HomeMy Public PortalAbout2022-25 Resolution Approving Loram Scannell EAW Negative DeclarationResolution No. 2022-25
April 5, 2022
Member _Albers__ introduced the following resolution and moved its adoption:
CITY OF MEDINA
RESOLUTION NO. 2022-25
RESOLUTION APPROVING THE RESPONSE TO COMMENTS, FINDINGS OF
FACT, AND RECORD OF DECISION FOR THE LORAM/SCANNELL MEDINA
INDUSTRIAL EAW AND MAKING A NEGATIVE DECLARATION REGARDING
THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT
WHEREAS, the city of Medina (the “City”) is a municipal corporation, organized and
existing under the laws of Minnesota; and
WHEREAS, Minnesota Rules 4410.4300 subpart 14, requires that an Environmental
Assessment Worksheet be prepared for projects that involve construction of a new or expansion
of an existing warehousing or light industrial facility equal to or in excess of 300,000 square feet;
and
WHEREAS, on February 1, 2022, the Loram/Scannell Medina Industrial Environmental
Assessment Worksheet (the “EAW”) was completed relating to a proposed project to consist of a
total of approximately 450,000 square feet of office/warehouse uses on the site and new
infrastructure, including water service, sewer, stormwater, streets, and utilities; and
WHEREAS, the City is the Responsible Government Unit for preparing the EAW for the
project pursuant to above-stated Rules; and
WHEREAS, on February 17, 2022 the City submitted a press release to the Crow River
News announcing the completion of the EAW and its availability for public comment; and
WHEREAS, by February 9, 2022, copies of the EAW were distributed to all persons and
agencies on the official Environmental Quality Board (EQB) distribution list and other interested
parties; and
WHEREAS, on February 15, 2022, the EAW was publicly noticed in the EQB Monitor,
commencing the 30-day public comment period; and
WHEREAS, the 30-day comment period ended March 17, 2022 at 4:30 p.m., and the
City accepted and responded to all written comments received in accordance with state
requirements; and
WHEREAS, none of the comments received recommended preparation of an
Environmental Impact Statement (an “EIS) for the project; and
Resolution No. 2022-25 2
April 5, 2022
WHEREAS, the proposed project requires various other land use approvals for which
the City maintains discretion and authority notwithstanding the EAW process or determination
whether an EIS is required; and
WHEREAS, the proposed project is also subject to relevant regulatory authority and
review by various agencies related to mitigating potential environmental impacts during the
review process; and
WHEREAS, the City has prepared a document entitled “Loram/Scannell Industrial
Findings of Fact and Record of Decision” dated March 30, 2022 related to the EAW (the
“Record of Decision”), which is incorporated into this resolution as if fully set forth herein.
NOW, THEREFORE BE IT RESOLVED, by the City Council of Medina, Minnesota that:
1. The EAW was prepared in compliance with the procedures of the Minnesota
Environmental Policy Act and Minnesota Rules, Parts 4410.1000 to 4410.1700.
2. The EAW satisfactorily addressed the environmental issues for which existing
information could have been reasonably obtained.
3. Based on the criteria established in Minnesota Rules 4410.1700, the proposed project
does not have the potential for significant environmental effects.
4. The City adopts the Record of Decision and directs the Planning Director, or their
designee, to maintain and to distribute it in accordance with the EQB rules.
5. Based upon the adopted Record of Decision, the City herby makes a “negative
declaration” as it relates to the EAW and hereby determines that an Environmental
Impact Statement is not required for the proposed project.
Dated: April 5, 2022.
__________________________________
Kathleen Martin, Mayor
ATTEST:
____________________________
Caitlyn Walker, City Clerk
Resolution No. 2022-25 3
April 5, 2022
The motion for the adoption of the foregoing resolution was duly seconded by member
_DesLauriers___ and upon vote being taken thereon, the following voted in favor thereof:
Albers, Cavanaugh, DesLauriers, Martin, Reid
and the following voted against same:
None
Whereupon said resolution was declared duly passed and adopted.
Resolution No. 2022-25 4
April 5, 2022
EXHIBIT A
Legal Description of the Property
That part of the South 1/2 of the Northwest Quarter, Section 11, Township 118, Range 23
described as beginning at the Northwest corner of said South 1/2 of the Northwest Quarter;
thence East along the North line thereof 1485 feet; thence South parallel to the West line thereof
528 feet; thence West parallel to the said North line 1485 feet to an intersection with the West
line thereof; thence North along said West line 528 feet to the point of beginning.
And
The South 250 feet of the Northwest Quarter of the Northwest Quarter, Section 11, Township
118, Range 23.