HomeMy Public PortalAbout13-8677 Purchase Materials for Pump Station 11C Sponsored by: City Manager
Resolution No. 13-8677
A RESOLUTION OF THE CITY COMMISSION OF THE
CITY OF OPA-LOCKA, FLORIDA, AUTHORIZING THE
CITY MANAGER TO PURCHASE MATERIALS FOR PUMP
STATION 11C FROM FERGUSON WATERWORKS, INC., IN
AN AMOUNT NOT TO EXCEED $11,265.51, AND TO
RECEIVE INSTALLATION SERVICES FROM IMECO, INC.,
IN AN AMOUNT NOT TO EXCEED $13,630.00, PAYABLE
FROM ACCOUNT NUMBER 35-535630; A BUDGETED
ITEM; PROVIDING FOR INCORPORATION OF
RECITALS; PROVIDING FOR AN EFFECTIVE DATE
WHEREAS, Pump Station 11C is under construction, and the by-pass system was not
included in construction documents, although Pump Station 11C is in need of a new by-pass
system; and
WHEREAS, six other pump stations currently discharge sewage into Pump Station 11C;
the new by-pass system will by-pass Pump Station 11C and discharge directly into the Force
Main; and
WHEREAS, the City solicited prices, and the lowest, most responsive and responsible
bidders for installation materials for Pump Station 11C were Imeco, Inc. and Ferguson
Waterworks, Inc.; and
WHEREAS, the City will buy the materials from Ferguson Waterworks, Inc., at a cost
not to exceed $11,265.51; and
WHEREAS, the installation service for Pump Station 11C will be provided by Imeco,
Inc., at a cost not to exceed $13,630.00; and
WHEREAS, the City Commission of the City of Opa-locka desires to purchase materials
needed for the installation of the new by-pass system for Pump Station 11C.
NOW, THEREFORE, BE IT DULY RESOLVED BY THE CITY COMMISSION
OF THE CITY OF OPA-LOCKA, FLORIDA:
Section 1. The recitals to the preamble herein are incorporated by reference.
Section 2. The City Commission of the City of Opa-locka, authorizes the City
Manager to purchase materials for Pump Station 11C from Ferguson Waterworks, Inc., in an
amount not to exceed $11,265.51, and award the installation services to Imeco, Inc., in an
amount not to exceed $13,630.00, a budgeted item, payable from Account Number 35-535630.
Section 3. This Resolution shall take effect immediately upon adoption.
PASSED AND ADOPTED THIS 11th day of September, 2013.
YRA 'AYLOR
MAYOR
Attest to: Approved as to form and legal sufficiency:
114 • ll�A� I - _
J'nna Flores Jos:-,e S. eller
City Clerk GI ENS'OON MARDER, PA
Cr Attorney
Moved by: COMMISSIONER HOLMES
Seconded by: COMMISSIONER JOHNSON
Commission Vote: 5-0
Commissioner Holmes: YES
Commissioner Johnson: YES
Commissioner Santiago: YES
Vice-Mayor Kelley: YES
Mayor Taylor: YES
/APP-LOOk4
O
u a
City of Opa-Locka
Agenda Cover Memo
Commission Meeting Item Type: Resolution Ordinance Other
Date: 9/11/2013 (EnterXin box) X
Fiscal Impact: Ordinance Reading: 1st Reading 2nd Reading
(EnterXin box) Yes No (EnterXin box)
x Public Hearing: Yes No Yes No
(EnterXin box) x x
Funding Source: (Enter Fund&Dept) Advertising Requirement: Yes No
35-535630 (EnterXin box) x
Contract/P.O.Required: Yes No RFP/RFQ/Bid#:
(EnterXin box)
Strategic Plan Related Yes No Strategic Plan Priority Area: Strategic Plan Obj./Strategy: (list the
(Enter X in box) specific objective/strategy this item will address)
X Enhance Organizational p
Bus.&Economic Dev (] Will be a cost savings for the
Public Safety - operation of pump station
Quality of Education l] 11C
Qual.of Life&City Image
Communcation 0
Sponsor Name Department: City Manager
City Manager
Short Title:
New By-Pass System at Pump Station 11C
Staff Summary:
Station 11C is the master pump station for the city and receives sewage from the entire city. The installation
of the new by-pass system will eliminate discharge from six pump stations (PS#8, 9, 10, 11A, 11B and 11D)
into station 11C and will discharge directly into the force main. Imeco, Inc. and Ferguson Waterworks, Inc.
are the lowest and most responsive bidders for the installation and materials respectively per the attached
quotes. City will buy the materials from Ferguson Waterworks and the installation will be conducted by
Imeco, Inc. Pump station 11C is currently under construction and the proposed by-pass system was not
included in the construction documents and as a result not in the scope of services for the awarded
contractor.
Staff recommends approval as the by-pass system will increase the master station capacity by 50%+/- by
discharging the flow directly into 11C force main. The operation of pump stations 8,9, 10, 11A, 11B and 11D will
not be dependent on pump station 11C.
z
►Mac me
1. Agenda
2. Quotes for Materials
3. Quotes for Installation
01,p-LOCkq\
� T
F O'
MEMORANDUM °RptE .
To: Mayor Myra L. Taylor
Vice Mayor Joseph L.Kelley
Commissioner Tim I thy Holmes
Commissioner Dor u by Johns;n
Commissioner Luis t. Sant'
FROM: Kelvin L.Baker,City Manag r
DATE: August 26,2013
RE: New By-Pass System at Pump Station 11C
Request:A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF OPA-LOCKA,
FLORIDA AUTHORIZING THE CITY MANAGER TO PURCHASE MATERIALS IN THE
AMOUNT NOT TO EXCEED ELEVEN THOUSAND TWO HUNDRED SIXTY FIVE DOLLARS
AND FIFTY ONE CENTS ($11,265.51) FROM FERGUSON WATERWORS, INC. AND ALSO TO
RECEIVE INSTALLATION SERVICES IN THE AMOUNT NOT TO EXCEED THIRTEEN
THOUSAND SIX HUNDRED THIRTY DOLLARS ($13,630.00) FROM IMECO, INC. AS
REQUIRED FOR THE NEW BY-PASS SYSTEM AT MASTER PUMP STATION 11C PAYABLE
FROM ACCOUNT NUMBER 35-535630.
Description: Station 11C is the master pump station for the city and receives sewage from the
entire city. The installation of the new by-pass system will eliminate discharge from six
pump stations (PS#8, 9, 10, 11A, 11B and 11D) into station 11C and will discharge directly
into the force main. Imeco, Inc. and Ferguson Waterworks, Inc. are the lowest and most
responsive bidders for the installation and materials respectively per the attached quotes.
City will buy the materials from Ferguson Waterworks and the installation will be conducted
by Imeco, Inc. Pump station 11C is currently under construction and the proposed by-pass
system was not included in the construction documents and as a result not in the scope of
services for the awarded contractor.
Account Number: 35-535630
Implementation Timeline: As soon as Possible.
Legislative History: None
Recommendation(s): Staff recommends approval as the by-pass system will increase the master station
capacity by 50%+/- by discharging the flow directly into 11C force main. The operation of pump stations
8,9, 10, 11A, 11B and 11D will not be dependent on pump station 11C.
Analysis: Pump station 11C serves the City and also adjacent sections of unincorporated Miami- Dade
County, and also some nearby areas of the City of Miami Gardens as station 11C receives discharges
from all other stations in the City and transmits sewage into Miami-Dade County Sewer system. The
installation of the new by-pass system will be cost savings for the city as the sewage discharge from
pump stations 8, 9, 10, 11A, 11B and 11D will not be required to pump out second time from 11C. It will
reduce 11C run time and thus less operating cost of the master pump station.
Attachment:
1. Quotes for Materials
2. Quotes for Installation
PREPARED BY: Mohammad Nasir,PE,City Engineer/C1P Director
END OF MEMORANDUM
Mohammad Nasir
Subject: Pump Station 11 By-pass system Material Quote
From: aroddymCa�abpipe.net fmailto:aroddymCaabpioe.netl
Sent: Friday, August 23, 2013 1:16 PM
To: Aroddy Morejon
Subject: Bid S1443946 PO# QUOTE #2
Quotation
Order Date Order Number
A&B PIPE & SUPPLY 08/22/2013 S 1443946
6500 NW 37TH AVENUE ORDER TO:
MIAMI,FL 33147 A&B PIPE&SUPPLY
305-691-5000 Fax 305-696-6810 6500 NW 37TH AVENUE
MIAMI,FL 33147
Phone:305-691-5000
QUOTE TO: SHIP TO:
CITY OF OPA-LOCKA CITY OF OPA-LOCKA
ATTEN: ACCOUNTS PAYABLE !! ATTEN: ACCOUNTS PAYABLE !!
P.O. BOX 540371 P.O. BOX 540371
OPA LOCKA, FL 33054 OPA LOCKA, FL 33054
Customer Number ' Customer Order Number Release Number 1 Salesperson
1942 QUOTE#2 HOUSE SALES
ACCOUNT
Writer Ship Via Terms Expr Date Freight
Allowed
Aroddy Morejon OT OUR TRUCK NET 20TH 10/06/2013 No
Description rd r Net Prc Ext Prc
QtY
12" COMPACT MJ LONG SLEEVE EPDXY 2ea 397.459 794.92
LINED LESS ACCESSORIES C153
(12CMJLSEPDXYLINED)
NON CANCELLABLE&NON RETURNABLE
12" CL350 TYTON DI PIPE EPDXY NEO 40ft 69.388 2775.52
GASKET (12DIEPCL350N)
NON CANCELLABLE &NON RETURNABLE
12" DEZURIK PLUG VALVE#PEC MJ SIDE 2ea 2038.750 4077.50
ACTUATED W/2" OPER NUT EPDXY LINED
SS BOLTS (12PLVALPEC)
NON CANCELLABLE &NON RETURNABLE
12" COMPACT MJ 45 EPDXY LINED LESS 2ea 414.341 828.68
ACCESSORIES C153 (12CMJ45EPDXY)
NON CANCELLABLE &NON RETURNABLE
12" COMPACT MJ EPDXY LINED WYE LESS 2ea 834.953 1669.91
ACCESSORIES C153 (12CMJWYEEPDXY)
1
NON CANCELLABLE &NON RETURNABLE
MEGALUG KIT DI NEOPRENE GASKET 12" 18ea 121.559 2188.06
(12MEGALUGKITNEOPRENE)
************** Kit Components ***************
* 1 - 12" MJ NEOPRENE GASKET
* Loc: 401070300
* 8 - 3/4 X 4" MJ T-BOLTS WITH NUTS TB40
* Loc: 403060200
* 1 - 12" MEGALUG GLAND FOR DI 1112
* Loc: 409100300
*********************************************
12" MEGA FLANGING SYSTEM FOR DI 2ea 291.549 583.10
2112 (211200)
NON CANCELLABLE&NON RETURNABLE
Shipping Instructions: Subtotal 12917.69
Tax *****
This is a quotation only&is valid based on receiving a complete order.Changes in Freight 0.00
qtys and/or materials within the quotation is subject to a re-quote&price change. Handling 0.00
Prices may change due to market conditions.Availability is subject to prior sale.
Taxes extra.' Total 12917.69:
I
2
Mohammad Nasir
From: Ronnie King
Sent: Monday, August 26, 2013 4:00 PM
To: Mohammad Nasir
Subject: Fw: Email Bid#B231670
From: Jonathan Tucker- 1216 POMPANO_WATERWORKS
To: Ronnie King
Sent: Fri Aug 23 16:27:36 2013
Subject: Email Bid# B231670
Price Quotation # B231670
FEI-MIAMI WATERWORKS #1216
10810 S.W.184TH ST.
MIAMI,FL 33157-6737
Phone:786-573-7140
Fax:305-969-0361
Bid No • B231670
Bid Date...: 08/23/13 Cust Phone: 786-338-6900
Quoted By: JT Terms • NET 10TH PROX
Customer.: CITY OF OPA LOCKA Ship To • CITY OF OPA LOCKA
780 FISHERMAN CT 780 FISHERMAN CT
OPA LOCKA,FL 33054 OPA LOCKA,FL 33054
Cust PO#..: Job Name.: QUOTE#2
Item 'Description Quantity Net Price [TM Total
MJLSP4LA12 12 MJ C153 P-401 LONG SLV L/A 1 450.450 EA 450.45
AFT35OPP412 12 CL350 P-401 DI FASTITE PIPE 40` 49.300 FT 1972.00
PLEASE SPECIFY VLV TYPE
Dl18MJGLA12 12 MJ N/LUBE PLUG W/GEAR VLV L/A 2 1 20.260 EA 40.52
MJ4P4LA12— 12 MJ C153 P-401 45 BEND L/A 2 1 433.590 EA 867.18
MJTP4LA12 12 MJ C153 P-401 TEE L/A f 2 634.680 EA 1269.361
PLEASE SPECIFY VLV TYPE
AFC52SCLW12 12 FLG L&W CHK VLV 1 11 3787.140 EA 3787.14
SSLDE12AP 12 DI WDG REST*ONELOK W/A 18 92.180 1 EA 1659.241
MJNEG12 12 MJ NEOP GSKT 18 28.740 EA 517.321
E2112 12 MEGAFLANGE FLG ADPT 2; 351.150 i EA 702.30 I
Subtotal: $11265.51
Inbound Freight: $0.00
Tax: $0.00
Order Total: $11265.51
1
Quoted prices are based upon receipt of the total quantity for immediate shipment(48 hours).SHIPMENTS BEYOND 48
HOURS SHALL BE AT THE PRICE IN EFFECT AT TIME OF SHIPMENT UNLESS NOTED OTHERWISE.Seller not
responsible for delays,lack of product or increase of pricing due to causes beyond our control,and/or based upon Local,State
and Federal laws governing type of products that can be sold or put into commerce.This Quote is offered contingent upon the
Buyer's acceptance of Seller's terms and conditions,which are incorporated by reference and found either following this
document,or on the web at http://wolselevna.com/terms conditionsSale.html.Govt Buyers:All items quoted are open market
unless noted otherwise.
2
IMECO, Inc.
12550 Biscayne B.vd
- North Miami, 33181
Phone: 1786i 691.1496
IMECO, Inc. Fax: 1786)691-1497
E Mail:fdagitaot.com
August 9. 2013
Mr. RONNIE KING
Water Division Supervisor
City of OPA-LOCKA
Public Works & Utilities Department
12950 Le Jleune Boulevard
Opa-Locka, FL 33054
RE: Pump Station 11C Sewer Connection Replacement
IMECO Proposal No.: C-1302
Dear Mr. KING.
Per your request, the following represents our costs estimate to implement the changes necessary to complete the above
referenced sewer connection replacement at Pump Station 11C. This estimate is for Equipment and Labor only as the
City of Opa-Locka will supply the necessary materials:
Mobilization of Equipment: (Backhoe and Skid Steer, Plate Compactor) $650.00 $650.00
Equipment Use: 6 Days of Backhoe and Skid Steer(�} $350.00 $2,100.00 $2.100.00
Labor: 48 crew hours r $125.00/hour $6.000.00 $6,000.00
Demobilization of Equipment $650.00 $650.00
ITEM SUB-TOTAL S9,400.00
IMECO Overhead rd 30% $2,820.00
IMECO Profit ra• 15% $1,410.00
TOTAL S13,630.00
The City of Opa-Locka shall furnish the following materials:
1) Two mechanical joint 12-inch solid sleeve w ith epoxy lining suitable for sewer service
2) Two 20-feet long 12-inch Ductile Iron Pipe with epoxy lining suitable for sewer service
3) Two 12-inch mechanical joint Plug valve
4) Two 45 Degree Elbows with epoxy lining suitable for sewer service
5) Two 12-inch WYE with epoxy lining suitable for sewer service
6) One 12-inch Check Vale
7) 18 Megalug kits
8) Two Megatlanges
9) One 12-inch to 16-inch reducer or one 16-inch run by 12-inch branch Ductile Iron Tee.
Please note that the last item will be verified in the field once we have uncovered the existing sewer main and determine
its actual size. I trust that the above is as required. Should have any questions or require additional information. please
contact the undersigned at your con enience at 954-699-5705.
��JJ''��
Sincerely.
JAi � riel
John Denis
President
C&1 CONSTRUCTION General Contractors
AND DESIGN INC. 14031 SW 143rd Court Unit 6,Miami,Florida
33186
Phone:(305)255-6067 Fax.:(786)430-1747
PROPOSAL/CONTRACT
NAME/ADDRESS DATE PROPOSAL/CONT.
8/22/2013
Mohammad Nasir, P.E
City Engineer PROJECT
City of Opa-Locka
Install insulation valve and force main by-pass
Labor
Scope of Work:
We propose hereby to furnish labor,equipment and material to complete in accordance with specifications:
Installation of two 12" Plug Pipes and Connection at Force Main
ENGINEER'S ESTIMATE OF COST
Item No: Description Unit Quantity
General Conditions
1 Mobilization LS 1
Earthwork and Paving
7 New Asphalt pavement(including Limerock SY 35
base&stabilization)
LABOR
1 12" DI Epoxy pipe LF 40
3 12" MJ Sleeve EA 2
5 12" Megalug MJ EA 20
6 12" MJ regular acc EA 20
10 12" Plug Valve EA 2
12 12"45 Elbow epoxy EA 3
14 12" MJ Wye Epoxy DI EA 2
15 12" MJ Check Valve EA 1
16 12" Flange Adapter EA 1
Equipment
1 Excavator LS 1
2 Backhoe LS 1
3 Van LS 1
4 Concrete Saw LS 1
5 Hand Tools LS 1
Installation of two 12 Plug Pipes and Connection at Force Main Labor RI Page 1 of 2
C&I CONSTRUCTION General Contractors
14031 SW 143rd Court U
AND DESIGN INC. Unit 6,Miami,Florida
33186
Phone:(305)255-6067 Fax. :(786)430-1747
PROPOSAL/CONTRACT
NAME/ADDRESS DATE PROPOSAL/CONT.
8/22/2013
Mohammad Nasir, P.E
City Engineer
City of Opa-Locka PROJECT
Install insulation valve and force main by-pass
Labor
PAYMENT TERMS:
Based upon Applications for Payment,submitted to the Owner/Agent by the Contractor,the Owner/Agent shall make progress payments on account of the Contract Sum to
the Contractor as provided below and elsewhere in this Proposal. Therefore,the Owner/Agent shall make payments to the Contractor as follows: Final retentions of the
balance owed are not allowed.Payments due and unpaid under the Contract Documents shall bear interest from the date payment is due at the following rate:any balance
past thirty(30)days will be subject to 1-2%per month(18%per annual)finance charge with the Owner/Agent paying for all attorneys'fees should collection be necessary.
This ro osal may be withdrawn by C&l Construction and Design Inc.if not accepted within 30 days.
We.ro.ose hereby to furnish material and labor complete in accordance with above specifications,for the sum of:
Authorized Signature:
$ 14,500.00
Carlos Maldonado
(Fourteen Thousand Five Hundred and 00/100 Dollars) Note:This proposal may be withdrawn by us if not accepted within 30 days.
All material is guaranteed to be as specified. All work to be completed in a Acceptance of Proposal
workmanlike manner according to standard practices. Any alteration or
deviation frorn above specification involving extra costs will be executed The above prices,specifications and conditions are satisfactory and are hereby accepted.
only upon written orders,and will become an extra charge over and above You are authorized to do the work as specified.Payment will be made as outlined above.
the estimate. All agreements contingent upon strikes, accidents or delays
beyond our control. Owner to carry fire, tornado and other necessary
insurance. Our workers are fully covered by Workmen's Compensation Signature
Insurance. Date of acceptance
Installation of two 12 Plug Pipes and Connection at Force Main Labor RI Page 2 of 2
JZT UTILITIES INCORPORATED
"General Contractors"
August 23, 2013
Mr. Ronnie King, Water Division Supervisor
Public Works & Utilities Department
City of Opa-Lacka
12950 NW 42nd Avenue
Opa-Lacka, Florida 33054
Phone:305-953-3058
Fax: 305-953-2835
Re: Pump Station 11-C Force main Repair&Modification
Subject: PROPOSAL
Dear Mr. King:
ZJT Utilities, Inc. hereby proposes to render the scope of as discussed at site meeting held on
August 23, 2013. This proposal is based on the schematic provided and includes all required labor
and equipment to prosecute the scope of work as detailed below:
1. Install Owner furnished material for the demolition, replacement and reconfiguration of 12 DIP
discharge from the coupling inside pump station and connecting to existing 12" force main.
Scope includes installation of 1 -12" isolation valve, 1-45 bend and 1-wye
2. Modification to existing 12" force main entering the sanitary man hole at pump station
including installation of 2-12"valve, 1-Wye and 1-45 bend.
The requisite bypass pumping and force main isolation to be performed by other.
JZT Utilities proposed to perform the aforementioned scope of work for a lump sum
$49, 850.00
Forty Nine Thousand, Eight Hundred and Fifty Dollars.
Ciro topher Facey
Senior Project Manager
Broward Office: Dade Office:
2240 NW.72 Way 6600 NW 27°i Avenue Hollywood,
Hollywood,FL 33024 Miami,Florida 33147
Ph:786-768-9405*Fax:954-987-6434 Ph:786-768-9405*
Email:chrisfaceyJZTCgmail.com