PROPERTIES AND
STREET FLOODING.
908,000 FY28 Design Services 5140 1.08
10858 GRANDA - HAWSON - CLAGER
STORM SEWER IMPROVEMENTS
CONSTRUCT 1,420 FEET OF 12-
INCH TO 48-INCH RCP STORM
SEWER.
BASEMENT, STREET, AND YARD
FLOODING.
482,000 FY27 Design Services 5140 1.39
11330 GRANDVIEW DR. #1309 STORM
SEWER
CONSTRUCT 115 FEET OF 15-INCH
STORM SEWER, ROCK BLANKET
AND BIOSTABILIZED SLOPE.
YARD EROSION. 214,000 FY27 Construction 5583 0.36
13533 GRATIOT 3527 SEWER AND CURB
INLET
CONSTRUCT 150 FEET OF 12-INCH
SEWER AND DOUBLE CURB INLET.
SURFACE FLOODING ON LOW
ELEVATION POINT IN STREET.
80,000 FY25 Design Services 5140 4.4
13533 GRATIOT 3527 SEWER AND CURB
INLET
CONSTRUCT 150 FEET OF 12-INCH
SEWER AND DOUBLE CURB INLET.
SURFACE FLOODING ON LOW
ELEVATION POINT IN STREET.
229,000 FY27 Construction 5140 4.4
13678 GRAVOIS CREEK OMCI
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES WITHIN THE
GRAVOIS CREEK OMCI.
STORMWATER ISSUES IN THE
GRAVOIS CREEK OMCI TAXING
SUBDISTRICT.
787,127 FY25 Construction, Phase
II
5571 #N/A
13394 GREENBRIAR ESTATES DR 105
STORM IMPROVEMENTS
CONSTRUCT 70 FEET OF 12-INCH
STORM SEWER, INLET AND
MANHOLE.
BASEMENT FLOODING. 39,000 FY27 Design Services 5140 1.35
10070 HALL STREET STORM SEWERS CONSTRUCT 5,500 FEET OF 12-
INCH TO 66-INCH STORM SEWER,
523 FEET OF 72-INCH TUNNEL,
AND 16,800 FEET OF DRAINAGE
DITCH ALONG HALL STREET.
STREET FLOODING ALONG HALL
STREET FROM ADELAIDE TO
RIVERVIEW DRIVE.
8,000,000 FY26 Construction 5120 0.3
10070 HALL STREET STORM SEWERS CONSTRUCT 5,500 FEET OF 12-
INCH TO 66-INCH STORM SEWER,
523 FEET OF 72-INCH TUNNEL,
AND 16,800 FEET OF DRAINAGE
DITCH ALONG HALL STREET.
STREET FLOODING ALONG HALL
STREET FROM ADELAIDE TO
RIVERVIEW DRIVE.
5,361,000 FY27 Construction
(Supplemental
Appropriation)
5120 0.3
10067 HALLSTEAD STORM CHANNEL
PHASE IV (MCBJ-230)
CONSTRUCT 1,220 FEET OF 45-
FOOT WIDE BY 12-FOOT HIGH
VERTICAL WALL CHANNEL, FROM
VORHOFF DRIVE SOUTH TO
HUDSON DRIVE.
DAMAGE TO PROPERTY DUE TO
EROSION.
100,000 FY25 Engineering During
Construction
Services
5120 1.25
10067 HALLSTEAD STORM CHANNEL
PHASE IV (MCBJ-230)
CONSTRUCT 1,220 FEET OF 45-
FOOT WIDE BY 12-FOOT HIGH
VERTICAL WALL CHANNEL, FROM
VORHOFF DRIVE SOUTH TO
HUDSON DRIVE.
DAMAGE TO PROPERTY DUE TO
EROSION.
4,600,000 FY25 Construction 5120 1.25
10067 HALLSTEAD STORM CHANNEL
PHASE IV (MCBJ-230)
CONSTRUCT 1,220 FEET OF 45-
FOOT WIDE BY 12-FOOT HIGH
VERTICAL WALL CHANNEL, FROM
VORHOFF DRIVE SOUTH TO
HUDSON DRIVE.
DAMAGE TO PROPERTY DUE TO
EROSION.
1,973,000 FY26 Construction
(Supplemental
Appropriation)
5120 1.25
11321 HEEGE RD. #5310 AND 5316 BANK
STABILIZATION
CONSTRUCT 225 FEET OF 8 TO 10
FOOT HIGH MODULAR BLOCK
RETAINING WALL.
EROSION THREATENING PARKING
LOT AND DRIVEWAY.
172,000 FY28 Design Services 5140 0.93
11063 HILLSDALE DR #7501 STORM
SEWER
CONSTRUCT 505 FEET OF 15-INCH
to 30-INCH STORM SEWER.
BASEMENT AND YARD FLOODING. 383,000 FY26 Construction 5589 3.12
Page 5
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
11063 HILLSDALE DR #7501 STORM
SEWER
CONSTRUCT 505 FEET OF 15-INCH
to 30-INCH STORM SEWER.
BASEMENT AND YARD FLOODING. 55,000 FY26 Construction 5589 3.12
11435 HILLTOP DRIVE #9931 BANK
STABILIZATION
CONSTRUCT 220 FEET OF
VEGETATED REINFORCED
EARTHEN SWALE.
FLOODING AND EROSION. 40,000 FY28 Design Services 5140 0.98
13276 HOLLY HILLS #3900 STORM
DRAINAGE IMPROVEMENTS
CONSTRUCT 175 FEET OF 12-INCH
STORM SEWER, A NEW INLET,
AND REPLACE AN EXISTING INLET.
STREET FLOODING. 59,000 FY27 Design Services 5140 1.31
13882 HUDSON AVENUE 9745 STORM
SEWER
CONSTRUCT 100 FEET OF NEW
STORM SEWER AND
APPURTENANCES.
GARAGE FLOODING. 38,000 FY27 Design Services 5140 1.4
13373 HURSTFIELD COURT 21 STORM
IMPROVEMENTS
CONSTRUCT 125 FEET OF 12-
INCJH STORM SEWER, AND ONE
INLET.
YARD EROSION AT 3 PROPERTIES. 30,000 FY27 Design Services 5140 1.25
10286 KINGSLAND AVENUE #1400
STORM SEWER IMPROVEMENT
CONSTRUCT 730 FEET OF 12-INCH
TO 48-INCH STORM SEWER AND
APPURTENANCES.
STREET FLOODING, STRUCTURE
FLOODING, AND EROSION, ALONG
KINGSLAND AVENUE.
294,000 FY26 Design Services 5140 1.81
10286 KINGSLAND AVENUE #1400
STORM SEWER IMPROVEMENT
CONSTRUCT 730 FEET OF 12-INCH
TO 48-INCH STORM SEWER AND
APPURTENANCES.
STREET FLOODING, STRUCTURE
FLOODING, AND EROSION, ALONG
KINGSLAND AVENUE.
839,000 FY28 Construction 5140 1.81
10340 KIRKHAM AND THORNTON -
SHADY GROVE CREEK BANK
STABILIZATION
CONSTRUCT 100 FEET OF ROCK
BLOCK TOE, 215 FEET OF ROCK
BLOCK TOE WITH COMPOSITE
REVETMENT, 140 FEET OF
MODULAR BLOCK WALL, 65 FEET
OF ROCK GRADE CONTROL, AND
40 FEET OF ROCK LINED SWALE.
STREAM BANK EROSION. 988,000 FY26 Construction 5566 0.8
11455 LACKLAND AVE. 9900 BLOCK
STORM SEWER
CONSTRUCT 440 FEET OF 12-INCH
TO 15-INCH STORM SEWER.
YARD PONDING. 210,000 FY26 Construction 5584 0.82
13747 LAMBERT AIRPORT RESTRICTED
ACCESS ASSETS INSPECTION AND
REPAIR
PERFORM CCTV INSPECTION,
REPAIR AND CIPP REHABILITATION
OF 48,000 FEET OF SANITARY
SEWER AND 26,000 FEET OF
STORM SEWER.
PUBLIC SANITARY AND STORM
SEWERS WITHIN THE FAA
RESTRICTED ACCESS AND
SECURITY REQUIREMENTS AREA
OF THE AIRPORT ARE IN NEED OF
INSPECTION AND REPAIR.
500,000 FY25 Construction
(Supplemental
Appropriation)
5120 Repairs
13747 LAMBERT AIRPORT RESTRICTED
ACCESS ASSETS INSPECTION AND
REPAIR
PERFORM CCTV INSPECTION,
REPAIR AND CIPP REHABILITATION
OF 48,000 FEET OF SANITARY
SEWER AND 26,000 FEET OF
STORM SEWER.
PUBLIC SANITARY AND STORM
SEWERS WITHIN THE FAA
RESTRICTED ACCESS AND
SECURITY REQUIREMENTS AREA
OF THE AIRPORT ARE IN NEED OF
INSPECTION AND REPAIR.
500,000 FY26 Construction
(Supplemental
Appropriation)
5120 Repairs
13747 LAMBERT AIRPORT RESTRICTED
ACCESS ASSETS INSPECTION AND
REPAIR
PERFORM CCTV INSPECTION,
REPAIR AND CIPP REHABILITATION
OF 48,000 FEET OF SANITARY
SEWER AND 26,000 FEET OF
STORM SEWER.
PUBLIC SANITARY AND STORM
SEWERS WITHIN THE FAA
RESTRICTED ACCESS AND
SECURITY REQUIREMENTS AREA
OF THE AIRPORT ARE IN NEED OF
INSPECTION AND REPAIR.
500,000 FY27 Construction
(Supplemental
Appropriation)
5120 Repairs
11460 LARIMORE PARKWAY TO
BIRMINGHAM CT. CHANNEL
IMPROVEMENTS (WC-16A)
CONSTRUCT 535 FEET OF 9 TO 12
FEET HIGH MODULAR BLOCK
RETAINING WALL AND 1,715 FEET
OF HEAVY STONE REVETMENT
BANK PROTECTION.
MODERATE RISK STRUCTURAL
EROSION.
2,844,000 FY26 Construction 5120 1.02
11164 LAWNWOOD DR. #1442 STORM
SEWER
CONSTRUCT 320 FEET OF 15-INCH
TO 18-INCH STORM SEWER.
YARD FLOODING. 336,000 FY26 Construction 5566 0.49
13614 LEA MEADOWS DRIVE 118 STORM
SEWER
CONSTRUCT 860 FEET OF 12-INCH
TO 21-INCH STORM SEWER.
YARD AND BASEMENT FLOODING
AT LEA MEADOWS DRIVE.
215,000 FY27 Design Services 5140 1.23
Page 6
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
13883 LEXINGTON AVENUE 743 STORM
SEWER
CONSTRUCT 185 FEET OF NEW
STORM SEWER AND
APPURTENANCES.
BUILDING FLOODING. 42,000 FY26 Design Services 5140 1.73
13883 LEXINGTON AVENUE 743 STORM
SEWER
CONSTRUCT 185 FEET OF NEW
STORM SEWER AND
APPURTENANCES.
BUILDING FLOODING. 119,000 FY28 Construction 5140 1.73
13792 LITTLE PINE CT 18001 BANK
STABILIZATION
CONSTRUCT 60 FEET OF 2 FOOT
HIGH HEAVY STONE REVETMENT
WITH 3 FOOT BIOSTABILIZATION.
STREAMBANK EROSION
THREATENING SIDEWALK AND
ROADWAY.
20,000 FY25 Design Services 5140 2.69
13792 LITTLE PINE CT 18001 BANK
STABILIZATION
CONSTRUCT 60 FEET OF 2 FOOT
HIGH HEAVY STONE REVETMENT
WITH 3 FOOT BIOSTABILIZATION.
STREAMBANK EROSION
THREATENING SIDEWALK AND
ROADWAY.
53,000 FY27 Construction 5140 2.69
13646 LOG HILL COURT 601 STORM
SEWER
CONSTRUCT 550 FEET OF 12-INCH
TO 30-INCH STORM SEWER.
STRUCTURE, OVERLAND, AND
STREET FLOODING.
160,000 FY26 Design Services 5140 1.74
13646 LOG HILL COURT 601 STORM
SEWER
CONSTRUCT 550 FEET OF 12-INCH
TO 30-INCH STORM SEWER.
STRUCTURE, OVERLAND, AND
STREET FLOODING.
455,000 FY28 Construction 5140 1.74
10686 LORETTA - GENTRY STORM SEWER
PHASE I
CONSTRUCT 1,570 FEET OF 4-
FOOT BY 3-FOOT REINFORCED
CONCRETE BOX AND 48-INCH
DIAMETER SEWER.
DAMAGE TO PROPERTY DUE TO
FLOODING.
932,000 FY27 Design Services 5140 1.45
11278 LORNA LANE #9709 STORM
SEWER
CONSTRUCT 515 FEET OF 18-INCH
TO 24-INCH RCP STORM SEWER .
YARD FLOODING. 365,000 FY27 Design Services 5140 0.64
10687 LOUISVILLE & WEST PARK STORM
SEWER
CONSTRUCT 30 FEET OF 12-INCH
STORM SEWER AND TWO RAIN
GARDENS
YARD FLOODING. 38,000 FY25 Design Services 5140 2.96
10687 LOUISVILLE & WEST PARK STORM
SEWER
CONSTRUCT 30 FEET OF 12-INCH
STORM SEWER AND TWO RAIN
GARDENS
YARD FLOODING. 106,000 FY27 Construction 5140 2.96
11292 MALINE CREEK BANK
STABILIZATION - ST. LOUIS PLACE
TO FLORISSANT RD.
CONSTRUCT 870 FEET OF 14 FOOT
HIGH MODULAR BLOCK WALL
AND 1,020 FEET OF 14 FOOT HIGH
BIOSTABILIZATION.
EROSION ALONG MALINE CREEK
DOWNSTREAM OF THE BRIDGE AT
SOUTH FLORISSANT ROAD.
2,906,000 FY26 Construction 5120 1.23
11546 MARK WESLEY LN. #463 BANK
STABILIZATION (FIS-27)
CONSTRUCT 110 FEET OF BANK
STABILIZATION.
BANK EROSION POTENTIALLY
THREATENING ONE STRUCTURE.
75,000 FY28 Design Services 5140 0.93
13703 MARKET STREET PERMEABLE
PAVEMENT AND RAIN GARDEN
IMPROVEMENTS
RECONSTRUCT PARKING LOT
USING PERMEABLE PAVEMENT,
AND CONSTRUCT RAIN GARDENS
AT VARIOUS LOCATIONS AT THE
SITE.
DETERIORATED PARKING LOT
PAVEMENT, AND OPPORTUNITY
FOR GREEN INFRASTRUCTURE TO
PROVIDE WATER QUALITY
IMPROVEMENTS.
590,000 FY25 Construction 4102 Repairs
13612 MAY VALLEY LANE 86 STORM
SEWER
CONSTRUCT 373 FEET OF 12-INCH
TO 18-INCH STORM SEWER.
HOUSE FLOODING AT MAY VALLEY
LANE.
78,000 FY26 Design Services 5140 2.23
13612 MAY VALLEY LANE 86 STORM
SEWER
CONSTRUCT 373 FEET OF 12-INCH
TO 18-INCH STORM SEWER.
HOUSE FLOODING AT MAY VALLEY
LANE.
223,000 FY28 Construction 5140 2.23
13401 MEADOWBROOK COUNTRY CLUB
ESTATES 67 STORM
IMPROVEMENTS
CONSTRUCT 100 FEET OF 54-INCH
STORM SEWER.
BASEMENT FLOODIJNG. 56,000 FY25 Design Services 5140 4.05
13401 MEADOWBROOK COUNTRY CLUB
ESTATES 67 STORM
IMPROVEMENTS
CONSTRUCT 100 FEET OF 54-INCH
STORM SEWER.
BASEMENT FLOODIJNG. 159,000 FY27 Construction 5140 4.05
11043 MIDDLEWOOD COURT STORM
SEWER
CONSTRUCT 190 FEET OF 24-INCH
STORM SEWER.
Yard and basement flooding 69,000 FY26 Design Services 5140 2.46
11043 MIDDLEWOOD COURT STORM
SEWER
CONSTRUCT 190 FEET OF 24-INCH
STORM SEWER.
Yard and basement flooding 195,000 FY28 Construction 5140 2.46
12749 MONTE CARLO DR 11263 STORM
IMPROVEMENT
CONSTRUCT 200 FEET OF 12-INCH
STORM SEWER.
STORMWATER FLOWS CAUSING
EROSION ALONG BUILDING WALL.
38,000 FY27 Design Services 5140 1.2
Page 7
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
12745 N WATERFORD 2735 STORM
IMPROVEMENTS
CONSTRUCT 210 FEET OF 18-INCH
TO 24-INCH STORM SEWER.
YARD FLOODING. 103,000 FY26 Construction 5564 0.6
11296 NEWELL AND NOAH DRIVE STORM
SEWER
CONSTRUCT 285 FEET OF 15-INCH
TO 18-INCH STORM SEWER.
YARD AND STREET FLOODING. 318,000 FY25 Construction 5576 0.72
10872 NORTH GEYER AND VILLA GARDEN
STORM SEWER
CONSTRUCT 165 FEET OF 12-INCH
STORM SEWER.
YARD PONDING. 318,000 FY25 Construction 5583 0.53
13615 NORTH HARRISON AVENUE 1030
STORM SEWER
CONSTRUCT 250 FEET OF 12-INCH
TO 21-INCH STORM SEWER.
PARKING GARAGE FLOODING AT
1030 NORTH HARRISON AVENUE.
243,000 FY26 Construction 5566 0.79
13369 NOVARA 355 STORM
IMPROVEMENTS
CONSTRUCT 370 FEET OF 12-INCH
STORM SEWER, AND TWO INLETS.
FLOODING. 74,000 FY25 Design Services 5140 6.74
13369 NOVARA 355 STORM
IMPROVEMENTS
CONSTRUCT 370 FEET OF 12-INCH
STORM SEWER, AND TWO INLETS.
FLOODING. 210,000 FY27 Construction 5140 6.74
13683 OLD BONHOMME 8444 STORM
SEWERS
CONSTRUCT 1,070 FEET OF 12-
INCH TO 42-INCH STORM SEWERS.
STRUCTURE FLOODING. 907,000 FY26 Construction 5566 1.47
12755 OLEATHA AVE 6918 STORM
IMPROVEMENTS
CONSTRUCT 275 FEET OF 12-INCH
STORM SEWER.
OVERLAND FLOW CAUSING YARD
AND BASEMENT FLOODING.
92,000 FY25 Design Services 5140 15.4
12755 OLEATHA AVE 6918 STORM
IMPROVEMENTS
CONSTRUCT 275 FEET OF 12-INCH
STORM SEWER.
OVERLAND FLOW CAUSING YARD
AND BASEMENT FLOODING.
261,000 FY27 Construction 5140 15.4
10724 PAGE #8227 STORM SEWER CONSTRUCT 735 FEET OF 12-INCH
TO 18-INCH STORM SEWER.
YARD FLOODING. 120,000 FY27 Design Services 5140 0.59
10729 PARCHESTER - HOLBORN STORM
SEWER
DESIGN AND CONSTRUCT
APPROXIMATELY 450 FEET OF 12-
INCH TO 15-INCH STORM SEWER
AND APPURTENANCES.
YARD PONDING. 142,000 FY27 Design Services 5140 0.55
10874 PARK WAY DRIVE 8000 STORM
SEWER
CONSTRUCT 100 FEET OF 15-INCH
RCP STORM SEWER AND
APPURTENANCES.
YARD EROSION. 214,000 FY26 Construction 5584 0.75
13889 PARKHURST TERRACE 210 STORM
SEWER
CONSTRUCT 75 FEET OF 12-INCH
TO 15-INCH STORM SEWER.
STREET FLOODING. 26,000 FY28 Design Services 5140 1
11284 PAUL DR. #472 CHANNEL
IMPROVEMENTS (MCMB-325)
CONSTRUCT 427 LF OF 14 FT HIGH
BIOSTABILIZATION.
EROSION ALONG MALINE CREEK IS
THREATENING AN ASPHALT
PARKING LOT.
86,000 FY27 Design Services 5140 0.59
10309 PEMBROKE DRIVE STORM
IMPROVEMENTS
CONSTRUCT 990 FEET OF 12-INCH
TO 27-INCH DIAMETER STORM
SEWER.
STREET FLOODING AT
INTERSECTION OF WATSON ROAD
AND PEMBROKE DRIVE.
640,000 FY26 Construction 5593 0.34
11044 PORT DIANE TO TENNANT BANK
STABILIZATION
CONSTRUCT 220 FEET OF 66-INCH
RCP, 445 FEET OF MODULAR
BLOCK WALL, 595 FEET OF
COMBINATION SLOPE
STABILIZATION, AND REPLACE 444
FEET OF 8-INCH DIP.
Creek erosion 965,000 FY26 Design Services 5140 1.61
11044 PORT DIANE TO TENNANT BANK
STABILIZATION
CONSTRUCT 220 FEET OF 66-INCH
RCP, 445 FEET OF MODULAR
BLOCK WALL, 595 FEET OF
COMBINATION SLOPE
STABILIZATION, AND REPLACE 444
FEET OF 8-INCH DIP.
Creek erosion 2,589,000 FY28 Construction 5140 1.61
13577 RIVER DES PERES CHANNEL
REHABILITATION
REHABILITATE DETERIORATED
SECTIONS OF THE RDP CHANNEL.
AREAS OF THE RDP CHANNEL ARE
DETERIORATING.
5,750,000 FY25 Construction 5120 Repairs
13257 ROLENS DR. #2540 STORM SEWER CONSTRUCT 135 FEET OF 12-INCH
STORM SEWER.
OVERLAND WATER FLOW
CAUSING YARD FLOODING.
32,000 FY27 Design Services 5140 1.33
10261 SACRE COEUR STORM CHANNEL CONSTRUCT 480 FEET OF
MODULAR CONCRETE BLOCK
RETAINING WALL.
CREEK BANK EROSION BETWEEN
ADVOCATE COURT AND TRINITY
CIRCLE.
332,000 FY27 Design Services 5140 1.41
Page 8
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
13457 SANDERS DRIVE 1009 STORM
SEWER
CONSTRUCT 660 FEET OF 18-INCH
STORM SEWER.
STRUCTURE FLOODING ALONG
SANDERS DRIVE.
544,000 FY25 Construction 5571 5.95
13491 SEMINARY OMCI
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES WITHIN THE
SEMINARY OMCI.
STORMWATER ISSUES IN THE
SEMINARY OMCI TAXING
SUBDISTRICT.
131,397 FY25 Construction, Phase
II
5593 #N/A
13606 SPRING OAKS DR 208 STORM
SEWER
CONSTRUCT 262 FEET OF 18-INCH
STORM SEWER.
YARD AND BASEMENT FLOODING
AT SPRING OAKS DR.
90,000 FY26 Design Services 5140 1.7
13606 SPRING OAKS DR 208 STORM
SEWER
CONSTRUCT 262 FEET OF 18-INCH
STORM SEWER.
YARD AND BASEMENT FLOODING
AT SPRING OAKS DR.
257,000 FY28 Construction 5140 1.7
13814 ST MARYS DR 118 STORM SEWER CONSTRUCT 50 FEET OF 12-INCH
STORM SEWER.
YARD FLOODING. 24,000 FY27 Design Services 5140 1.29
11462 ST. ANDREWS PLACE AND ST.
MARYS LANE STORM SEWER
CONSTRUCT 1,390 FEET OF 12-
INCH TO 27-INCH STORM SEWERS
.
BASEMENT, STREET, AND YARD
FLOODING.
211,000 FY26 Design Services 5140 1.13
11462 ST. ANDREWS PLACE AND ST.
MARYS LANE STORM SEWER
CONSTRUCT 1,390 FEET OF 12-
INCH TO 27-INCH STORM SEWERS
.
BASEMENT, STREET, AND YARD
FLOODING.
603,000 FY28 Construction 5140 1.13
11180 ST. GEORGE CT. STORM SEWER CONSTRUCT 2,255 FEET OF 12-
INCH TO 36-INCH STORM SEWER.
BASEMENT AND YARD FLOODING. 57,000 FY28 Design Services 5140 0.43
12920 STODDARDS MILL #558 STORM
IMPROVEMENTS
CONSTRUCT 160 FEET OF 12-INCH
STORM SEWER AND TWO INLETS.
YARD AND STRUCTURE FLOODING. 23,000 FY26 Design Services 5140 1.55
12920 STODDARDS MILL #558 STORM
IMPROVEMENTS
CONSTRUCT 160 FEET OF 12-INCH
STORM SEWER AND TWO INLETS.
YARD AND STRUCTURE FLOODING. 66,000 FY28 Construction 5140 1.55
13008 STORMWATER INFRASTRUCTURE
REPAIRS (2025)
CONSTRUCT REPAIR OR
REPLACEMENT OF STORMWATER
INFRASTRUCTURE THROUGHOUT
THE DISTRICT.
AGING AND DETERIORATING
STORMWATER INFRASTRUCTURE
IS IN NEED OF REPAIR AND
REPLACEMENT.
5,000,000 FY25 Work Order Repair
Costs (Capital)
5120 Repairs
13009 STORMWATER INFRASTRUCTURE
REPAIRS (2026)
CONSTRUCT REPAIR OR
REPLACEMENT OF STORMWATER
INFRASTRUCTURE THROUGHOUT
THE DISTRICT.
AGING AND DETERIORATING
STORMWATER INFRASTRUCTURE
IS IN NEED OF REPAIR AND
REPLACEMENT.
5,000,000 FY26 Work Order Repair
Costs (Capital)
5120 Repairs
13010 STORMWATER INFRASTRUCTURE
REPAIRS (2027)
CONSTRUCT REPAIR OR
REPLACEMENT OF STORMWATER
INFRASTRUCTURE THROUGHOUT
THE DISTRICT.
AGING AND DETERIORATING
STORMWATER INFRASTRUCTURE
IS IN NEED OF REPAIR AND
REPLACEMENT.
5,000,000 FY27 Work Order Repair
Costs (Capital)
5120 Repairs
13011 STORMWATER INFRASTRUCTURE
REPAIRS (2028)
CONSTRUCT REPAIR OR
REPLACEMENT OF STORMWATER
INFRASTRUCTURE THROUGHOUT
THE DISTRICT.
AGING AND DETERIORATING
STORMWATER INFRASTRUCTURE
IS IN NEED OF REPAIR AND
REPLACEMENT.
5,000,000 FY28 Work Order Repair
Costs (Capital)
5120 Repairs
13130 STORMWATER INFRASTRUCTURE
REPAIRS (REHABILITATION) (2025)
CONSTRUCT CURED-IN-PLACE PIPE
INSTALLATION FOR STORMWATER
SYSTEM REHABILITATION AND
REPAIR, AS NEEDS ARE IDENTIFIED
BY SEWER CLEANING AND
INSPECTION EFFORTS.
DETERIORATED AND DAMAGED
STORMWATER SEWER LINES
CAUSE PIPE COLLAPSES, BLOCKED
SEWERS, AND STREET AND YARD
FLOODING.
2,000,000 FY25 Construction 5120 Repairs
13131 STORMWATER INFRASTRUCTURE
REPAIRS (REHABILITATION) (2026)
CONSTRUCT CURED-IN-PLACE PIPE
INSTALLATION FOR STORMWATER
SYSTEM REHABILITATION AND
REPAIR, AS NEEDS ARE IDENTIFIED
BY SEWER CLEANING AND
INSPECTION EFFORTS.
DETERIORATED AND DAMAGED
STORMWATER SEWER LINES
CAUSE PIPE COLLAPSES, BLOCKED
SEWERS, AND STREET AND YARD
FLOODING.
4,000,000 FY26 Construction 5120 Repairs
Page 9
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
13132 STORMWATER INFRASTRUCTURE
REPAIRS (REHABILITATION) (2027)
CONSTRUCT CURED-IN-PLACE PIPE
INSTALLATION FOR STORMWATER
SYSTEM REHABILITATION AND
REPAIR, AS NEEDS ARE IDENTIFIED
BY SEWER CLEANING AND
INSPECTION EFFORTS.
DETERIORATED AND DAMAGED
STORMWATER SEWER LINES
CAUSE PIPE COLLAPSES, BLOCKED
SEWERS, AND STREET AND YARD
FLOODING.
4,000,000 FY27 Construction 5120 Repairs
13133 STORMWATER INFRASTRUCTURE
REPAIRS (REHABILITATION) (2028)
CONSTRUCT CURED-IN-PLACE PIPE
INSTALLATION FOR STORMWATER
SYSTEM REHABILITATION AND
REPAIR, AS NEEDS ARE IDENTIFIED
BY SEWER CLEANING AND
INSPECTION EFFORTS.
DETERIORATED AND DAMAGED
STORMWATER SEWER LINES
CAUSE PIPE COLLAPSES, BLOCKED
SEWERS, AND STREET AND YARD
FLOODING.
4,000,000 FY28 Construction 5120 Repairs
13828 STORMWATER MUNICIPALITY
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES THROUGHOUT
THE DISTRICT.
STORMWATER ISSUES
THROUGHOUT THE DISTRICT TO
BE ADDRESSED VIA A
COOPERATIVE EFFORT WITH
LOCAL MUNICIPAL PARTNERS.
10,200,000 FY26 Construction, Phase
II
5140 #N/A
13828 STORMWATER MUNICIPALITY
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES THROUGHOUT
THE DISTRICT.
STORMWATER ISSUES
THROUGHOUT THE DISTRICT TO
BE ADDRESSED VIA A
COOPERATIVE EFFORT WITH
LOCAL MUNICIPAL PARTNERS.
10,200,000 FY27 Construction, Phase
II
5140 #N/A
13828 STORMWATER MUNICIPALITY
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES THROUGHOUT
THE DISTRICT.
STORMWATER ISSUES
THROUGHOUT THE DISTRICT TO
BE ADDRESSED VIA A
COOPERATIVE EFFORT WITH
LOCAL MUNICIPAL PARTNERS.
10,200,000 FY28 Construction, Phase
II
5140 #N/A
13352 STORMWATER QUALITY GREEN
INFRASTRUCTURE - SMALL GRANT
RAINSCAPING PROGRAM
SMALL GRANT PROGRAM TO
FUND CONSTRUCTION AND
ENCOURAGE THE USE OF
RAINSCAPING TECHNIQUES BY
INDIVIDUAL LANDOWNERS.
PUBLIC PARTICIPATION
RAINSCAPING NEEDED TO
ADDRESS WATER QUALITY OF
STORMWATER RUNOFF.
200,000 FY25 Construction 5110 #N/A
13352 STORMWATER QUALITY GREEN
INFRASTRUCTURE - SMALL GRANT
RAINSCAPING PROGRAM
SMALL GRANT PROGRAM TO
FUND CONSTRUCTION AND
ENCOURAGE THE USE OF
RAINSCAPING TECHNIQUES BY
INDIVIDUAL LANDOWNERS.
PUBLIC PARTICIPATION
RAINSCAPING NEEDED TO
ADDRESS WATER QUALITY OF
STORMWATER RUNOFF.
200,000 FY26 Construction 5110 #N/A
13352 STORMWATER QUALITY GREEN
INFRASTRUCTURE - SMALL GRANT
RAINSCAPING PROGRAM
SMALL GRANT PROGRAM TO
FUND CONSTRUCTION AND
ENCOURAGE THE USE OF
RAINSCAPING TECHNIQUES BY
INDIVIDUAL LANDOWNERS.
PUBLIC PARTICIPATION
RAINSCAPING NEEDED TO
ADDRESS WATER QUALITY OF
STORMWATER RUNOFF.
200,000 FY27 Construction 5110 #N/A
13352 STORMWATER QUALITY GREEN
INFRASTRUCTURE - SMALL GRANT
RAINSCAPING PROGRAM
SMALL GRANT PROGRAM TO
FUND CONSTRUCTION AND
ENCOURAGE THE USE OF
RAINSCAPING TECHNIQUES BY
INDIVIDUAL LANDOWNERS.
PUBLIC PARTICIPATION
RAINSCAPING NEEDED TO
ADDRESS WATER QUALITY OF
STORMWATER RUNOFF.
200,000 FY28 Construction 5110 #N/A
13176 STORMWATER RESILIENCY
PROGRAM FOR FLOOD
MITIGATION
PROVIDE PROPERTY ACQUISITION
FUNDING FOR ACQUISITION AND
REMOVAL OF FLOOD PRONE
STRUCTURES.
STRUCTURES DAMAGED BY
FREQUENT STORMWATER
FLOODING.
3,400,000 FY26 Land Purchase 5140 #N/A
13176 STORMWATER RESILIENCY
PROGRAM FOR FLOOD
MITIGATION
PROVIDE PROPERTY ACQUISITION
FUNDING FOR ACQUISITION AND
REMOVAL OF FLOOD PRONE
STRUCTURES.
STRUCTURES DAMAGED BY
FREQUENT STORMWATER
FLOODING.
3,400,000 FY27 Land Purchase 5140 #N/A
13176 STORMWATER RESILIENCY
PROGRAM FOR FLOOD
MITIGATION
PROVIDE PROPERTY ACQUISITION
FUNDING FOR ACQUISITION AND
REMOVAL OF FLOOD PRONE
STRUCTURES.
STRUCTURES DAMAGED BY
FREQUENT STORMWATER
FLOODING.
3,400,000 FY28 Land Purchase 5140 #N/A
13490 SUGAR CREEK OMCI
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES WITHIN THE
SUGAR CREEK OMCI.
STORMWATER ISSUES IN THE
SUGAR CREEK OMCI TAXING
SUBDISTRICT.
154,288 FY25 Construction, Phase
II
5583 #N/A
Page 10
Detailed Stormwater CIRP Project List
Project
Number Project Name Scope of Work Problem Description Budget
Amount
Financial
Year Task Fund Priority
13198 SUN VALLEY DR #2171 CREEK
BANK STABILIZATION
CONSTRUCT 300 FEET OF CREEK
BANK STABILIZATION.
CREEK EROSION, ALONG MALINE
CREEK NEAR HALLS FERRY BRIDGE.
80,000 FY27 Design Services 5140 0.6
11287 THOROUGHMAN AND CLAY AVE.
STORM SEWER
CONSTRUCT 1,000 FEET OF 12-
INCH TO 30-INCH RCP STORM
SEWER .
BASEMENT AND YARD FLOODING
ALONG CLAY AND
THOROUGHMAN.
365,000 FY27 Design Services 5140 1.13
13471 TREHERNE CT 1566 STORM SEWER CONSTRUCT 160 FEET OF 12-INCH
STORM SEWER AND ONE INLET.
FLOODING AND EROSION 35,000 FY25 Design Services 5140 14.35
13471 TREHERNE CT 1566 STORM SEWER CONSTRUCT 160 FEET OF 12-INCH
STORM SEWER AND ONE INLET.
FLOODING AND EROSION 99,000 FY27 Construction 5140 14.35
13396 TROWBRIDGE RD 15958 STORM
IMPROVEMENTS
CONSTRUCT BERM AND OUTFALL
TO BUILD DETENTION BASIN ON
EXISTING COMMON GROUND.
GARAGE AND YARD FLOODING. 68,000 FY26 Design Services 5140 1.72
13396 TROWBRIDGE RD 15958 STORM
IMPROVEMENTS
CONSTRUCT BERM AND OUTFALL
TO BUILD DETENTION BASIN ON
EXISTING COMMON GROUND.
GARAGE AND YARD FLOODING. 182,000 FY28 Construction 5140 1.72
11270 TWEED DRIVE STORM SEWER
PHASE II
CONSTRUCT 480 FEET OF 15-INCH
TO 36-INCH DIAMETER STORM
SEWER.
STREET AND YARD FLOODING. 245,000 FY27 Construction 5574 0.44
10779 ULENA AVE. #5042 STORM SEWER CONSTRUCT 160 FEET OF 15-INCH
SEWER.
BASEMENT AND YARD FLOODING. 65,000 FY25 Design Services 5140 2.58
10779 ULENA AVE. #5042 STORM SEWER CONSTRUCT 160 FEET OF 15-INCH
SEWER.
BASEMENT AND YARD FLOODING. 184,000 FY27 Construction 5140 2.58
13489 UNIVERSITY CITY OMCI
REIMBURSEMENTS PROGRAM
OFFER STORMWATER GRANTS TO
MUNICIPALITIES WITHIN THE
UNIVERSITY CITY OMCI.
STORMWATER ISSUES IN THE
UNIVERSITY CITY OMCI TAXING
SUBDISTRICT.
498,781 FY25 Construction, Phase
II
5584 #N/A
10790 VILLE TERESA CT. STORM SEWER CONSTRUCT 70 FEET OF 12-INCH
STORM SEWER.
YARD FLOODING AND EROSION. 75,000 FY26 Design Services 5140 1.67
10790 VILLE TERESA CT. STORM SEWER CONSTRUCT 70 FEET OF 12-INCH
STORM SEWER.
YARD FLOODING AND EROSION. 214,000 FY28 Construction 5140 1.67
13293 WARSON ROAD SOUTH 2000
STREAMBANK STABILIZATION
INSTALL HEAVY STONE
REVETMENT TO STABILIZE THE
CREEK BANK.
EROSION. 141,000 FY26 Construction 5566 0.86
11275 WEST FLORISSANT #9315 BANK
STABILIZATION
CONSTRUCT 428 FEET OF 16 FOOT
HIGH BIOSTABILIZATION.
PARKING LOT THREATENED BY
EROSION.
145,000 FY27 Design Services 5140 0.52
13626 WIELAND 5743 STORM SEWER
IMPROVEMENTS
CONSTRUCT 175 FEET OF 12-INCH
STORM SEWER.
OVERLAND FLOODING AT 5743
WIELAND.
45,000 FY25 Design Services 5140 2.83
13626 WIELAND 5743 STORM SEWER
IMPROVEMENTS
CONSTRUCT 175 FEET OF 12-INCH
STORM SEWER.
OVERLAND FLOODING AT 5743
WIELAND.
128,000 FY27 Construction 5140 2.83
13603 WOODFIELD ESTATES DR 1009
STORM SEWER
CONSTRUCT 275 FEET OF 15-INCH
STORM SEWER.
YARD AND BASEMENT FLOODING
AT 1009 WOODFIELD ESTATES
DRIVE.
54,000 FY28 Design Services 5140 1.11
11548 WOODSIDE VILLAGE LN. #973
STORM SEWER
CONSTRUCT 130 FEET OF 12-INCH
RCP STORM SEWER.
EROSION AND YARD FLOODING 26,000 FY28 Design Services 5140 1.06
13363 WYNCREST DR 1308 STORM
IMPROVEMENTS
CONSTRUCT 170 FEET OF 12-INCH
STORM SEWER AND INLET.
YARD FLOODING AND EROSION. 36,000 FY28 Design Services 5140 1.06
13604 YAFFBURY LANE 9515 STORM
SEWER
CONSTRUCT 110 FEET OF 12-INCH
STORM SEWER.
YARD AND BASEMENT FLOODING
AT 9515 YAFFBURY LANE.
31,000 FY26 Design Services 5140 1.95
13604 YAFFBURY LANE 9515 STORM
SEWER
CONSTRUCT 110 FEET OF 12-INCH
STORM SEWER.
YARD AND BASEMENT FLOODING
AT 9515 YAFFBURY LANE.
88,000 FY28 Construction 5140 1.95
159,213,500
Page 11