CITY OF MEDINA
RESOLUTION NO. 97- 31
RESOLUTION GRANTING A PERMIT TO MINNEGASCO
FOR GAS MAIN INSTALLATION
WHEREAS, Minnegasco has made an application to the City requesting permission to a gas
main at Wichita Trail;
NOW, THEREFORE, BE IT RESOLVED that said application be approved in accordance
with the plans and specifications submitted, subject to the following conditions:
1. The street and right of way shall be restored to its original condition upon completion of
installation and applicant shall be liable for settlement or other damage caused by said
installation for a period of one year following completion.
2. All utilities shall be placed in the utility easement using a joint trench.
Dated: August 5, 1997
I/7 07
Joh Ferris, Mayor
Paul Robinson, Clerk -Treasurer
The motion for the adoption of the foregoing resolution was duly seconded by member Hamilton
and upon vote being taken thereon, the following voted in favor thereof:
Ferris, Hamilton, Johnson, and Thies
and the following voted against same: None Absent: Zietlow
Whereupon said resolution was declared duly passed and adopted.
Signed by
Date -2R-q`7
5. Work to start within -5"0
6. Will detouring of traffic be necessary?
"y
' jpymnegasco
City of VI E1 I N �.
nlyc ///f
Permit no.
APPLICATION FOR PERMIT TO
INSTALL UTILITIES OR TO PLACE
UNDERGROUND CONSTRUCTION
Name of party or organization performing work MINNEGASCO.
Address P.O. Box 1165, Mpls., MN 55440-1165 Telephone 32 I- 5 4 Z
1. Nature of work ;gas main installation ❑ gas service installation ❑ other
Type of surface to be disturbed
(Check type) ❑ Gravel ❑ Bituminous ❑ Concrete k'Boulevard
2. Location
Street, avenue and house number
(Additional information attached when necessary)
3. Size and kind of pipe, conduit or cable Z Pi-
Depthfrom surface - ❑ 2.5'feet ± 3`feet + y,
Dimensions of excavation I o oo ± \ ' 4-2- I 1 S7A- 6. '47 ( 55
4. Method of installation or construction (including method of compaction and excavation)
In accordance with procedures described in Minnegasco Operations Manual: Procedures,
Section 500, `Installation'; the most recent edition on file with the permitting authority.
Machine excavation: Yes X No
days and be completed within 10 days thereafter.
t O If so, describe routing:
For MINNEGASCO
(Applic t
�-c
The date when work is completed must be reported to the person designated by municipality.
AUTHORIZATION OF PERMIT
Upon payment of permit fee in the amount of $ and in consideration of the agreement to comply in all
respects with the street or alley excavation ordinances and regulations applicable covering such operations, permission
is hereby granted for the work to be done as described in the above application, said work to be done in accordance with
special precautions required, as hereby stated:
/We s641e t /tZt d f f//// ? .
It is expressly understood that this permit is conditioned upon replacement or restoration of the road surface to its
proper condition in accordance with the appropriate rules and regulations. It is further understood that this permit is
subject to revocation within ten (10) days of receipt of copy of application by the county engineer when the permit is for
work on a county road.
APPROVED
DATE
All requirements shown on reverse side to be complied with.
White copy —applicant. Yellow —Municipality Engineer. Blue —Municipality Street Superintendent.
Form 16 R7/88
RULES PERTAINING TO STREET AND ALLEY EXCAVATIONS
SAFETY
1. Excavations shall be properly protected and identified by barricades and flags in the daytime, and flares, red
lanterns or flashing signals at night.
2. Barricades shall be erected so they provide suitable visibility in all directions.
3. Excavations must be cribbed when necessary, depending upon type of soil, in order to prevent cave-ins.
4. No guys or stays should be attached to trees on right-of-way.
5. Underground construction must be constructed so it will not harm or unnecessarily destroy the root growth of
trees.
ROADWAY
1. Installation of pipe under concrete or high type bituminous pavements shall be done by jacking or boring unless
otherwise authorized by engineer.
2. All backfilling must be placed in 6-inch layers and thoroughly tamped; material must be flush and even with the
road surface when finally in place, unless engineer authorizes alternate method of construction,
3. Finished surface, base, and sub -base of road after excavation and backfill shall be at least equal in stability to
finished surface, base, and sub -base prior to excavation.
4. Concrete pavement shall be replaced according to specifications provided by the engineer.
5. If settlement or excavation caves in within one year of completion date so materials settle (bituminous mat or
concrete base), it shall be restored to its original condition by the holder of this permit.
6. No pole anchors, anchors, braces, or other construction shall be put on roadway shoulder except by special
authorization.
7. There will be no driving onto highway from ditch or driving on shoulders except when authorized by the engineer;
if damage occurs, permit holder will make proper repairs.
8. No machine excavation shall be permitted except when noted in application for permit.
9. Excavations greater than four feet in width at top of trench will not generally be permitted and may be made only
when expressly provided for on the permit.
10. Street may not be closed to traffic unless expressly authorized by the permit.
LIMITATIONS
1. No lugs which will damage the road surface shall be used on equipment traversing road.
2. Roadside shall be cleaned up after work is completed.
3. The permit holder shall notify the municipality issuing the permit and, when applicable, the county engineer
within 24 hours, (Saturdays, Sundays and legal holidays excluded) that the work has been completed and is ready
for final inspection.
4. The county engineer shall notify the applicant of any objection the county may have to the application within 10
days of receiving the permit application.
Nc�-tE. INS-rf.t_.. Pt Po c7 2.!Lrg.c�-co
MAIN la-T cFF RIG k—oF-wAY
bJ I C H 1 TA T FzA 1 t_
$
NOTE:
BORE ALL PAVED STREETS AND DRIVEWAYS
Minimum depth requirements for pneumegopher crossings
of state highways and county roads is 60". Minimum
depth requirement for pneumagopher croeeings of city
streets and township roads le 18". Minimum depth for
parallel installations on state highways and county
rondo is 36". Minimum depth for parallel inet:nllntione
on city streets and township roads in 30".
rNS-Tate:
MINNEGASCO MAIN JOB
a 3�r 7 O - -1
140191 16710 010I°I 11-I°131
MAJOR MINOR SUFFIX
1 II1j1�1
PROJECT LOCATION
1d, 1-1 101 10121 a1 LPJ
WORK ORDER SIZE TYPE
FL T go rTom wAY
T E, Z�P=At9 Sr F!VI=
EXTE.NP ZT2 SoU"Tl i,
37 NJ
t7-P-1 oK.
- 2.41- .1
� SSrz:1
ScALI= : 11=2061
Nr=r�IJCPrN c )
"ONE CALL"
Quadrant
Section
Twp./Range
NaJ
Al-
ItB—Z3
i
Pipe Required 1 000 ± 22-i p., a -Co
Total Pipe 1000 +'
Main will lie ft.+6" below existing grade
PERMITS REQUIRED
St. Hwy. 1,10, SS R.R.
Co. Rd.
City of Mapft-3A
Addition
Map work needed Yes ❑ Noligt
DD# EMP GAS VALVE
Update: Yes ❑ No,lit Yes ❑ NOV
DESIGNED BY S . v 0RA tJ 1 G le-- DATE
TEL. NO. 3ZI - 54Z'/-1 -7-Z9 9%
DESIGN APPROVED
RELEASE FOR CONST.
Mg-) (ji aii 7- z1 -1
P
RNBiz E
O
M
A 101-2,
P
Four 299M n2/97 101773