HomeMy Public PortalAboutORD14317 BILL NO. 2007-144
• SPONSORED BY COUNCILMAN Harvey
ORDINANCE NO. O � 17
AN ORDINANCE OF THE CITY OF JEFFERSON, MISSOURI, AUTHORIZING THE
MAYOR AND CITY CLERK TO EXECUTE CHANGE ORDER 1 TO THE AGREEMENT
WITH LEHMAN CONSTRUCTION FOR THE MISSOURI RIVER INTERCEPTOR PIPE
BRIDGE REPLACEMENT PROJECT.
NOW, THEREFORE, BE IT ENACTED BY THE COUNCIL OF THE CITY OF
JEFFERSON, MISSOURI, AS FOLLOWS:
Section 1. The Mayor and City Clerk are hereby authorized to execute Change
Order 1 to the agreement with Lehman Construction for Missouri River Interceptor Pipe
Bridge Replacement.
Section 2. The Change Order shall be substantially the same in form and content
as that Change Order attached hereto as Exhibit A.
Section 3. This Ordinance shall be in full force and effect from and after the date
• of its passage and approval.
Passed: Approv ZD cq
�"iding Officer Mayor
ATTEST: APPROVED AS T FORM:
�we
City Cie City Counselor
DEPARTMENT OF COMMUNITY DEVELOPMENT
ENGINEERING DIVISION FJAN 9 2008
320 EAST McCARTY STREET I
JEFFERSON CITY, MISSOURI 65101
Shange Order No. One(1) - Revision 1 Project No. 31082 Date: January 21,2008
Job & Location: MISSOURI RIVER INTERCEPTOR PIPE BRIDGE REPLACEMENT
Contractor: Lehman Construction
......................................................................................................................................................................................................................:....................................................................
It is hereby mutually agreed that when this change order has been signed by the contracting parties, the following described changes
in the work required by the contract shall be executed by the contractor without changing the terms of the contract except as herein
stipulated and agreed.
..................................................................................................................................................................................................................................................................................:........
DESCRIPTION OF CHANGES: (See Attached Sheet for Detailed Description/Explanation)
Note: Item numbers prefixed with "EW" (Extra Work)are new line items to the contract.
Quantity in Revised Amount of
Quantity in Change Contract Overrun or
Item No. Description Unit Contract Order Quantity Unit Price Underrun
EW-1 Remove 12" Pipe Piers LS 0 -1 -1 $2,400.00 ($2,400.00)
EW-2 Remove 20" Pipe Piers LS 0 -1 -1 $3,600.00 ($3,600.00)
EW-3 Install HP 14 x 73 Piers LS 0 1 1 $24,820.00 $24,820.00
EW-4 Pile Driving Shoes LS 0 1 1 $2,400.00 $2,400.00
EW-5 Extra Concrete & Steel for Pile Caps LS 0 1 1 $8,370.00 $8,370.00
EW-6 Restocking Fee for Piles LS 0 1 1 $840.00 $840.00
EW-7 Remove & Dispose of Existing 36" Pipe LS 0 1 1 $1,000.00 $1,000.00
CONTRACTORS PROPOSAL FOR THE ABOVE DESCRIBED CHANGES:
e hereby agree to the modifications of the contract as described above and agree to furnish all materials and labor and perform all
rk in connection therewith in accordance with the requirements for similar work in existing contract except as otherwise stipulated
herein, for the following considerations:
Contract Amount- Add $31,430.00 (Thirty One Thousand Four Hundred Thirty Dollars and No Cents)to the Contract
Amount
Contract Time-Add 81 working days to the Contract
STATEMENT OF CONTRACT AMOUNT:
Arnount % Change Time
ORIGINAL CONTRACT $255,430.00 45
PREVIOUS APPROVED CHANGE ORDERS $0.00 0.0% 0
TOTAL THIS CHANGE ORDER $31,430.00 12.3% 81
TOTAL OF ALL CHANGE ORDERS $31,430.00 12.3% 81
CONTRACT AMOUNT TO DATE $286,860.00 126
................................................................................................I.................... . . ........................... ............................................................................................................................
Lehman Construction
l- 07�0t
Contra or Date
Recommended by: 1-16)-08
i
Comm. Develop ent Direc—G eputy Director Date
Verification of Encumbrance: /_ /S- • L
• Finance Date
Accepted by: I - Z5-- r�8
r/Mayor Date
Y
CITY OF JEFFERSON
ATTACHMENT TO CHANGE ORDER NO.1
PROJECT NO.31082
Description of Changes:
Enter the explanation for this change order. Unit C.O.Ouan. Unit Price Unit Total
Item EW-1 - Remove 12"Pipe Piers LS -1 $2,400.00 ($2,400.00)
SCOPE OF WORK:
The work included in this item shall include the furnishing ofall labor,equipment,and material for the removal of
pipe piers to be replaced by driven piles
MEASUREMENT,PAYMENT,and TIME:
This item will be measured by lump sum cost
Item EW-2 - Remove 20"Pipc Piers LS -1 $3,600.00 ($3,600.00)
SCOPE OF WORK:
The work included in this item shall include the furnishing of all labor,equipment,and material for the removal of
pipe piers to be replaced by driven piles
MEASUREMENT,PAYMENT,and TIME:
This item will be measured by lump sum cost
Item EW-3 - Install KHP14x73 Pile LS 1 $24,820.00 $24,820.00
SCOPE OF WORK:
The work included in this item shall include the furnishing of all labor,equipment,and material for the driving of 6
piles
MEASUREMENT,PAYMENT,and TIME:
This item will be measured by lump sum cost
0tem EW4 - Pile Driving Shoes LS 1 $2,400.00 $2,400.00
SCOPE OF WORK:
The work included in this item shall include the furnishing of all labor,equipment,and material for the 6 pile shoes
to be installed.
MEASUREMENT,PAYMENT,and TIME:
This item will be measured by the lump sum cost.
Item EW-5 - Extra Concrete&Steel for Pile Caps LS 1 $8,370.00 $8,370.00
SCOPE OF WORK:
The work included in this item shall include the furnishing of all labor,equipment,and material for the larger pier
caps required for the driven piles.
MEASUREMENT,PAYMENT,and TIME:
This item will be measured by the lump sum cost.
Item EW-6 - Restocking Fee for Piles LS 1 $840.00 $840.00
SCOPE OF WORK:
The work included in this item shall include the furnishing of all labor,equipment,and material for restocking the
piers that will not be required.
MEASUREMENT,PAYMENT,and TIME:
This item will be measured by the lump sum cost.
Item EW-7 - Remove&Dispose of Exixting 36"Pipe LS 1 $1,000.00 $1,000.00
SCOPE OF WORK:
This item will be measured by the lump sum cost to safely remove and salvage the existing aerial pipeline(existing
piers to remain).
&SUREMENT,PAYMENT,and TIME:
V i!ea"wiP be rn 5,swedf by!�U an "'m r,com
AOL
w
AM6
lqw
.v
tLENAIAN
constru+ction Company
PHONE(573)-796-8101
FAX(573)-796-8293
Date: THURSDAY 6TH DECEMBER,2007
Project: JC PIPE BRIDGE JEFFERSON CITY,MO
RE: PRICING FOR DESIGN CHANGE
Eric Seaman,P.E.
A change in the design for the Jefferson City Pipe Bridge has been proposed to change the piling type from
and length as well as the size of the concrete caps on the intermediate piers. The following changes are
addressed below as well as their associated cost difference.
DESCRIPTION PRICE
2- 12"PIPE PILE CONCRETE FILLED WITH REINFORCEMENT -$2400.00
• 2-20"PIPE PILE CONCRETE FILLED WITH REINFORCEMENT -$3600.00
HP 14 X 73 PILE 292' $24,820.00
PILE DRIVING SHOES 8 TOTAL $2400.00
EXTRA CONCRETE FOR CAPS 9.3 CY+720 LBS REBAR $8,370.00
RESTOCKING FEE FOR PIPE PILE $840.00
TOTAL: $30,430.00
Please do not hesitate to contact me with any questions or comments.
Respectfully Submitted,
Nate Haldiman
Lehman Construction LLC
r.
;0C ax§truction Company
PHONE(573)-796-8101
FAX(573)-796-8293
Date: MONDAY 17TH DECEMBER,2007
Project: JC PIPE BRIDGE JEFFERSON CITY,MO
RE: PRICING FOR DEMOLITION
Eric Seaman,P.E.
The following pricing is for substructure demolition of the existing pipe bridge.
DESCRIPTION PRICE
Existing pipe span to be removed and salvaged to the contractor $1,000.00
2-fiftei mediate piet s and pim caps to be removed
8--
—��1lter�t-piers-end-1�e+ e�1 , 9-W---------------------
TE)szALs $9,600.00
e
Please do not hesitate to contact me with any questions or comments.
Respectfully Submitted,
Nate Haldiman
Lehman Construction LLC
•