HomeMy Public PortalAbout110_Doc_DocchangeorderCHANGE ORDER A1A DOCUME':M1'T G701 Distribution to: OWNER ARCHITECT CONTRACTOR FIELD OTHER R PROJECT: Tybee Energy Retrofit TO: Catamount Constructors, Inc 10 Mansell Court East, Suite 150 Roswell, GA 30076 You are directed to make the following changes in this Contract: CHANGE ORDER NUMBER: 02 INITIATION DATE: March 3, 2011 CONTRACT FOR: Renovation CONTRACT DATE: August 20. 2010 Incorporate the following authorized additional/deductive work into the scope of this Contract Agreement 7 Architectural Fee to Explore 1 /z in' /: out $397.00 8 CREDIT for airlock change at Gymnasium ($1,071.00) Total Add This Change ($674.00) Not valid until signed by both the Owner and Contractor. Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time The original (Lump Sum Price) was ........................................... ............................... $ 194,400.00 Net change by previously authorized Change Orders .............. ............................... S 5,748.73 The (Lump Sum Price) prior to this Chan a Order was ...... ............................... S 194,400.00 The (Lump Sum Price) will be cress by this Change Order ....................... ($ 674.00) The new (Lump Sum Price ) including this Change Order will be ....................... S 199,475.00 The Contract Time will b Unchan Authorized: OWNER City of Tybee Island 403 Butler Avenue Tybee Island, GA 31328 By Date :_ 1 O / 1 -- - CONTRACTOR Catamount Constructors. Inc 10 Mansell Court East. Suite 150 Roswell, GA 30076 By: Date: AIA DOCUMENT G701 CHANGF. ORDER APRIL 1978 EDITION AIAX x''1978 THE AME=RICAN INSTITUTE OF ARCHITECTS 1735 NEW YORK AVE., N.W.. WASHINGTON, D.C. 20006701 - 1978